Citations

Full opinion text

MEMORANDUM OPINION AND ORDER RE: FEDERAL DEFENDANT’S MOTION TO DISMISS; WESTLANDS WATER DISTRICT’S & SAN BENITO COUNTY WATER DISTRICT’S MOTION TO DISMISS; SANTA CLARA VALLEY WATER DISTRICT’S MOTION TO DISMISS WANGER, District Judge. In separate pleadings, Federal Defendants, Defendant-Intervenors Santa Clara Valley Water District, Westlands Water District, and San Benito County Water District, move to dismiss Plaintiffs complaint, under Fed.R.Civ.P. 12(B)(1) and 12(B)(6). See Docs. 28, 30, 31. Plaintiff opposes the motions. See Doc. 38. Defendants and Defendant-Intervenors filed reply briefs December 6 and December 9, 2002. See Docs. 43, 44, 46. The motions were heard March 31, 2003 at 10:00 AM. I. BACKGROUND Federal defendants provide the following’ undisputed overview of the Central Valley Project origin and the issues in this suit: The Delta-Mendota Canal (DMC) was constructed by the United States Bureau of Reclamation (Reclamation) as one of the initial features of the Central Valley Project (CVP), authorized by section 2 of the Act of August 26, 1937, 60 Stat. 844. The Tracy Pumping Plant, another of the original CVP facilities, lifts water from the Sacramento-San Joaquin Delta into the DMC where some of the water is conveyed southeasterly about 116 miles to the Mendota Pool on the San Joaquin River and some is diverted west to the San Luis Reservoir. The water is conveyed to the Mendota Pool primarily so Reclamation can perform its water right contract with the Exchange Contractors in which reclamation committed to provide ‘substitute water’ from the DMC in exchange for the Exchange Contractors’ commitments not to divert water from the San Joaquin River pursuant to their senior water rights on that River, thereby allowing reclamation to store water upstream in Millerton Lake behind Fri-ant Dam. Reclamation also entered into CVP water service contracts with districts adjacent to the DMC such as Del Puerto Water District (Del Puerto) ... and its predecessor districts. The water that is diverted from the DMC and conveyed to the San Luis Reservoir is ultimately used by water users in both the San Luis Unit and the San Felipe division of the CVP. The San Luis Unit of the CVP was authorized by the Act of June 3, 1960, 74 Stat. 156. The statute expressly provided in Section 1 that the San Luis Unit was to be constructed, operated and maintained ‘as an integral part of the Central Valley project.’ The San Felipe division of the CVP was authorized by the Act of August 27, 1967, 81 Stat. 173, which, like the San Luis Act, expressly provided that the Division was to be constructed, operated and maintained ‘as an addition to, and an integral part of, the Central Valley project.’ Doc. 28 at 1-2. Del Puerto provides the following undisputed background of the Central Valley Project units: The CVP consists of nine distinct geographic areas known as Divisions. These are: 1) Trinity; 2) Shasta; 3) Sacramento; 4) American River; 5) Delta; 6) Eastside; 7) San Felipe; 8) West San Joaquin, and; 9) Friant. The Delta Division consists of the Delta Cross Channel, the BUREAU’S Tracy Pumping Plant in the South Delta, and the Delta-Mendota Canal. As part of the West San Joaquin Division, the San Luis Unit was authorized in 1960 to be built and operated jointly with the State of California. The San Luis Unit consists of San Luis Dam and Reservoir (joint federal-state facilities), O’Neill Dam, and Forebay (joint federal-state facilities), and related facilities. Doc. 24 ¶ 12 at 4. Del Puerto Water District filed this action for declaratory and injunctive relief on August 1, 2002. Doc. 1. Del Puerto filed its First Amended Complaint October 10, 2002. Doc. 24. Del Puerto avers federal jurisdiction exists under 28 U.S.C. § 1331, 43 U.S.C § 390uu and the APA, 5 U.S.C. § 701 et seq. Id. Del Puerto’s 1953 contract with the Bureau of Reclamation for water delivery service expired February 28, 1994. Since then, Del Puerto has been operating under a series of interim 2-year delivery contracts. In 1992, Congress enacted the Central Valley Improvement Project Act (CVPIA), which in part requires no new water delivery contracts exceed a term of twenty-five years. CVPIA 3404(c), Pub.L. 102-575, 106 Stat. 4600. The Act also requires the government engage in appropriate environmental review prior to renewing any long-term contracts: No such renewals shall be authorized until appropriate environmental review, including the preparation of the environmental impact statement required in section 3409 of this title, has been completed. Contracts which expire prior to the completion of the environmental impact statement required by section 3409 may be renewed for an interim period not to exceed three years in length and for successive interim periods of not more than two years in length until the environmental impact statement required by section 3409 has been finally completed at which time such interim renewal contracts shall be eligible for long-term renewal as provided above. CVPIA 3404(c), Pub.L. 102-575, 106 Stat. 4600. The Bureau of Reclamation (Defendant) is currently negotiating water delivery contracts with Del Puerto and Interve-nor-defendants. These contracts are not expected to near the finalization stage until mid-2004. Doc. 44 at 4. Del Puerto complains defendants must recognize and grant Del Puerto water contract delivery priority, in the to-be-finalized contracts, over contractors in the San Luis Unit of the Central Valley Project (CVP). Del Puerto alleges the San Luis Unit was formed “to receive supplemental water that was in excess of that needed to meet the BUREAU’S obligation to the Exchange Contractors and DMC water service contractors, such as DEL PUERTO.” Doc. 24 ¶ 14 at 4 (emphasis added). Del Puerto, as a DMC contractor, therefore has allegedly enjoyed a “course of dealing,” which creates “federal contract priority” to water over San Luis Unit contractors. Del Puerto contends, [wjater demands for the DMC and San Luis Unit are composed of two separate types: CVP water service contractors and Exchange Contractors. The Exchange Contractors conditionally exchanged their senior water rights to water in the San Joaquin River for a CVP water supply from the Delta. The DMC water service contractors also receive their water supply from the Delta. The DMC contractors and Exchange Contractors began receiving water from the Delta at or about the same time, circa 1951. Doc. 24 ¶ 13 at 4. Del Puerto asserts its original contract “was intended to provide that the total quantity of water available at Mendota Pool and from the Delta-Mendo-ta Canal in excess of the quantity required to meet the Exchange Contract obligation was to be equally apportioned among existing and future Mendota Pool and Delta-Mendota Canal (DMC) contractors only [,] based upon their contract quantity.” Id. ¶ 18 at 6 (emphasis added). Therefore, “by definition and in point of time, the original DEL PUERTO shortage provision contract language excludes apportionment with non-Mendota Pool and/or non-DMC contractors,” such as San Luis Unit contractors. Id. ¶ 18 at 6. Del Puerto’s first claim for relief alleges the Secretary and Regional Directors’ “intended revision to the DEL PUERTO long-term water service contract pursuant to which the BUREAU intends to pro-rate available water supplies equally between DEL PUERTO and San Luis Unit contractors[,] is contrary to the provisions of the DEL PUERTO water service contracts.” Doc. 24 ¶ 31 at this 9. This claim requests an injunction, which would forbid the Bureau from treating the San Luis Unit contractors “on an equal footing with that of Del Puerto.” Id. ¶ 33 at 9. Del Puerto’s second claim for relief is identical to the first claim for relief, except that it requests declaratory relief “concerning the BUREAU’S obligation to apportion the available water supply among the DMC and San Luis Unit contractors.” Id. ¶ 37 at 9. Del Puerto claims declaratory relief is required because it has “exhausted any and all administrative remedies available.” Id. Del Puerto’s third claim for relief alleges the Secretary and Regional Directors’ intended revision “is contrary to state law governing priority of appropriative use.” Doc. 24 ¶ 38 at 10. Del Puerto contends it has appropriated water to beneficial use since 1950, and this use is prior in time to the San Luis Unit contractors. Id. ¶ 39 at 10. Del Puerto alleges this “prior use” entitles it to an absolute priority in time over any “junior appropriator(s).” Id. Del Puerto claims “first in time, first in right” law governing water appropriation rights applies to it through the Bureau’s State Water Control Board permits: The BUREAU obtained its permits to appropriate water for the CVP subject to state law. Under state law, appropriators may only appropriate that water that is put to beneficial use. With the exception of lands not in issue in this action, the Bureau does not put the water appropriated to beneficial use directly, but does so through the use by its contractors. Therefore, the Bureau’s right to water depends solely on its contractors’ beneficial use thereof. In this capacity, the Bureau must apply state water priority principles. Doc. 24 ¶ 40 at 10. Del Puerto requests a temporary, preliminary, and permanent injunction ordering the Bureau to “apportion the available water supply pumped at the Delta among the Exchange Contractors and DMC contractors according to the shortage provisions of the DMC water service contracts that have existed for more than 40 years.” Doc. 24 ¶ 1 at 10-11. Del Puerto requests a declaration that the Bureau “may not satisfy its obligation to the San Luis Unit by apportioning water to the San Luis Unit contractors on the same footing as DEL PUERTO and DMC contractors.” Doc. 24 ¶ 2 at 11. Del Puerto further requests a declaration that the Bureau “holds its water permits subject to state law governing the appropriation of water” and calls for an order that the Bureau “recognize the priority of water rights in accordance with state law.” Id. ¶ 3 at 11. Santa Clara Valley Water District intervened as a Defendant-Intervenor September 9, 2002. Westlands Water District intervened as a Defendant-Intervenor September 24, 2002. San Benito County Water District intervened as a Defendant-Intervenor October 8, 2002. Defendant-Intervenors contend Del Puerto has no greater water delivery priority right than any other CVP contractor. Defendant-Intervenor Santa Clara Valley Water District moves to dismiss based on subject matter jurisdiction, FRCP (b)(1) and failure to state a claim, FRCP 12(b)(6). Doc. 30. Defendant-Intervenors Westlands Water District and San Benito County Water District move to dismiss based on subject matter jurisdiction, FRCP (b)(1) and failure to state a claim, FRCP 12(b)(6). Doc. 31. Federal defendants move to dismiss under Fed.R.Civ.P. 12(b)(6), failure to state a claim upon which relief can be granted. Doc. 28. II. LEGAL STANDARD A. Fed.R. Civ.P. 12(b)(1) Motion to Dismiss, Lack of Subject Matter Jurisdiction Rule 12(b)(1) of the Federal Rules of Civil Procedure allows a motion to dismiss for lack of subject matter jurisdiction. It is a fundamental precept that federal courts are courts of limited jurisdiction. Limits upon federal jurisdiction must not be disregarded or evaded. Owen Equipment & Erection Co. v. Kroger, 437 U.S. 365, 374, 98 S.Ct. 2396, 57 L.Ed.2d 274 (1978). The plaintiff has the burden to establish that subject matter jurisdiction is proper. Kokkonen v. Guardian Life Ins. Co., 511 U.S. 375, 114 S.Ct. 1673, 1675, 128 L.Ed.2d 391 (1994). This burden, at the pleading stage, must be met by pleading sufficient allegations to show a proper basis for the court to assert subject matter jurisdiction over the action. McNutt v. General Motors Acceptance Corp., 298 U.S. 178, 189, 56 S.Ct. 780, 80 L.Ed. 1185 (1936); Fed.R.Civ.P. 8(a)(1). When a defendant challenges jurisdiction facially, all material allegations in the complaint are assumed true, and the question for the court is whether the lack of federal jurisdiction appears from the face of the pleading itself. Thornhill Publishing Co. v. General Telephone Electronics, 594 F.2d 730, 733 (9th Cir.1979); Mortensen v. First Fed. Sav. & Loan Ass’n, 549 F.2d 884, 891 (3d Cir.1977); Cervantez v. Sullivan, 719 F.Supp. 899, 903 (E.D.Cal.1989), rev’d on other grounds, 963 F.2d 229 (9th Cir.1992). A defendant may also attack the existence of subject matter jurisdiction apart from the pleadings. Mortensen, 549 F.2d at 891. In such a ease, the court may rely on evidence extrinsic to the pleadings and resolve factual disputes relating to jurisdiction. St. Clair v. City of Chico, 880 F.2d 199, 201 (9th Cir.1989); Roberts v. Corrothers, 812 F.2d 1173, 1177 (9th Cir.1987); Augustine v. United States, 704 F.2d 1074, 1077 (9th Cir.1983). “No presumptive truthfulness attaches to plaintiffs allegations, and the existence of disputed material facts will not preclude the trial court from evaluating for itself the merits of jurisdictional claims.” Thornhill Publishing, 594 F.2d at 733 (quoting Mortensen, 549 F.2d at 891). Lack of subject matter jurisdiction can be raised at any time by any party. Am. Fire & Cas. Co. v. Finn, 341 U.S. 6, 17-18, 71 S.Ct. 534, 95 L.Ed. 702 (1951). B. Fed.R. Civ.P. 12(b)(6) Motion to Dismiss, Failure to State a Claim A complaint “should not be dismissed unless it appears beyond doubt that plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Van Buskirk v. Cable News Network, Inc., 284 F.3d 977, 980 (9th Cir.2002) (citations omitted); see also Gilligan v. Jamco Dev. Corp., 108 F.3d 246, 249 (9th Cir.1997) (issue is not whether plaintiff will ultimately prevail, but whether claimant is entitled to offer evidence to support the claim). In deciding a motion to dismiss, the court accepts as true all material allegations in the complaint and construes them in the light most favorable to the plaintiff. See Newman v. Sathyavaglswaran, 287 F.3d 786, 788 (9th Cir.2002). The court need not accept as true, allegations that contradict facts which may be judicially noticed. See Mullis v. United States Bankruptcy Ct., 828 F.2d 1385, 1388 (9th Cir.1987). For example, matters of public record may be considered, including pleadings, orders, and other papers filed with the court or records of administrative bodies, see Mack v. South Bay Beer Distributors, 798 F.2d 1279, 1282 (9th Cir.1986), while conclusions of law, conclusory allegations, unreasonable inferences, or unwarranted deductions of fact need not be accepted. See Western Mining Council v. Watt, 643 F.2d 618, 624 (9th Cir.1981); see also Branch v. Tunnell, 14 F.3d 449, 453 (9th Cir.1994) (“[A] document is not ‘outside’ the complaint if the complaint specifically refers to the document and if its authenticity is not questioned.”). Allegations in the complaint may be disregarded if contradicted by facts established by exhibits attached to the complaint. See Durning v. First Boston Corp., 815 F.2d 1265, 1267 (9th Cir.1987). C. Review Under Administrative Procedure Act (“APA”) Under the APA, federal courts can only review whether agency decisions were “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A) (2001). A decision is arbitrary and capricious if the agency: has relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise. O’Keeffe’s, Inc. v. United States Consumer Prod. Safety Comm’n, 92 F.3d 940, 942 (9th Cir.1996) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm, Mut. Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983), and citing Haw. Helicopter Operators Ass’n v. Fed. Aviation Admin., 51 F.3d 212, 214-15 (9th Cir.1995) (quoting Beno v. Shalala, 30 F.3d 1057, 1073 (9th Cir.1994) (quoting Motor Vehicle Mfrs. Ass’n, 463 U.S. at 44, 103 S.Ct. 2856))). Put another way, “if the agency examines the relevant facts and reaches a conclusion that is rationally supported by the facts[,] then its decision is not arbitrary, even if the decision is a ‘stupid’ one.” United States ex rel. Sequoia Orange Co. v. Sunland Packing House Co., 912 F.Supp. 1325, 1341 (E.D.Cal.1995) (quoting Riverbend Farms, Inc. v. Madigan, 958 F.2d 1479, 1487 (9th Cir.1992) (Under APA review, “[s]o long as it explains its reasons, [an agency] may adopt a rule that all commentators think is stupid or unnecessary.”)) (internal citation omitted). “The court will let the agency’s decision stand if the ‘evidence before the agency provided a rational and ample basis for it.’ ” Christopher A. Goelz & Meredith J. Watts, California Practice Guide: Ninth Circuit Civil Appellate Practice ¶ 14:554 (quoting Systech Envtl. Corp. v. E.P.A., 55 F.3d 1466, 1469 (9th Cir.1995)). “Most importantly, ‘review under the arbitrary and capricious standard is narrow, and the reviewing court may not substitute its judgment for that of the agency.’” United States v. Snoring Relief Labs Inc., 210 F.3d 1081, 1085 (9th Cir.2000) (quoting O’Keeffe’s, Inc., 92 F.3d at 942 (citing Marsh v. Or. Natural Res. Council, 490 U.S. 360, 376, 109 S.Ct. 1851, 104 L.Ed.2d 377 (1989))) (alteration marks omitted). D. Judicial Notice “A judicially noticed fact must be one not subject to reasonable dispute in that it is either (1) generally known within the territorial jurisdiction of the trial court or (2) capable of accurate and ready determination by resort to sources whose accuracy cannot reasonably be questioned.” Fed.R.Evid. 201(b) (1984). “A court shall take judicial notice if requested by a party and supplied with the necessary information.” Fed.R.Evid. 201(d) (1984). Judicially noticed facts often consist of matters of public record, such as prior court proceedings, see, e.g., Emrich v. Touche Ross & Co., 846 F.2d 1190, 1198 (9th Cir.1988); administrative materials, see, e.g., Barron v. Reich, 13 F.3d 1370, 1377 (9th Cir.1994); city ordinances, see, e.g., Toney v. Burris, 829 F.2d 622, 626-27 (7th Cir.1987) (holding that federal courts may take judicial notice of city ordinances); official maps, see, e.g., Aiello v. Town of Brookhaven, 136 F.Supp.2d 81, 86 n. 8 (E.D.N.Y.2001) (taking judicial notice of geological surveys and existing land use maps); or other court documents, see, e.g., Rothman v. Gregor, 220 F.3d 81, 92 (2d Cir.2000) (taking judicial notice of a filed complaint as a public record). Federal courts may “take notice of proceedings in other courts, both within and without the federal judicial system, if those proceedings have a direct relation to the matters at issue.” U.S. ex rel Robinson Rancheria Citizens Council v. Borneo, Inc., 971 F.2d 244, 248 (9th Cir.1992). III. ANALYSIS A. Plaintiffs Motion to Strike Defendant’s Declarations or, in the Alternative, Convert Defendant’s 12(b)(6) Motions to a Rule 56 Summary Judgment Motion; Defendants’ Requests for Judicial Notice Plaintiff moves to strike the declarations and exhibits attached to defendant and defendant-intervenor’s requests for judicial notice. Plaintiff claims these declarations and exhibits are “outside the scope of the limited analysis” permitted under Rule 12(b)(6). Doc. 38 at 1. Plaintiff is mistaken. In a rule 12(b)(6) Motion to Dismiss, matters of public record may be considered, including pleadings, orders, and other papers filed with the court or records of administrative bodies, see Mack v. South Bay Beer Distributors, 798 F.2d 1279, 1282 (9th Cir.1986); see also Branch v. Tunnell, 14 F.3d 449, 453 (9th Cir.1994) (“[A] document is not ‘outside’ the complaint if the complaint specifically refers to the document and if its authenticity is not questioned.”). There are two exceptions to the general rule that consideration of extrinsic evidence converts a Rule 12(b)(6) motion to a summary judgment motion. Lee v. City of Los Angeles, 250 F.3d 668, 688 (9th Cir.2001). First, a court may consider material that the plaintiff properly submitted as part of the complaint or, even if not physically attached to the complaint, material that is not questioned as inauthentic and that is necessarily relied upon by the plaintiffs complaint. Id. Second, under Federal Rule of Evidence 201, a court may-take judicial notice of matters of public record. Id. at 689. Some of the documents’ existence and authenticity at issue are not reasonably subject to dispute, e.g., Del Puerto’s Long Term Contract, dated June 10, 1953; Senate and House Reports; water permit applications; State Water Resources Control Board Decisions D-990, D-935 and D~ 1020; a copy of the Bureau’s “Report on the Feasibility of Water Supply Development” for the San Luis Unit CVP; a copy of the Bureau’s “Integrated Key Milestones” distributed to the public by the Department of Interior; and a copy of California Civil Code § 1450, all of which are public or quasi-public records. Those documents are of a type appropriate for judicial notice. See Mir v. Little Co. of Mary Hosp., 844 F.2d 646, 649 (9th Cir.1988) (“In addition to the complaint, it is proper for the district court to ‘take judicial notice of matters of public record outside the pleadings’ and consider them for purposes of the motion to dismiss them.”) (quoting MGIC Indem. Corp. v. Weisman, 803 F.2d 500, 504 (9th Cir.1986), and citing Mack v. South Bay Beer Distrib., 798 F.2d 1279, 1282 (9th Cir.1986)). Defendants’ Motion for Judicial Notice is GRANTED in part and DENIED in part. Judicial Notice is taken of the existence and authenticity of the public and quasi public documents listed. To the extent their contents are in dispute, such matters of controversy are not appropriate subjects for judicial notice. Judicial notice is not taken of the press releases submitted. Plaintiffs motion to strike Defendants’ judicial notice requests and attendant documents is DENIED. Plaintiffs motion to convert defendants’ 12(b)(6) Motion to a Rule 56 Summary Judgment Motion is DENIED. B. Santa Clara Valley Water District’s Motion to Dismiss Santa Clara Valley Water District moves to dismiss Del Puerto’s complaint under Fed.R.CivJP. 12(b)(1) and 12(b)(6). Doc. 30. 1. 12(b)(1) motion a. Mootness claim Santa Clara contends Del Puerto’s First and Second Claims for Relief are based upon long expired contracts and should therefore be dismissed. Doc. 31 at 4-6 citing Complaint, Doc. 24, ¶¶ 32-33. Del Puerto counters that it does not contend its “federal contract priority rights” are based upon its expired long-term contract: Santa Clara asserts that the claim is moot because the original water service contract expired more than eight years before this action was commenced. [Citation omitted]. Santa Clara obviously misunderstands the gravamen of Del Puerto’s claim. The claim is not based on an expired contract. Rather, Del Puerto asserts that the original long-term contract is evidence of the Bureau’s prior conformance with state law. It is further evidence of the parties information, belief, and intent at the time the contracts were signed. Del Puerto does not and did not cast its claims in terms of breach of contract because that is not the nature of the prayer for relief. Nowhere in the First Amended Complaint does Del Puerto assert rights based solely on an expired contract. Doc. 38 at 4: This statement expressly contradicts the language of Del Puerto’s First Amended Complaint, as well as its arguments at Doc. 38 at 3:28-4:2, 5:25-28, 12:15-24, 13:4-6. Del Puerto’s First Amended Complaint states: plaintiff,... holds contractual rights to water from defendant United States of America... for distribution of water from the Central Valley project within the DEL PUERTO service area. A true and correct copy of the most recent long-term water service contract between DEL PUERTO and the BUREAU, Contract No. 14-02-200-922 dated June 10,1953 is attached as exhibit A. (¶ 3 at 2). Paragraph 31 states: “The SECRETARY and REGIONAL DIRECTOR’S intended revision to the DEL PUERTO long-term water service contract pursuant to which the BUREAU intends to pro-rate available water supplies equally... is contrary to the provisions of the DEL PUER-TO water service contract.” Doc. 24, ¶ 31 at 9 (emphasis added). Paragraph 32 states, “DEL PUERTO does not have a plain, speedy or adequate remedy at law in that the DEL PUERTO water service contract provides that the BUREAU shall not be liable in damages for injury resulting from its failure to supply water pursuant to the terms of the contract.” (Emphasis added). Paragraph 33 states: “unless restrained and enjoined, the BUREAU will treat the San Luis Unit contractors on an equal footing with that of DEL PUERTO and fail to apportion water according to the terms of the DEL PUERTO water service contract.” The same language is repeated in Del Puerto’s second claim for relief, except that Del Puerto requests a declaratory judgment. While Del Puerto does not claim Breach of Contract, the language of Del Puerto’s First and Second Claims for Relief, and Del Puerto’s “federal contract priority rights” legal theory, is grounded entirely upon its expired, and now inoperative, 1953 contract and the parties’ performance under that contract. Santa Clara accurately rejoins that Del Puerto’s opposition ignores its own amended complaint and advances three new bases for relief: (1) “dicta from State Water Resources Control Board (“SWRCB”) Decision D-935; (2) this Court’s decision in Westlands Water District ...; and (3) the potential hardship Del Puerto could suffer if this Court were to fail to recognize the unusual legal theory developed by Del Puerto.” Doc. 46 at 6 citing Opposition Brief, Doc. 38 at 11-12. Santa Clara’s reply reiterates its argument that a provisional or interlocutory (non-final) agency decision is not subject to judicial review. This issue is discussed infra at 21-27. Del Puerto relies on 42 U.S.C. § 390uu for jurisdiction, which is discussed and rejected infra at 28. It is difficult, if not impossible, to reconcile Del Puerto’s First Amended Complaint with its Opposition Brief arguments. “To satisfy Article Ill’s standing requirements, a plaintiff must show: (1) it has suffered an injury in fact that is concrete and particularized and is actual or imminent, not conjectural or hypothetical; (2) the injury is fairly traceable to the challenged action of the defendant; and (3) it is likely, as opposed to merely speculative, that the injury will be redressed by a favorable decision.” Friends of the Earth, Inc. v. Laidlaw Environmental Services (TOC), Inc., 528 U.S. 167, 181, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000) citing U.S.C.A. Const. Art. 3, § 2, cl. 1. The Ninth Circuit describes the doctrine of mootness as “the requirement that the controversy remain live even after the plaintiff demonstrates initial standing.” Skysign Intern., Inc. v. City and County of Honolulu, 276 F.3d 1109, 1114 (9th Cir.2002). “As the Supreme Court has recently noted, both standing and mootness are jurisdictional issues deriving from the requirement of a case or controversy under Article III.” Cole v. Oroville Union High School Dist., 228 F.3d 1092 (9th Cir.2000) citing Friends of the Earth, Inc. v. Laidlaw Envtl. Servs. (TOC), Inc., 528 U.S. 167, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000). “The “capable of repetition, yet evading review” exception to mootness applies only when (1) the challenged action is too short in duration to be fully litigated before cessation or expiration, and (2) there is a reasonable expectation that the same complaining party will be subjected to the same action again.” Cole, 228 F.3d at 1098 citing Spencer v. Kemna, 523 U.S. 1, 17, 118 S.Ct. 978, 140 L.Ed.2d 43,(1998); see also Natural Resources Defense Council, Inc. v. Evans, 316 F.3d 904, 911 (9th Cir.2003) (“Government actions fall within the “capable of repetition, yet evading review” exception when (1) the duration of the challenged action is too short to allow full litigation before it ceases, and (2) there is a reasonable expectation that the plaintiffs will be subjected to it again.”) (citing Greenpeace Action v. Franklin, 14 F.3d 1324, 1329 (9th Cir.1992)). Here, the challenged action has not yet occurred. Final contract negotiations have not yet concluded. Even if allegedly unlawful action is threatened; ie., that the Agency, the Department of the Interi- or, will fail to recognize purported vested water rights under state and federal water law to require the government to contract in a particular manner, is to usurp the Agency’s administrative discretion delegated by federal law. See Westlands Water Dist. v. Firebaugh Canal, 10 F.3d 667, 671 (9th Cir.1993) (“judicial deference to an agency’s construction of a statute ‘is particularly important where, as here, Congress has vested broad discretion in an agency to interpret a statute.... ’ ... The Reclamation Act of 1902 grants the Secretary of Interior broad authority ‘to perform any and all acts ... as may be necessary and proper for the purpose of carrying the provisions of this Act into full force and effect.”) Westlands Water Dist. v. Firebaugh Canal, 10 F.3d 667, 671 (9th Cir.1993) citing 43 U.S.C. § 373. This case is directly analogous to the Westlands Water District v. U.S. and Hoopa Valley Tribe, CIV-F-00-7124, where water users sought to enjoin the Secretary of the Interior from signing a Record of Decision (ROD) providing for restoration of the Trinity River through use of the Central Valley Project, based on a claim that the ROD violated NEPA and the ESA and such action was therefor, arbitrary, capricious, and contrary to law. See CIV-F-00-7124, Doc. 85 filed Jan 30, 2001. Such provisional relief was denied as an inappropriate judicial interference with the implementation of the Executive Branch’s administrative discretion. b. Ripeness Claim Santa Clara contends the court lacks jurisdiction to hear Del Puerto’s complaint because the claim is not ripe for review. Doc. 30 at 9-11. The ripeness requirement “is designed ‘to prevent the courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also to protect the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.’ ” Ohio Forestry Ass’n, Inc. v. Sierra Club, 523 U.S. 726, 732-733, 118 S.Ct. 1665, 140 L.Ed.2d 921 (1998) citing Abbott Laboratories v. Gardner, 387 U.S. 136, 148-149, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967). The doctrine “is concerned with whether the initial decision-maker has arrived at a definitive position on the issue that inflicts an actual, concrete injury.” Puget Sound Energy, Inc. v. U.S., 310 F.3d 613, 624-625 (9th Cir.2002) citing Ma v. Reno, 114 F.3d 128, 130 (9th Cir.1997) (quoting Darby v. Cisneros, 509 U.S. 137, 144, 113 S.Ct. 2539, 125 L.Ed.2d 113 (1993)); see also Franklin v. Massachusetts, 505 U.S. 788, 797, 112 S.Ct. 2767, 120 L.Ed.2d 636 (1992) (“The core question is whether the agency has completed its decisionmaking process, and whether the result of that process is one that will directly affect the parties.”). “The Supreme Court has held in other contexts,’ and so [has the 9th circuit], that if an initial agency action may be modified or reversed during administrative reconsideration or review it is rendered non-final while such review is pending.” Puget Sound Energy, Inc. v. U.S., 310 F.3d 613, 624-625 (9th Cir.2002) citing I.C.C. v. Bhd. of Locomotive Engineers, 482 U.S. 270, 284-85, 107 S.Ct. 2360, 96 L.Ed.2d 222(1987); Acura v. Reich, 90 F.3d 1403, 1408-9 (9th Cir.1996). The ripeness doctrine is grounded in the consideration that “it would waste scarce government resources to undertake parallel judicial review under such circumstances.” Puget Sound, 310 F.3d at 624-625 citing Acura, 90 F.3d at 1407. “In deciding whether an agency’s decision is, or is not, ripe for judicial review, the Court has examined both the ‘fitness of the issues for judicial decision’ and the ‘hardship to the parties of withholding court consideration.’ ” Ohio Forestry, 523 U.S. at 733,118 S.Ct. 1665 citing Abbott Laboratories 387 U.S. at 148-149, 87 S.Ct. 1507. Factors to consider are: “(1) whether delayed review would cause hardship to the plaintiffs; (2) whether judicial intervention would inappropriately interfere with further administrative action; and, (3) whether the courts would benefit from further factual development of the issues presented.” Ohio Forestry, 523 U.S. at 733, 118 S.Ct. 1665; see also Puget Sound, 310 F.3d at 624-625 (“The relevant considerations in determining finality are whether the process of administrative decision making has reached a stage where judicial review will not disrupt the orderly process of adjudication” citing Port of Boston Marine Terminal Ass’n v. Rederiaktiebolaget Transatlantic, 400 U.S. 62, 71, 91 S.Ct. 203, 27 L.Ed.2d 203 (1970)). 1) Whether judicial intervention would inappropriately interfere with further administrative action Santa Clara contends Del Puerto’s complaint “asks the court to restrain and enjoin the Bureau from treating Del Puerto in a certain manner in the contract that has yet to be finalized.” Doc. 30 at 8. Del Puerto has no final long-term contract and the negotiations are expected to continue through mid-2004. Del Puerto does not have even a proposed contract; Santa Clara contends, “the court cannot determine whether the proposed long-term contract shortage provisions that the Bureau will present to Del Puerto are contrary to State or Federal law.” Id. at 9. Santa Clara argues immediate judicial review “could also hinder the Bureau’s efforts to refine its policies and further define the exact language that will be included in Del Puerto’s contract.” Id. at 11 citing Ohio Forestry, 523 U.S. at 736, 118 S.Ct. 1665. Santa Clara notes “[t]he purpose of negotiations is to develop ‘mutually agreeable terms and conditions,’ rather than to draft a contract containing language imposed by the courts through an early declaration of the parties positions, rights, and responsibilities.” Doc. 30 at 11:12-15. Any declaratory or injunctive relief could deny the Bureau the opportunity “to revise or even reverse its position as it further consults with its experts and proceeds with the negotiations.” Doc. 30 at 11 citing Pacific Gas and Electric v. State Energy Resources Conservation and Development Comm’n, 461 U.S. 190, 201, 103 S.Ct. 1713, 75 L.Ed.2d 752 (1983). Del Puerto does not address this argument; it reiterates its conclusion that the Bureau’s indication that contractual priority will not be a basis for negotiation is, “for these purposes... a final agency decision.” Doc. 38 at 5:15-19. 2) Whether the court would benefit from further factual development of the issues presented According to Santa Clara, “courts have repeatedly emphasized that that [sic] review should be withheld if further factual development would render an issue more complete.” Doc. 30 at 10 citing Assiniboine, 792 F.2d at 789; Ohio Forestry, 523 U.S. at 737, 118 S.Ct. 1665, 140 L.Ed.2d 921 (1998). Santa Clara argues the action would benefit from further factual development because, once the contract provisions are finally developed, “the court will be able to determine exactly how the Bureau proposes to treat not only Del Puerto, but also the other contractors.” Doc. 30 at 10. Additional information will be available regarding whether, and how, the final long-term contract language differs from the original long-term contract or priorities. Id. at 11. Santa Clara observes, “it is difficult to determine how the court may restrain and enjoin the Bureau from failing to apportion water according to the terms of a contract that is no longer in effect or a contract that has yet to be finalized.” Id. Del Puerto responds that “no further factual development is needed. The facts regarding the development and construction'of the CVP are well-established and not substantially in dispute. The only further factual development still to occur involves the actual water reduction that will occur after full implication of the terms of the CVPIA.” Santa Clara rejoins that Del Puerto has not shown how further factual development is unnecessary. Doc. 44 at 6:6-8. Santa Clara contends “further implementation of the CVPIA .. .will help in resolving this suit,” and more factual detail will be known as negotiations progress. Doc. 44 at 6. Santa Clara clarifies it is not asking the court to wait until the contract is signed, but it is asking for a delay until the contracts are “ready to be executed,” before the court requires the Bureau to include certain terms. Doc. 44 at 6-7. As the parties well know, there are at least sixteen cases pending in this court that implicate evolving implementation of the CVPIA. Four of the cases have been decided on appeal. Three more are on appeal. The additional time will benefit all parties as CVPIA implementation continues to be judicially scrutinized. 3) Whether delayed review would cause hardship to the plaintiffs “To meet the hardship requirement, a litigant must show that ‘withholding review would result in ‘direct and immediate’ hardship and would entail more than possible financial loss.’ ” People of Village of Gambell v. Babbitt, 999 F.2d 403, 408 (1993) quoting Western Oil & Gas Ass’n v. Sonoma County, 905 F.2d 1287, 1290 (9th Cir.1990) cert. denied, 498 U.S. 1067, 111 S.Ct. 784, 112 L.Ed.2d 846 (1991) (quoting Winter v. California Medical Review, Inc., 900 F.2d 1322, 1324 (9th Cir.1989)). Santa Clara asserts Del Puerto does not contend it will suffer immediate hardship or immediate economic loss without judicial review: Del Puerto “will suffer no hardship from a postponement until the terms of the long-term contract are agreed-upon” because it currently receives water under an interim contract. Doc. 30 at 11-12. Without any explanation, Del Puerto responds that it will suffer harm if the issue is not resolved. Del Puerto concludes all parties will suffer harm, “insofar as they will not know their contractual rights and obligations and cannot plan accordingly.” Doc. 38 at 5:13-15. Under Central Delta Water v. United States, 306 F.3d 938 (9th Cir.2002), threatened harm is sufficient to provide standing and jurisdiction: “we agree with those circuits that have recognized that a credible threat of harm is sufficient to constitute actual injury for standing purposes, whether or not a statutory violation has occurred.” Cite at [9]. (p. 20 on net copy). However, Central Delta is distinguishable. There, the government had made specific annual CVP water allocations which the plaintiffs challenged. Although the Plaintiffs had not yet suffered harm in Central Delta, they argued they would suffer harm if the existing water allocations continued. Here, no final agency decision has been made. Del Puerto has provided no explanation as to how it will be harmed without immediate judicial review. In Central Delta, plaintiffs demonstrated that if federal defendants (the Bureau of Reclamation) violated the applicable statute, which the Bureau said it would not do, plaintiffs would be harmed in 16% of the months CVP water was delivered. 2. 12(b)(6) motion Santa Clara’s arguments, which address Del Puerto’s state law claims, replicate federal defendants’ and Westlands Water District/San Benito Water Districts’ arguments. This issue is addressed infra, at 34-42. Del Puerto does not directly address Santa Clara’s 12(b)(6) motion. Doc. 38 at 19:4-6. C. Westlands Water District/San Benito County Water District motion Westlands Water District and San Benito County Water District (“Intervenors”) jointly move to dismiss Del Puerto’s complaint under Fed.R.Civ.P. 12(b)(1) and 12(b)(6). Doc. 31. 1. Intervenors’ 12(b)(1) motion Del Puerto invokes federal jurisdiction, in part, under federal APA review. Doc. 31 at 3. The APA allows for judicial review if an individual has suffered “[a] legal wrong because of agency action, or [is] adversely affected or aggrieved by agency action within the meaning of a relevant statute.” Lujan v. National Wildlife Federation, 497 U.S. 871, 882, 110 S.Ct. 3177, 111 L.Ed.2d 695 (1990) citing 5 U.S.C. § 702; see also Public Citizen v. Department of Transp., 316 F.3d 1002, 1019 (9th Cir.2003). The person claiming a right to sue “must identify some ‘agency action’ that affects him in the specified fashion. Agency action means the whole or a part of an agency rule, order, license, sanction, relief, or the equivalent or denial thereof, or failure to act.” Lujan 497 U.S. at 883, 110 S.Ct. 3177 citing 5 U.S.C. § 551(13). “When review ... is sought not pursuant to specific authorization in the substantive statute, but only under the general review provisions of the APA, the ‘agency action’ in question must be ‘final agency action.’ Lujan, 497 U.S. at 883, 110 S.Ct. 3177 citing 5 U.S.C. § 704 (“Agency action made reviewable by statute and final agency action for which there is no other adequate remedy in a court are subject to judicial review.”). Intervenors contend subject matter jurisdiction does not exist under the APA because there is no “final agency action” to review. Doc. 31 at 3 citing 5 U.S.C. § 704. “Two conditions must be met for agency action to be considered final under the APA.” Montana Wilderness Ass’n., Inc. v. U.S. Forest Service, 314 F.3d 1146, 1150 (9th Cir.2003) citing Ecology Ctr., Inc. v. U.S. Forest Serv., 192 F.3d 922, 925 (9th Cir.1999). “First, ‘the action should mark the consummation of the agency’s decision making process; and [second], the action should be one by which rights or obligations have been determined or from which legal consequences flow.’ ” Montana Wilderness Ass’n., 314 F.3d at 1150 citing Ecology Ctr., Inc. v. U.S. Forest Serv., 192 F.3d 922, 925 (9th Cir.1999) (citing Bennett v. Spear, 520 U.S. 154, 177, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997)). Intervenors argue that a non-finalized contract is not “final agency action” because it cannot be characterized as “the consummation of the agency’s decision making process nor can it be an action affecting rights or obligations that result in legal consequences.” Doc. 31 at 4. Del Puerto argues that the Bureau has come to a “decision” about the priority issue and therefore it is “final” regardless of whether the contract itself is final. Because the contract is still under negotiation, and “has not been offered to Del Puerto for execution,” Defendants contend the process has not been consummated, rights and obligations have not been defined, and there is no final agency action subject to judicial review. Doc. 31 at 4. Del Puerto counters that federal jurisdiction exists because Del Puerto’s claim is “based on Section 8 of the Reclamation Act of 1902 and its mandate that federal reclamation law follow the state law to the extent not inconsistent with the stated objectives of Congress.” Doc. 38 at 3. This basis for jurisdiction applies to plaintiffs Third Claim only. Plaintiffs First and Second claims must have some other source of federal jurisdiction. Del Puerto argues final agency action is not required because: 1) the district court has jurisdiction under the APA through 43 U.S.C. § 390uu (Doc. 38 at 3,5), or, alternatively; 2) the APA requirement of final agency action is waivable. Doc. 38 at 5-6. Despite the fact that Del Puerto invokes APA jurisdiction in its First Amended Complaint, Doc. 24 ¶ 1 at 1-2, Del Puerto now argues the APA is “inapposite.” Doc. 38 at 5:22. Del Puerto avers: “subject matter jurisdiction exists in judicial review of agency action only if the action challenged constitutes final agency action or a statute specifically authorizes judicial review.” Doc. 38 at 5 citing Doc. 31 at 2:8-10 (emphasis added). Del Puerto contends section 390uu, a statute, “specifically authorizes judicial review of the kind sought here. The rights being adjudicated are contract rights and all the parties are contracting parties under Reclamation Law.” Intervenors rejoin that section 390uu does not provide federal jurisdiction because Del Puerto’s claims address ajfuture, unformed contract. The critical portion of 390uu states: “Consent is given to join the United States as a necessary party defendant in any suit to adjudicate, confirm, validate, or decree the contractual rights of a contracting entity and the United States regarding any contract executed pursuant to Federal Reclamation Law.” 43 U.S.C. 390uu (emphasis added). Section 390uu does not provide jurisdiction for any of Del Puerto’s claims; it pertains to executed Federal Reclamation contracts, as Del Puerto admits (Doc. 24 ¶ 31; Doc. 38 at 7:2-13), the disputed future contract under negotiation has not yet been “executed pursuant to Federal Reclamation Law.” Del Puerto argues in the alternative that the final agency action requirement presents no bar to APA jurisdiction because the Bureau has indicated the contractual priority issue is non-negotiable, therefore “further processes with the Bureau by Del Puerto would be futile.” Doc. 38 at 6. Del Puerto states, “if the court... rules that the APA is applicable and that there has not been sufficient ‘final agency action’ under that Act, the court would elevate the exhaustion requirement to the level of the absurd.” Doc. 38 at 7:17-19. Del Puerto relies on Weinberger v. Salfi, 422 U.S. 749, 95 S.Ct. 2457, 45 L.Ed.2d 522 (1975), for the proposition that requiring exhaustion when futile would be a waste of administrative resources. In such a case, “an agency decision may be deemed final before exhaustion of remedies is completed.” Doc. 38 at 6. Intervenors suggest Del Puerto conflates the doctrine of finality with the doctrine of exhaustion. Doc. 46 at 5 n. 5 citing Salfi, 422 U.S. 749, 766, 95 S.Ct. 2457, 45 L.Ed.2d 522 (1975) (“the requirement of finality is ‘something more than simply a codification of the judicially developed doctrine of exhaustion, and may not be dispensed, with merely by a judicial conclusion of futility.’ ”) (emphasis added). Intervenors contend the court must “determine whether the Bureau’s actions are ‘final’ under section 704 before determining whether Del Puerto has fully exhausted the administrative remedies.” Doc. 46 at 5 n. 5. Salfi is inapplicable; that case dealt with a constitutional challenge to a social security provision. The Social Security Administration had made an actual decision to deny social security benefits based on a relationship-duration provision in the benefits statute; the decision had been the subject of one hearing and one appeal. Administrative appeal procedures remained, but because the agency’s decision was based upon a statutory requirement that could not be altered by the agency, the plaintiff did not pursue additional internal review. The Supreme Court held the plaintiff had reached a “sufficiently high level of review to satisfy the Secretary’s administrative needs.” 422 U.S. 749, 766, 95 S.Ct. 2457, 45 L.Ed.2d 522 (1975). The Secretary did not raise a jurisdictional challenge based on “non-exhaustion” and the Court interpreted that “to be a determination by [the Secretary] that for the purposes of [the] litigation the reconsideration determination [was] final. ’ ” Id. at 767, 95 S.Ct. 2457 (emphasis added). The futility and waste of administrative resources of which the Court spoke referred to the fact that the Secretary could not change the statute upon which the decision was based; additional appeals of the decision were truly futile. The legal issue concerned the statute’s constitutionality itself, not the underlying decision. Contrary to plaintiffs contentions, Salfi does not hold that the final agency decision rule under the APA is waivable. Without explanation, Del Puerto contends that waiting for Interior to finalize the contract risks upending water rights of thousands of CVP water users, and that the “rights and obligations of dozens of contractors will be affected retroactively.” Doc. 38 at 7. It also argues the Bureau has had a full opportunity to create a factual record and has no plans to reverse its position, therefore waiting for a finalized contract will not effectuate the exhaustion requirement’s purpose. Doc. 38 at 7:14-21. Intervenors rejoin that a “formal basis for negotiations” document has not yet been released, and Del Puerto has only alleged what the federal defendants are unwilling to include it in the negotiations. Id. There has been no final agency decision. The parties continue to negotiate the contract, which is not anticipated to be signed for another 12-18 months. Del Puerto submits a declaration from William Harrison, the Water District’s manager, which states Del Puerto “has been told” by the Bureau’s Mid-Pacific Regional Director Kirk Rogers that a water priority contract provision “will not be included in the basis for negotiations.” Doc. 42 ¶ 4 at 2. Such an oral expression of negotiating posture simply does not constitute “final agency decision.” Were it so, the courthouse doors would be flung wide open to any number of parties negotiating government contracts as soon as a point in the negotiations went against the non-governmental party. Such an oral expression does not “mark the consummation of the agency’s decision making process,” and it does not determine legal rights or create legal consequences. See Montana Wilderness Ass’n., 314 F.3d at 1150 citing Ecology Ctr., Inc. v. U.S. Forest Serv., 192 F.3d 922, 925 (9th Cir.1999) (citing Bennett v. Spear, 520 U.S. 154, 177, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997)). The Plaintiffs’ position invites an advisory opinion. There is still ample time for Interior to change its negotiating position. A government negotiating “indication” is not final agency action. Del Puerto’s claims are contrary to Ninth Circuit law. 2. Intewenors’ 12(b)(6) motion Intervenors proffer three 12(b)(6) arguments: (1) Del Puerto’s priority claim is based on an expired contract, therefore, even if that contract provided a priority, such a right expired with the contract in 1996; (2) Del Puerto’s “congressional intent/course of dealing” claim is not proved; and, (3) no legal authority exists to support Del Puerto’s state law “appropriative right” claim. Intervenors contend that once Del Puerto’s 1953 contract expired, any rights under it expired. Furthermore, “even if such a right once existed, Del Puerto waived it.” It appears Intervenors also argue that because Del Puerto has not, in its interim contracts, reasserted its supposed priority right under Article 9 of its long-term contract, Del Puerto waived any such right. Doc. 31 at 5. Del Puerto responds that federal contract priority rights have already been recognized in the Westlands decision, which established the Exchange Contractor’s priority over CVP contractors. Doc. 38 at 19:4-24. Del Puerto contends: [t]he Exchange Contractors enjoy a contractual priority to water from the CVP.... the fact that such a priority may stem from a valid threat to exercised preexisting water rights is irrelevant. Because the exchange contractors [sic] substitute water delivered by the CVP is obtained through contract and that water is guaranteed, a federal contract priority does exist within the CVP. Doc. 38 at 19 (emphasis added). Del Puer-to dismisses Intervenors’ waiver argument, stating that it has “repeatedly sought to have contractual priority included in the basis for negotiations.” Doc. 38 at 19:22-24. Del Puerto does not address Interve-nors’ arguments on course of dealing, congressional intent, or the state law claim. Intervenors rejoin that Del Puerto has ignored and not refuted Intervenors’ allegation that whatever contract rights existed in the now-expired long-term contract are gone. Doc. 46 at 7:6-9. Intervenors contend the Bureau has always allocated water among CVP contractors on a pro rata basis and that the congressional document cited by Del Puerto does not show any governmental intent to grant Del Puerto a contractually based priority for CVP water. Doc. 46 at 7. This is inaccurate. As Interve-nors well know, the Bureau makes preferential allocations to certain Exchange Contractors based on contract-based priority recognizing preexisting vested water rights that were exchanged. The judicial decision recognizing such priority is now on appeal. Intervenors reiterate the argument that the Westlands Water District decision does not create a generic “federal contract priority;” Del Puerto is not in the same position as the Exchange Contractors in Westlands Water District. Doc. 46 at 8-9. Intervenor allege Del Puerto has no preexisting water rights, nor is there any precedent for creating federal “contract priority” based on water service under a now-terminated agreement. Finally, Interve-nors contend D-935 is inapplicable as it was an interim-water decision and Del Puerto’s trust concept, whether true or not, does not support a federal contract priority arising from a state water law claim. Doc. 46 at 8-9. Del Puerto’s argument that the West-lands decision constitutes judicial recognition of a generic “federal contract priority right” categorically misstates the West-lands’ holding See infra at 38-89. Del Puerto does not address its First and Second Claims—that Del Puerto continues to enjoy contractually-based rights, arising from a contract that expired eight years ago. D-935 lends no support for Del Puerto’s claims, as addressed infra at 38-39. D. Federal Defendants’ Motion to Dismiss Federal defendants move to dismiss Del Puerto’s complaint under Fed.R.Civ.P. 12(b)(6), Doc. 28, on the grounds that Del Puerto’s water rights arising from their prior contract are neither superior nor inferior to the other San Luis Unit contractors. Doc. 28 at 5. Federal defendants oppose any legal claim to superior water rights based on Del Puerto’s signing water delivery service contracts prior to the other San Luis Unit water districts. Doc. 28 at 9. Defendant proffers the following arguments: 1) no federal policy or legal precedent exists for Del Puerto’s claim, (claims 1 & 2); 2) Del Puerto incorrectly relies upon the Exchange Contractors’ judicially affirmed vested water rights priority (over other CVP users) as an example of applicable federal water rights contract priorities, (claims 1 & 2); and, 3) contracting water districts who apply water to beneficial use do not acquire any appropri-ative federal water rights cognizable under state law, (claim #3). Id. citing Westlands Water District v. United States, 153 F.Supp.2d 1133 (E.D.Cal.2001) and Orff v. United States, CVF-93-5327-OWW, appeal pending, Ninth Circuit No. 00-16922. 1. Del Puerto’s First & Second Claim Federal Defendants contend, “Del Puerto can point to no legal basis for asserting a prior right to DMC water based on Federal law, State law, its expired contract, its interim contracts or any decision of the SWRCB.” Doc. 28 at 10-11. Defendants claim Del Puerto’s implied rebanee on Westlands Water District v. United States, 153 F.Supp.2d 1133 (E.D.Cal.2001), is misplaced. Westlands Water District addresses the relationship between the Bureau’s commitment of CVP water to the Exchange Contractors and the Bureau’s commitment of CVP water to contractors in the San Luis Unit and Fri-ant Units of the CVP. Del Puerto’s status as a CVP contractor is not comparable to the “Exchange Contractors.” Id. at 10. Federal defendants assert their statutory right “to manage the CVP as an integrated whole.” Id. citing Westlands Water District, 153 F.Supp.2d at 1158. Del Puerto admits its claim of a “Federal contract priority” is a “novel legal theory.” Doc. 38 at 11:2-3. It counters however, that the “intent and conduct of the parties during the planning, debate, implementation and operation of the CVP gives rise to an unmistakable inference that a priority did and does exist as between the contracting parties to water debvered by the CVP.” Id. at 11:3-6. Del Puerto argues the conflict must be viewed by examining “the time the CVP was constructed... when initial long-term water service contracts... were signed,” in light of California’s “first in time” water law. Id. at 11:8-12. Del Puerto asserts the federal government evidenced its intent to follow state water priority rights law in its dealing with interim contracts in the Friant Unit and these actions support Del Puerto’s “course of dealing” argument. Doc. 11:13-22 citing SWRCB D-935: “the United States proposes to dispose of this interim water by 6-year contractual arrangements with the foregoing applicants, with priority being determined by the date of application for water service” (Doc. 38 at 11:13-19). Del Puerto argues this statement demonstrates the Bureau recognized “contractual priorities ... from the beginning.” Id. at 11:19-22. The federal government rejoins that discussions regarding interim water contractual arrangements are inadmissible as parole evidence and further that Del Puerto misleads by omitting relevant text of D-935: “the full text states: ‘within the near future certain excess interim waters will be available pending consummation of the total deliveries under long-term contracts. The United States proposes to dispose of this interim water by 6-year contractual arrangements with the foregoing applications.’ ” Doc. 43 at 3:8-19 citing D-935 (emphasis added). As interim contracts for a short term (6 year) water supply, any such priority arrangement has no relevance or comparability to the prior or future long-term contracts to be negotiated. Doc. 43 at 33:15-28. Defendants contend there is no such thing as a “vested federal contract right[ ].” Id. at 4:10-17. Del Puerto suggests Westlands Water District, 153 F.Supp.2d 1133 (E.D.Cal. 2001), recognizes the concept of “federal contract priority.” Id. at 11:23-28,12:1-3. Westlands Water District, which dealt with water priority rights as between the Exchange Contractors and Westlands, which advanced a “no priority” pro rata theory of CVP water service entitlement among all CVP users, does not support Del Puerto’s broad “federal contract priority” legal theory. The relationship between the Exchange Contractors and other CVP water users is unique and distinguishable from the relationship of all other CVP users inter se. The Exchange Contractors have priority water rights to CVP water under a specifically negotiated contract “in which Reclamation committed to provide ‘substitute water’ from the DMC in exchange for the Exchange Contractors’ commitments not to divert water from the San Joaquin River pursuant to their senior water rights on that river, thereby allowing Reclamation to store water upstream in Millerton Lake behind Friant Dam.” Doc. 28 at 2. Del Puerto and the remaining CVP contractors gave up no such senior riparian water rights, which facilitated creation of the CVP, which would justify a right to receive water from the Bureau on a priority basis. CVP contractors purchase water service under a standard government contract, the wording of which is similar in most cases. Doc. 44 at 3:22-24. The contractual relationship between the Exchange Contractors and the Bureau is not based on a generalized “federal contract priority right,” rather, their priority is case-specific. Del Puerto contends federal defendants’ broad discretion to control and maintain the CVP, under federal and state law, should not be “confused” with the “acquisi- tion of water rights.” Doc. 38 at 12:4-25 citing SWRCB D-990. Del Puerto argues its claim “is concerned with the allocation of water based on contractual priority within the CVP,” not with the construction or maintenance of the CVP. Del