OPINION WOLIN, District Judge. INTRODUCTION Plaintiff, the Township of Belleville, brings this suit to challenge the issuance of a finding of no significant impact (FONSI) by defendant, the Federal Transit Administration (FTA). The FTA issued the FONSI to New Jersey Transit (NJT), thereby authorizing the use of federal transportation funds for the construction and design of a project known as the Newark City Subway Extension (subway extension) Vehicle Base Facility (base facility) (jointly, the project). Plaintiff premises its cause of action on the theory that certain federal statutory provisions have not been met by defendants, making the grant of the FONSI illegal. In light of these alleged violations, plaintiff seeks an injunction halting design and construction of the project until the defendants remedy the alleged procedural deficiencies through the preparation of an Environmental Impact Statement (EIS) under the National Environmental Policy Act (NEPA), 42 U.S.C. 4321 et seq., and a Major Investment Study (MIS) under the Intermodal Surface Transportation Efficiency Act (ISTEA), Pub.L. No. 102-240, 105 Stat.1914 (codified as amended in scattered sections of U.S.C.). Plaintiff has named as the FTA’s co-defendants: Gordon Linton, Administrator of the FTA; Thomas J. Ryan, Regional Administrator of the FTA; and Shirley A. DeLibero, Executive Director of NJT. This Opinion addresses a number of motions and cross motions made by the parties, including said motion for preliminary and permanent injunctive relief by plaintiff, summary judgment motions by all parties, and motions to dismiss by defendants De-Libero and the FTA. BACKGROUND Some familiarity with the background of this suit is essential. The Newark City Subway (the subway or NCS) is a light rail system maintained and operated by NJT that serves eleven stations between Franklin Avenue in Belleville and Pennsylvania Station in Newark on a 4.3 mile double track line. The subway operates daily from 4:30 a.m. to 12:30 a.m., provides peak hom’ service on two minute headways, connects to greater than fifty bus routes along the line, and carries over 16,000 passengers each weekday. It operates independently, without a physical connection to any other rail line. The subway opened for service in 1935. Since 1954, all revenue service on the subway has been provided by thirty President’s Conference Committee cars (PCCs), manufactured between 1946 and 1949. Over the years, the fleet has dwindled, and currently only twenty-four active PCCs remain. A minimum of sixteen cars are required in order to maintain the current level of peak period service on the subway. The New Jersey Legislature created NJT as a public corporation in 1979, and on October 14,1980, NJT acquired the former owner of the subway. NJT has operated and maintained the subway ever since. In 1981, NJT commissioned an $18 million program to rehabilitate and refurbish the subway infrastructure and rolling stock, which program was completed in 1988. Modernization of the PCC fleet was designed to extend the fleet’s life approximately ten years. Currently, the PCCs are stored beneath Pennsylvania Station, where the subway maintenance facility is also located. The maintenance facility has one stub-end inspection/repair track. Space limitations in the maintenance facility allow only routine maintenance and minor repairs. More extensive work requires removal and trucking of the PCCs to off-site shops. The structural deterioration of the PCCs has led to considerable difficulty in their upkeep. Among the many problems with the PCCs, major car components are no longer manufactured, the cars have doors on only one side, and the design of the cars does not lend itself to compliance with the accessibility requirements mandated by the Americans with Disabilities Act (ADA). Considering the advanced age of the cars, modification of the PCCS to make them ADA accessible has been determined by NJT to be both structurally unfeasible and economically unwise. Accordingly, NJT intends to replace the PCCs with sixteen new light rail vehicles (LRVs), which comply with ADA requirements and are compatible for use on two other proposed light rail systems, the Hudson-Bergen Light Rail Transit System (HBLRTS) and the Newark-Elizabeth Rail Link (NERL). The acquisition of the LRVs will pose new and different maintenance demands, unable to be met within the limited space of the Pennsylvania Station maintenance facility. A modernization study examined the possibility of expanding and retrofitting the existing facility, but concluded that this was neither feasible nor cost-effective. The study recommended that NJT construct a new base facility to replace the existing one at Pennsylvania Station. The project was first advanced as a component of the NERL. In June, 1993, a NERL Options Study recommended construction of a single vehicle base facility in order to store, service, and maintain both the subway and NERL LRVs. In November, 1994, NJT notified the FTA that a new base facility would be required for the subway, regardless of whether the NERL system was ever constructed. The base facility was thereby advanced as an independent project, and an environmental assessment (EA) and technical report for the base facility, and extension of the Subway to reach it, were prepared in July, 1996. The EA and Technical Report, upon which the issuance of the FONSI was based, detail the project. This Opinion will not duplicate what is already extensively reported upon in those documents. However, the general overview of the planned project is useful, and will be excerpted from the EA here: 1.1 PROPOSED ACTION The Proposed Action is the construction of a vehicle base facility (VBF) for replacement light rail vehicles (LRVs) for the Newark City Subway (NCS), an extension of the NCS tracks to connect with the VBF ..., along with three station options. The Proposed Action would be located in the municipalities of Belleville, Bloomfield, and Newark. The proposed improvements would be located primarily on abandoned industrial land, in existing transportation corridors and on open vacant land. Specific elements would include the following: • Construction of a 0.3 mile (0.48 km) two-track light rail connection from the NCS Franklin Avenue Station to CONRAIL’s Bloomfield Industrial Track (previously the Orange Branch). • Rehabilitation of 0.60 mi (0.96 km) of CONRAIL’s exiting freight only, single-track Bloomfield Industrial Track to a multiple track, 750 volt D.C. overhead electrified and signalized joint-use-freight and light rail transit line from Franklin Avenue in Newark, NJ to the vicinity of Bloomfield Avenue in Bloomfield, NJ. • Construction of a new [Light Rail Transit (LRT) ] grade crossing of Franklin Avenue in Newark. • Reconstruction of existing at-grade freight railroad crossings (at Franklin Street in Belleville, Belmont Avenue in Belleville, and Grove Street in Bloomfield, NJ). • Construction of an LRV maintenance shop and operations center building, storage yard, traction power substation, maintenance-of-way facility, police substation, and employee parking on an approximately 13 to 15 acre (5.3-6.1 ha) tract of vacant industrial property in Belleville and Bloomfield. • Combining of the existing Franklin Avenue and Heller Parkway NCS stations into a single new station. • Optional Intermodal station at Grove Street with park-and-ride facilities and bus transfer facilities in Bloomfield. • Optional walk-on station at Belmont Avenue and Franklin Street in Belleville. • Acquisition of property required for the proposed action. The VBF shop and yard may be constructed initially to accommodate only the required NCS replacement fleet, which is currently estimated to be 16 LRVs. The VBF site (and design concept developed for the VBF) would allow expansion to accommodate a prospective combined NCS/NERL fleet of up to 39 vehicles. No future additional land acquisition is anticipated to accommodate the fleet expansion. (EA, 1-1 to 1-3). The EA states that construction of the base facility would require a level site of approximately thirteen to fifteen acres in order to provide adequate space for the facility, storage yard, and test track. (EA, 2-1). The document notes that such sites “are scarce in the densely built-up area served by the NCS and none exists adjacent to the line.” (EA, 2-1). Two sites were considered for the base facility in the EA: 1) the Nesbitt Street Site, located in Newark between Orange Street and the NJT Morris and Essex Lines, and between Nesbitt Street and Dr. Martin Luther King, Jr., Boulevard; and 2) the Franklin Street Site, bounded by Franklin Street, Belmont Avenue, Bloomfield Avenue, Grove Street, and Watessing Avenue, and located on the Bloomfield/Belleville Township boundary. (EA, 2-1). According to the EA, the Franklin Street site was selected as the preferred location for reasons pertaining to cost and construction. A main factor is the proximity of the existing CONRAIL Bloomfield Industrial Track (freight line), which passes about 400 feet from the northern terminus of the subway at Franklin Avenue. Accordingly, by obtaining rights to use the freight line, access can be established to the base facility site from the subway through the construction of a 0.3 mile two-track rail connection. Further, the availability of -additional vacant land proximate to the proposed site and Bloomfield Avenue, a major feeder bus route, would allow construction of a new bus transfer and park-and-ride terminal station for the subway at Grove Street and Bloomfield Avenue. (EA, 2-1). The Nesbitt Street Site was determined to be unfeasible because it would require extensive retaining wall construction for both the site and access track, and two roadway bridges over the Morris and Essex Lines would have to be lengthened and replaced. Furthermore, a major electrical substation serving the Morris and Essex Lines would require relocation and reconstruction. (EA, 2-1). The EA also considered an unsolicited proposal received by NJT that suggested, constructing the base facility inside the existing loop at Franklin Avenue. This proposal lacked merit due to insufficient space at that site. Tunneling eastward to grade under Raymond Plaza East at Pennsylvania Station to increase underground space for maintenance in the existing shop was also proposed, but was deemed infeasible because the transition from subway to surface could not be physically accommodated in that area. (EA, 2-1). In December, 1996, the FTA issued a finding of no significant impact (FONSI) with regard to the project. NJT asserts that construction on the base facility has already commenced and that investment to date surpasses $15 million. The project total is expected to cost greater than $60 million, a large portion of which will be financed through federal funding. The Townships of Newark and Bloomfield favor the project, however, considerable opposition to the project has been brought by the Township of Belleville. This lawsuit arises as a result. DISCUSSION A. Standing 1. Overview The initial issue confronting a federal court in every case is whether the court has jurisdiction to hear the claim. Steel Co. v. Citizens for a Better Environment, 523 U.S. 83, -, 118 S.Ct. 1003, 1013, 140 L.Ed.2d 210 (1998); Lujan v. Defenders of Wildlife, 504 U.S. 555, 560, 112 S.Ct. 2130, 119 L.Ed.2d 351 (1992). A threshold jurisdictional issue entails the determination of whether plaintiff has standing to bring suit. Steel Co., 523 U.S. at -, 118 S.Ct. at 1016. A “showing of standing ‘is an essential and unchanging’ predicate to any exercise of our jurisdiction.” Florida Audubon Soc’y v. Bentsen, 94 F.3d 658 (D.C.Cir.1996) (quoting Defenders of Wildlife, 504 U.S. at 560, 112 S.Ct. 2130). For purposes of determining standing, the Court “must accept as true all material allegations of the complaint, and must construe the complaint in favor of the complaining party.” Warth v. Seldin, 422 U.S. 490, 501, 95 S.Ct. 2197, 45 L.Ed.2d 343 (1975). The notion of standing includes both the Article III limitation on federal judicial review to “cases” and “controversies” as well as prudential considerations exercised as “part of judicial self-government.” Defenders of Wildlife, 504 U.S. at 560, 112 S.Ct. 2130. Generally speaking, the case or controversy requirement of Article III standing requires at the least three showings: first, that the plaintiff has suffered an “injury in fact” that is (a) “concrete” and “particularized”, and (b) “actual” or “imminent”, not hypothetical or conjectural; second, that the injury is causally connected to the challenged action; and third, that the injury is likely to be redressed by a favorable decision. Steel Co., 523 U.S. at ---, 118 S.Ct. at 1016-17; Bennett v. Spear, 520 U.S. 154, 117 S.Ct. 1154, 1161, 137 L.Ed.2d 281 (1997); Defenders of Wildlife, 504 U.S. at 560-61, 112 S.Ct. 2130. In the Court’s view, plaintiff in this case has little difficulty establishing a ease or controversy. Plaintiff is the Township of Belleville. The alleged injury is the immi-_ nent construction of the project, which will result in rail service within the town’s borders, affecting its citizens personally, as well as their residences and businesses. Among the alleged injuries are noise, air, and visible pollution. Such personal aesthetic and con-servational injuries to residents satisfy the injury in fact requirement. United States v. Students Challenging Regulatory Agency Procedures, 412 U.S. 669, 687, 93 S.Ct. 2405, 37 L.Ed.2d 254 (1973) (SCRAP); Sierra Club v. Morton, 405 U.S. 727, 734, 92 S.Ct. 1361, 31 L.Ed.2d 636 (1972). Further, the township claims that the rail service will pose significant danger to its pedestrians, increase traffic, strike a blow to “civic pride”, and result in a loss of property taxes. If such injuries are established, the Court finds that it would be impossible not to conclude that at least some of these injuries also result in discrete and particularized harm to the township. “To prove causation, a plaintiff seeking the preparation of an EIS must demonstrate that the particularized injury that the plaintiff is suffering or is likely to suffer is fairly traceable to the agency action that implicated the need for an EIS.” Florida Audubon Soc’y, 94 F.3d at 669. Here, plaintiff challenges the issuance of a FONSI by the FTA without an EIS or MIS. The FONSI is a prerequisite to the grant of federal funds. The project cost is expected to exceed $60 million, much of which will be received through federal transportation grants. There is little doubt that, without such funding, the project would not go forward. Cf. Township of Springfield v. Lewis, 702 F.2d 426, 450 (3d Cir.1983) (no standing where there was no evidence that NJDOT would not have continued project without federal monies). Plaintiff has, therefore, also met the causation element of Article III standing. The Supreme Court has noted that, in eases alleging violations of procedural rights, as in a suit challenging the failure to prepare an EIS, a plaintiff need not meet the normal requirement of redressability. Defenders of Wildlife, 504 U.S. at 573 n. 7, 112 S.Ct. 2130. Thus, a plaintiff alleging a procedural violation is not forced to convince the Court that the preparation of an EIS or MIS would cause the agency to halt its plans, or even alter them. Justice Scalia did much to forward this thinking in his influential seventh footnote to the Defenders of Wildlife opinion: There is much truth to the assertion that “procedural rights” are special: The person who has been accorded a procedural right to protect his concrete interests can assert that right without meeting all- thq normal standards for redressability and immediacy. Thus, under our case law, one living adjacent to the site for proposed construction of a federally licensed dam has standing to challenge the licensing agency’s failure to prepare an environmental impact statement, even though he cannot establish with any certainty that the statement will cause the license to be withheld or altered, and even though the dam will not be completed for many years. 504 U.S. at 572 n. 7, 112 S.Ct. 2130; see also Florida Audubon Soc’y, 94 F.3d at 669 (“in EIS suits, a court should not review redress-ability”); Brian J. Gatchel, Informational and Procedural Standing after Lujan v. Defenders of Wildlife, 11 J. LAND USE & ENVTL. L. 75, 106 (1995) (providing a thoughtful discussion of procedural standing and arguing that “courts should utilize footnote seven standing to completely remove redressability as a barrier for procedural plaintiffs”). This Court does not intend to broaden the point made by the Supreme Court. In the quoted footnote from Defenders of Wildlife, Justice Scalia used .the example of “one living adjacent to the site for proposed construction”, thus insuring that the alleged injury would directly impact upon the claimant personally, and making it considerably more difficult for a person seeking to raise a third party’s interests to establish injury and causation. Without seeking to expand on language that is more properly interpreted by our Court of Appeals, this Court simply follows the directive of the Supreme Court in concluding that here, where a township faces the prospect of extension of rail service and the construction of at least a portion of a maintenance facility within its own borders, plaintiff has Article III standing to challenge the FTA’s decision to issue a FONSI without first requiring preparation of an EIS or MIS, notwithstanding plaintiffs inability to satisfy normal redressability requirements, when the other elements of standing are established. In addition to Article III requirements, courts must take into account those prudential limitations on standing “ ‘founded in concern about the proper — and properly limited — role of the courts in a democratic society.’” Bennett v. Spear, 117 S.Ct. at 1161 (citation omitted). Among those limitations, the Supreme Court has interpreted the Administrative Procedure Act (APA), 5 U.S.C. § 702 et seq., “to impose a prudential standing requirement in addition to the requirement[] imposed by Article III of the Constitution.” National Credit Union Admin. v. First Nat’l Bank & Trust Co., 522 U.S. 479, 118 S.Ct. 927, 933, 140 L.Ed.2d 1 (1998). Prudential standing under the APA requires that the “ ‘interest sought to be protected by the complainant [must be] arguably within the zone of interests to be protected or regulated by the statute ... in question.’ ” Id. (quoting Association of Data Processing Service Orgs., Inc. v. Camp, 397 U.S. 150, 153, 90 S.Ct. 827, 25 L.Ed.2d 184 (1970)). Although no clear rule encapsulates the zone of interest test, the Supreme Court has clarified the initial inquiry to be taken: The proper inquiry is simply “whether the interest sought to be protected by the complainant is arguably within the zone of interests to be protected ... by the statute.” Hence in applying the “zone of interests” test, we do not ask whether, in enacting the statutory provision at issue, Congress specifically intended to benefit the plaintiff. Instead, we first discern the interests “arguably ... to be protected” by the statutory provisions at issue; we then inquire whether the plaintiffs interests affected by the agency action in question are among them. Id. 118 S.Ct. at 935 (citation omitted). Accordingly, the Court will examine whether plaintiffs claims satisfy the prudential standing requirement of the APA. 2. The APA In the present case, plaintiff claims a right to judicial review of the FTA’s decision to issue a FONSI pursuant to the APA, 5 U.S.C. § 702, which provides: A person suffering legal wrong because of agency action, or adversely affected or aggrieved by agency action within the meaning of a relevant statute, is entitled to judicial review thereof. The “relevant statute” refers to the statute “whose violation is the gravamen of the complaint.” See National Wildlife Federation, 497 U.S. at 886, 110 S.Ct. 3177. In cases where the action challenged is not made reviewable by statute, the APA authorizes review of “final agency action for which there is no other adequate remedy in court.” 5 U.S.C. § 704; Florida Audubon Soc’y, 94 F.3d at 665. In the present case, the issuance of a FONSI constituted final agency action, see Catron County Bd. of Comm’rs v. U.S. Fish & Wildlife, 75 F.3d 1429, 1434 (10th Cir. 1996), and it appears that judicial review alone will suffice to remedy the plaintiffs alleged injury. Plaintiffs claims that the FTA violated provisions of NEPA and IS-TEA by issuing a FONSI without first requiring an EIS and MIS to be prepared make clear that the relevant statutes are NEPA and ISTEA. 3. NEPA Provisions The National Environmental Policy Act was enacted to declare a national policy which will encourage productive and enjoyable harmony between man and his environment; to promote efforts which will prevent or eliminate damage to the environment and biosphere and stimulate the health and welfare of man; to enrich the understanding of the ecological systems and natural resources important to the Nation; and to establish a Council on Environmental Quality. See Township of Springfield, 702 F.2d at 429 (quoting 42 U.S.C. § 4321(a) (1976)). “Toward this end, Congress imposed ... a substantive obligation upon all federal agencies to balance the environmental considerations and goals of the Congress along with the traditional factors of public interest particular to each agency’s mandate.” Shiffler v. Schlesinger, 548 F.2d 96, 100 (3d Cir.1977); see 42 U.S.C. § 4321(b). The statute requires preparation of a detailed statement, commonly known as an environmental impact statement, for any proposed federal actions “significantly affecting the quality of the human environment”. 42 U.S.C. § 4332. The EIS is to consider (i) the environmental impact of the proposed action, (ii) any adverse environmental affects which cannot be avoided should the proposal be implemented, (in) alternatives to the proposed action, (iv) the relationship between local short-term uses of man’s environment and the maintenance and enhancement of long-term productivity, and (v) any irreversible and irretrievable commitments of resources which could be involved in the proposed action should it be implemented. 42 U.S.C. § 4332(C); See Township of Springfield, 702 F.2d at 429; Catron County, 75 F.3d at 1434. The preparation of an EIS serves two main purposes: (1) “to inject environmental considerations into the federal agency’s deci-sionmaking process,” and (2) “to inform the public that the agency has considered environmental concerns in its decisionmaking process.” Catron County, 75 F.3d at 1434; see Public Interest Research Group v. Federal Hwy. Admin., 884 F.Supp. 876, 885 (D.N.J.1995). The detailed statement requirement has been described as the “heart and soul” of NEPA. Morris County Trust for Historic Preservation v. Pierce, 714 F.2d 271, 275 (3d Cir.1983). It also affords those outside the agency the opportunity to critically evaluate the agency’s actions. See Environmental Defense Fund, Inc. v. Froehlke, 473 F.2d 346, 351 (8th Cir.1972). The Joint FTA/Federal Highway Administration (FHWA) regulations implement NEPA for highway and mass transit projects. See 23 C.F.R. Part 771. As not all proposals for federal funding will “significantly affect the environment,” the regulations describe “three classes of action which prescribe the level of documentation required in the NEPA process.” 23 C.F.R. § 771.115. (a) Class I (EIS s). Actions that significantly affect the environment require an EIS (40 C.F.R. § 1508.27). (b) .Class II (CE s). Actions that do not individually or cumulative have a significant environmental affect are excluded from the requirement to prepare an EA or EIS. (e) Class III (EA s). Actions in which the significance of the environmental impact is not clearly established. All actions that are not Class I or Class II are Class III. All actions in this class require the preparation of an EA to determine the appropriate environmental document required. 23 C.F.R. § 771.115. For each action that is not a CE and “does not clearly require the preparation of an EIS, or where the Administration believes an EA would assist in determining the need for an EIS” an EA is to be prepared. 23 C.F.R. § 771.119. After following numerous steps to inform the public of its action, and after conducting a thorough environmental analysis to determine the potential for social, economic, or environmental impact, if no significant impacts are identified, the applicant is to furnish the administration a copy and recommend a FONSI. The recommendation is thereafter reviewed by the administration and, if adopted, a FONSI will issue, incorporating the EA by reference. 23 C.F.R. § 771.121(a). If the administration determines at any time in the EA process that the action is likely to have a significant impact on the environment, the regulations direct that an EIS will be required. 23 C.F.R. § 771.120(1). (a) NEPA: Standing [14,15] Plaintiffs standing to seek judicial review under the APA of an agency’s decision not to prepare an EIS as required by NEPA is well established. E.g. Township of Lower Alloways Creek v. Public Service Elec. & Gas Co., 687 F.2d 732 (3d Cir.1982); Concord Township v. United States, 625 F.2d 1068 (3d Cir.1980); Shiffler v. Schlesinger, 548 F.2d 96 (3d Cir.1977); Public Interest Research Group v. Federal Hwy., Admin., 884 F.Supp. 876 (D.N.J.1995). “NEPA does create a discrete procedural obligation on governmental agencies to give written consideration of environmental issues in connection with certain major federal actions and a right of action in adversely affected parties to enforce that obligation.” Aberdeen & Rockfish R. Co. v. Students Challenging Regulatory Agency Procedures, 422 U.S. 289, 319, 95 S.Ct. 2336, 45 L.Ed.2d 191 (1975) (SCRAP II). Thus, plaintiff has standing under the APA to seek judicial review of an agency’s failure to prepare an EIS under NEPA. The Court will reserve a zone of interest analysis for the issue of whether plaintiff has standing under the APA to challenge the FTA’s failure to prepare an MIS under IS-TEA. 4. ISTEA Provisions Sections 1024, 1025, and 3012 of ISTEA, Pub.L. 102-240, 105 Stat.1914, amended title 23, U.S.C., and the Federal Transit Act by revising sections 134 and 135 of Title 23 and section 8 of the Federal Transit Act (49 U.S.C. app. 1607) which require a continuing, comprehensive, and coordinated transportation planning process in metropolitan areas and States. Statewide Planning; Metropolitan Planning, 58 Fed.Reg. 58040 (1993). The relevant section of ISTEA states as its purpose the “national interest to encourage and promote the development of transportation systems embracing various modes of transportation in a manner which will efficiently maximize mobility of people and goods within and through urbanized areas and minimize transportation-related fuel consumption and air pollution.” 23 U.S.C. § 134(a). Regulations promulgated pursuant to ISTEA provide that “where the need for a major metropolitan transportation investment is identified, and Federal funds are potentially involved, major investment (corridor or subarea) studies shall be undertaken to develop or refine the plan and lead to decisions by the [metropolitan planning organization], in cooperation with participating agencies, on the design and scope of the investment.” 23 C.F.R. § 450.318(a). The FTA and FHWA are responsible for the policies and procedures relating to metropolitan planning organizations (MPOs) as those acts relate to various funding programs. See 58 Fed.Reg. 58040. The metropolitan transportation planning process is to include “a proactive public involvement process that provides complete information, timely public notice, full public access to key decisions, and supports early and continuing involvement of the public in developing plans.” 23 C.F.R. § 450.316(b)(1). The regulations state that an MIS “shall evaluate the effectiveness and cost-effectiveness of alternative investments or strategies in attaining local, state and national goals and objectives. The analysis shall consider the direct and indirect costs of reasonable alternatives and such factors as mobility improvements; social, economic, and environmental affects; safety; operating efficiencies; land use and economic development; financing; and energy consumption.” 23 C.F.R. § 450.318(e). At a minimum, the MIS is to serve “as input to an environmental impact statement or environmental assessment prepared subsequent to the completion of the study,” 23 C.F.R. § 450.318(f)(1). Such analysis “may lead to decisions that modify the project design and scope assumed in the plan development process.” 23 C.F.R. § 450.318(g). An MIS is to be prepared for major metropolitan transportation investments, defined as “transit improvement of substantial cost that is expected to have a significant effect on capacity, traffic flow, level of service, or mode share at the transportation corridor or subarea scale.” 23 C.F.R. § 450.104. The statutory basis for these regulations is 49 U.S.C. § 5309(e)(2): The Secretary of Transportation may approve a grant or loan under this section for a capital project for a new fixed guideway system or extension of an existing fixed guideway system only if the Secretary decides that the proposed project is— (A) based on the results of an alternatives analysis and preliminary engineering; (B) justified based on a comprehensive review of its mobility improvements, environmental benefits, cost effectiveness, and operating efficiencies; and (C) supported by an acceptable degree of local financial commitment, including evidence of stable and dependable financing sources to construct, maintain, and operate the system or extension. However, the source for the regulations regarding the preparation of an MIS has ■ recently been amended by Section 1308 of the Transportation Equity Act for the 21st Century, P.L. 105-78, 112 Stat. 107 (June 9, 1998), which reauthorizes the highway and transit programs through fiscal year 2003. The amendment provides: The Secretary shall eliminate the major investment study set forth in section 450.318 of title 23, Code of Federal Regulations, as a separate requirement, and promulgate regulations to integrate such requirement, as appropriate, as part of the analyses required to be undertaken pursuant to the planning provisions of title 23 United States Code, and chapter 53 of title 49, United States Code, and the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for Federal-aid highway and transit projects. The scope of the applicability of such regulations shall be no broader than the scope of such section. (a) ISTEA: Standing The issue of standing under the APA to seek judicial review of an agency’s decision not to require an MIS has been largely overlooked, although this must in part be attributed to the relative youth of ISTEA. The opinion coming nearest to addressing the issue comes from our own district. See Town of Secaucus v. United States Dept. of Transp., 889 F.Supp. 779 (D.N.J. 1995), aff'd without opinion, 79 F.3d 1139 (3d Cir.1996). In Secaucus, however, the Court addressed primarily the Article III requirements of standing, and not specifically whether plaintiffs alleged injury fell within the zone of interests arguably- to be protected under ISTEA. Id. at 788-89. Likewise, in Clairton Sportsmen’s Club v. Pennsylvania Turnpike Commission, 882 F.Supp. 455 (W.D.Pa.1995), the Court considered the merits of plaintiffs MIS claim under the APA, but did not address the prudential standing requirement. Id. at 463. A few courts have declined to review an agency’s decision under ISTEA because the act has been held not to provide a private right of action. That conclusion is separate from whether plaintiff in this case has standing to seek review of an agency’s decision not to prepare an MIS under the APA based on an alleged violation of ISTEA. The APA contains “ ‘generous review provisions.’ ” Bennett v. Spear, 117 S.Ct. at 1161 (quoting Clarke v. Securities Industry Ass’n, 479 U.S. 388, 400 n. 16, 107 S.Ct. 750, 93 L.Ed.2d 757 (1987) (other citation omitted)). In order for an injury to be reviewable, it must fall within “the meaning of a relevant statute.” 5 U.S.C. § 702. The relevant statute here is ISTEA and its provisions regarding when an MIS is required. The simple issue is whether plaintiffs interest in requiring an MIS is “‘arguably within the zone of interests’” to be protected by the MIS provisions of ISTEA.. See National Credit Union Admin., 118 S.Ct. at 938. It is irrelevant to the analysis to question whether, in enacting the provisions, “Congress specifically intended to benefit the plaintiff.” Id. 118 S.Ct. at 935. Rather, the Court is to conduct a two part inquiry: first, what interests are arguably to be protected by the statutory and regulatory provisions, and second, whether the plaintiffs interests “affected by the agency action in question are among them.” Id. A consideration of the relevant portions of ISTEA reveals that the Secretary of Transportation is only to approve a grant or loan for a capital project or extension of an existing fixed guideway system if the Secretary concludes that it is “justified based on a comprehensive review of its ... environmental benefits, costs effectiveness, and operating efficiencies”, and “based on the result of an alternatives analysis and preliminary engineering”. 49 U.S.C. § 5309(e)(2)(a-b). The metropolitan transportation planning process is to include “a proactive public involvement process that provides complete information, timely public notice, full public access to key decisions, and supports early and continuing involvement of the public in developing plans.” 23 C.F.R. § 450.316(b)(1). At a minimum, the MIS is to serve “as input to an environmental impact statement or environmental assessment prepared subsequent to the completion of the study” in order to allow appropriate modification of the project. 23 C.F.R. §§ 450.318(f)(1) & 450.318(g). The MIS analysis is to “consider the direct and indirect costs of reasonable alternatives and such factors as ... social, economic, and environmental affects; safety; ... [and] land use and economic development.” 23 C.F.R. § 450.318(c). The import of the MIS requirement appears clear. It protects both local and state interests by insuring local and state officials the ability to participate in a meaningful way in the planning process leading up to projects that will directly affect their interests. Interests sought to be protected include the social, economic, safety, and environmental interests of those impacted by major metropolitan transportation investments receiving federal funds. In the instant matter, plaintiff is the Township of Belleville. Township officials have an interest in requiring the FTA to base its decision on an MIS before it issues a FONSI, which would allow federal funds to flow to a project that will'occur in large part within the plaintiffs borders. Primarily, the interest is one of participation in the planning process. Subsumed in this interest are the plaintiffs interests in insuring that reasonable alternatives be considered and that potential significant impacts of the project be scrutinized. Based upon this inquiry, the Court concludes that the interests raised by plaintiff arguably fall within the zone of interests sought to be protected by the ISTEA provisions. The Court finds further support for its position in the recent amendment of the Transportation Equity Act, P.L. 105-78, 112 Stat. 107, which eliminates the separate MIS requirement, but mandates an MIS, as appropriate, as part of the analysis required under NEPA. Although regulations have yet to be adopted implementing the amendment, the language of the new law would seem to further plaintiffs standing in this case, where plaintiff also seeks to insure that a “hard look” has been taken at the environmental consequences of the action under NEPA. B. Summary Judgment Having determined that plaintiff has standing to bring its suit, the Court next considers the parties’ summary judgment motions. Summary judgment shall be granted if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c); see Hersh v. Allen Prods., Co., 789 F.2d 230, 232 (3d Cir.1986). This is an administrative review case. The Court finds no genuine dispute of material facts in the record and affidavits submitted by the parties. See Clairton Sportsmen’s Club v. Pennsylvania Turnpike Commission, 882 F.Supp. 455, 463 (W.D.Pa.1995). Rather, the parties urge different conclusions based on their characterizations of the same facts. The real issue to be decided summarily is whether and to what degree the FTA complied with the procedural requirements of NEPA and ISTEA. See id. C. Scope of Review Under the APA The scope of review under the APA is described as follows: To the extent necessary to decision and when presented, the reviewing court shall decide all relevant questions of law, interpret constitutional and statutory provisions, and determine the meaning or applicability of the terms of an agency action. The reviewing court shall— (1) compel agency action unlawfully withheld or unreasonably delayed; and (2) hold unlawful and set aside agency action, findings, and conclusions found to be— (A) arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law; (B) contrary to constitutional right, power, privilege, or immunity; (C) in excess of statutory jurisdiction, authority, or limitations, or short of statutory right; (D) without observance of procedure required by law; (E) unsupported by substantial evidence in a case subject to sections 556 and 557 of this title or otherwise reviewed on the record of an agency hearing provided by statute; or (F) unwarranted by the facts to the extent that the facts are subject to trial de novo by the reviewing court. In making the forgoing determinations, the court shall review the whole record or those parts of it cited by a party, and due account shall be taken of the rule of prejudicial error. 5 U.S.C. § 706. In applying these directives, the Third Circuit has repeatedly declined to decide whether the appropriate standard of review to apply to an agency’s decision not to prepare an EIS is an “arbitrary or capricious” standard, or one of “reasonableness.” See State of New Jersey Dep’t of Envtl. Protection and Energy v. Long Island Power Auth., 30 F.3d 403, 415 (3d Cir.1994); Morris County Trust for Historic Preservation v. Pierce, 714 F.2d 271, 278 n. 5 (3d Cir.1983); Township of Springfield v. Lewis, 702 F.2d 426, 436 (3d Cir.1983); Township of Lower Alloways Creek v. Public Service Electric & Gas Co., 687 F.2d 732, 742 (3d Cir.1982). Despite the lack of endorsement for either standard, the Third Circuit has commented on the issue: Some- courts, recognizing that an initial decision to omit the preparation of an Environmental Impact Statement may bypass the direction of NEPA to consider environmental factors “to the fullest extent possible”, have concluded that such a decision must be subject to a more searching judicial inquiry than the review of the merits of agency action after preparation of an impact statement. These courts reason that the National Environmental Protection Act is not merely a full disclosure law but one designed to effect substantive changes, and thus the policy of the Act requires that the decision not to prepare an impact statement should be measured by its reasonableness in the circumstances. That standard of review is far less deferential to the agency than the arbitrary and capricious standard of section 706(2)(A) of the Administrative Procedure Act. ... This court has reserved decision on the appropriate scope of review of a threshold agency decision not to prepare an impact statement. The district courts in this circuit tend to apply the higher standard of reasonableness to such threshold determinations. There is much to be said in favor of subjecting these threshold determinations to the higher scrutiny on review. Concord Township v. United States, 625 F.2d 1068, 1073-74 (3d Cir.1980) (footnotes omitted). Because the FTA’s decision to issue a FONSI in this case passes muster under either standard of review, it is unnecessary for this Court to choose one standard over another. In these circumstances it is appropriate to apply the reasonableness standard, and the FTA’s decision will be upheld absent a showing that it acted unreasonably in issuing a FONSI without requiring an EIS or MIS to be prepared. See Public Interest Research Group 884 F.Supp. at 887 (noting that Third Circuit jurisprudence is controlling and applying the reasonableness standard of review) (citing Lower Alloways Creek, 687 F.2d at 742 (citing Concord Township, 625 F.2d at 1073)). D. The Merits 1. NEPA Plaintiff argues that the FTA’s decision to issue a FONSI violated NEPA. First, plaintiff charges that the plain language of the regulations required an EIS to be prepared for the project. Second,. plaintiff argues that the FONSI should not have been issued because NJT failed to properly examine alternatives to the project and failed to adequately evaluate the environmental impacts of the project. Prior to analyzing the NEPA process, the Court emphasizes its limited role in such inquiry. “NEPA itself does not mandate particular results, but simply prescribes the necessary process.” Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). When conducting its analysis under NEPA, the agency is not required, nor would it be desirable, to elevate environmental concerns over other appropriate considerations. Id. Rather, the requirements of NEPA simply are meant to insure that the “agency, has taken a ‘hard look’ at environmental consequences.” Kleppe v. Sierra Club, 427 U.S. 390, 406, 96 S.Ct. 2718, 49 L.Ed.2d 576 (1976) (citation omitted). If the Court finds that the agency has fulfilled these requirements, the Court must not “ ‘interject itself within the area of discretion of the executive as to the choice of the action to be taken,’ ” but must affirm the agency action chosen. Id. (citation omitted). Were the Court to find a violation of NEPA, however, the matter should be remanded to the agencies. Florida Power & Light Co. v. Lorion, 470 U.S. 729, 744, 105 S.Ct. 1598, 84 L.Ed.2d 643 (1985). (a) Class of Project Plaintiffs main support for its argument that the regulations require an EIS to be prepared is 23 C.F.R. § 771.115(a), which states that “examples of actions that normally required an EIS,” ie., “CLASS I” projects, include: (3) New construction or extension of fixed rail transit facilities (e.g., rapid rail, light rail, commuter rail, automated guideway transit). Plaintiff argues that a plain reading of this regulation requires an EIS: Defendants also rely on the language of the regulations. They point out that actions that do not have significant environmental effects are “CLASS II”, which are categorically excluded from the requirement for an EIS or EA. 23 C.F.R. § 771.115(b). The list of examples of categorical exclusions includes “construction of rail storage and maintenance facilities in areas used predominately for industrial or transportation purposes, where such construction is not inconsistent with existing zoning and where there is no significant noise impact on the surrounding community,” 23 C.F.R. § 771.117(d)(ll), and “track and railbed maintenance and improvements when carried out within the existing right of way,” 23 C.F.R. § 771.117(c)(18). The base facility site is zoned for industry, and the short segment of rail improvement that will be carried out in Belleville will take place within the existing right-of-way owned by Conrail. Thus, the defendants contend that, arguably, the project could have been classified as a categorical exclusion, requiring neither an EIS or EA. The defendants further emphasize that, in order to insure their satisfaction of NEPA, the FTA chose a conservative approach and required an EA for the project according to the regulations defining “CLASS III” projects. Those regulations provide that, where it is not clearly established whether a project proposed for FTA funding will have a significant impact, an EA is to be performed to determine the appropriate environmental document required. 23 C.F.R. § 771.115(c). According to the Court’s reading of the regulations and the record, the FTA acted reasonably in requiring an EA to be prepared. The base facility is to be constructed on a site zoned for industrial purposes. That portion of the project falls squarely within the categorical exception. The upgrading of the Conrail track to two tracks within the right of way would normally also fall within the categorical exclusion, but a question remained as to whether the environmental impacts due to the extension of subway service and increase in activity on the tracks would be significant. Accordingly, the FTA was correct to classify the project as a “Class III” (“[ajctions in which the significance of the environmental impact is not clearly established”) and require an EA to be prepared to determine the appropriate environmental document required. 23 C.F.R. § 771.115(c). (b) EA Conclusions Plaintiff next challenges the finding of the EA that an EIS was not required for the project. Plaintiff argues that the FTA should have required an EIS because the EA failed to consider reasonable alternatives and failed to adequately evaluate likely significant environmental impacts of the project. An EA is intended to “provide sufficient evidence and analysis for determining whether to prepare an environmental impact statement or a finding of no significant impact.” 40 C.F.R. § 1508.9(a)(1). It is to include “brief discussions of the need for the proposal, of alternatives as required by section 102(2)(E), of the environmental impacts of the proposed action and alternatives, and a listing of agencies and persons consulted.” 40 C.F.R. § 1508.9(b). (1) Alternatives The main thrust of plaintiffs inadequate-alternative-analysis argument is that the EA failed to consider grade separation of the project in the Silver Lake area, specifically, at the Belmonb-Franklin crossing. Investigating reasonable alternatives is, without doubt, a primary obligation imposed under NEPA. See 42 U.S.C. § 4332(2)(E). The concept of alternatives under NEPA, however, “must be bounded by some notion of feasibility” and “common sense.” Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 551, 98 S.Ct. 1197, 55 L.Ed.2d 460 (1978). “NEPA’s requirement of a discussion of alternatives ... should be superintended according to a ‘rule of reason.’” Stated another way, “[t]he degree to which an existing alternative should be considered, or indeed whether an alternative should be considered at all, varies with existing circumstances.” The “rule of reason necessarily governs which alternatives the agency must discuss, and the extent to which it must discuss them.” Reasonableness is measured by whether it achieves the goals the Agencies set out to achieve. Clairton Sportsmen’s Club, 882 F.Supp. at 477. When considering lack of examination into an alternative, the Court bears in mind that the appropriate inquiry normally resides within the administrative record, which includes all materials compiled by the agency, and before it, at the time the decision was made. Sierra Club v. Slater, 120 F.3d at 638. While the Court is to view critically post-hoc reasons offered for an agency’s actions or inaction, see National Wildlife Federation v. Hanson, 623 F.Supp. 1539, 1544-45 (E.D.N.C.1985), in some circumstances it may be obvious from the record and entirety of the facts that there was no need for express explanation by the agency. See City Federal Sav. & Loan Ass’n v. Federal Home Loan Bank Bd., 600 F.2d 681, 689 (7th Cir.1979). In the instant case, the Court notes that the defendants considered grade elevation of the entire project from Heller Parkway to the base facility. Grade elevation was found impractical for sound engineering, economic, and environmental reasons. See Plaintiff’s App. 19 (NCS Access Track and Vehicle Base Facility Evaluation of LRT Aerial Alignment). The defendants did not specifically include in the grade elevation-document an analysis of grade separation solely at the Belmont-Franklin crossing. The omission of this analysis, however, is not fatal if reasonable in light of the record. Although it should not be considered plaintiff’s responsibility to suggest alternatives, it should be noted that plaintiff was given ample opportunity to voice its opinions and objections to the project. Despite the availability of the grade separation study, at no point during the preparation of the EA did the plaintiff ask NJT to study the feasibility of grade separation solely at the Belmont-Franklin crossing. More critical to determining the reasonableness of the EA’s omission, however, is the fact that the record indicates that grade separation at the Belmont-Franklin Street crossing is impractical. Plaintiff has offered a half page memorandum, composed by the Township Engineer, which appears to acknowledge that grade separation above the crossing is impractical. PLApp. 20. Thomas J. Herits Memo (“It is our understanding that NJ Transit has already investigated the option of a grade separation over said roadways and concluded it was impractical due to available right-of-way and engineering alignment difficulties”). The Township Engineer goes on to further assert that “after a very preliminary inspection it appears that the option of going under the said roadways may be feasible.” The paragraph offered in support of this conclusion, however, does not address the very problems evident from the record that weighed against elevating the project over the roadways: namely, (1) that the freight right of way is at grade and must remain that way, (2) that without the use of the freight rail, the project would require the construction of two below ground tracks, requiring considerable acquisition or condemnation of private property in Belleville, (3) the technical difficulty facing the realignment of the track and the required curvature beneath the Belleville crossings, (4) the restriction of ingress and egress to the yard, thus compromising intended yard flow and creating congestion in the yard, and (5) the obvious increase in cost. See Plaintiffs App., 19 (NCS Access Track and Vehicle Base Facility Evaluation of LRT Aerial Alignment) at 1-3. Based on these facts of record, the Court cannot find fault with NJT’s failure to examine grade separation further. It must be acknowledged that requiring an agency to investigate an allegedly suitable alternative that is, in reality, not a suitable alternative at all, would contravene all prudence and good sense. The grade separation study prepared, although it did not specifically examine grade separation only at the Belmont-Franklin crossing, provided the agency with adequate information with which it could determine that grade separation was infeasible. In light of the evidence before the agencies, the Court finds the omission of a grade separation analysis regarding the Belmont-Franklin crossing patently reasonable. (2) Environmental Impacts Plaintiff argues that there is a substantial possibility of significant impacts from the project, and that the FTA acted unreasonably in issuing a FONSI for the project based on the EA, without requiring an EIS. The parties spend a good portion of their briefs debating the significance of the project’s impacts. (a) Traffic Plaintiff charges that the project will cause significant traffic congestion in the area around the Belmonb-Franklin signalized intersection. In some circumstances, traffic congestion can amount to significant environmental impact requiring an EIS. See United States v. 27.09 Acres of Land, 760 F.Supp. 345, 351 (S.D.N.Y.1991). According to the full build-out analysis of the EA, the subway would operate on a three-minute headway (one vehicle crossing each 1.5 minutes) during peak hours. (EA at 3-8). The intersection capacity analysis assumes an exclusive LRT phase with 21 seconds of green time for the LRT to cross the street, except at the Franklin Street and Belmont Avenue intersections. Since these intersections are adjacent to each other and operate as one intersection, 30 seconds of green time are allocated for the exclusive LRT phase. This will allow the LRT to cross the intersection without having the intersection blocked by queued vehicles. The traffic mitigation assumes that the LRT grade crossings would use traffic signals and not gates and the LRT vehicles would operate at a maximum speed of 25 miles per hour. (Technical Report at 4-10). Current levels of service at the Belmont-Franklin intersection are classified as “C”. (Technical Report at 4-5 to 4-6). The level of service predicted in 2015 with the no-build alternative remains the same. Without mitigation, the level of service predicted in the full build-out option in 2015 is “F”. With mitigation, the level of service in the full build-out option in 2015 during peak hours is described as “C” in the morning and “D” in the evening. (Technical Report at Table 4-4). The mitigation suggested for the Belmont-Franklin intersection is described in the Table as follows: Change signal timing/phasing cycle length & eliminate four parking spaces south side of Franklin Street east of Belmont Avenue, and two spaces north side of Franklin Street, west of Belmont Avenue. (Technical Report at Table 4-4). Mitigation is discussed more fully in the Technical Report under “Mitigation Plan”: Mitigation measures for the at-grade LRT crossing of Franklin Street and Belmont Avenue have been carefully considered and would result in no significant impacts due to any of the alternatives. The two at-grade crossings are approximately 500 feet (152.4 meters) apart. Together with the signalized intersection of Franklin Street and Belmont Avenue, the two LRT grade crossings form a “triange” of about 250 feet (76 meters) to the southwest. Selected mitigation measures for Options 2 and 3 consist of the following (see Figure 4-3): • Change signal phasing for the intersection of Belmont Avenue/Franklin Street to Accommodate revised traffic movements • Provide left turn/through lane for westbound Franklin Street to southbound Belmont Avenue. • Restrict parking on south side of Franklin Street between Belmont Avenue and Heckel Street and north side of Franklin Street between the two Belmont Avenue approaches. This will provide an additional southbound lane. Replacement parking will be created on Heckel Street in the proposed cul-de-sac and additional replacement off-street parking can be created on Franklin Street north of Belmont Avenue, on land acquired for the VBF. • Signalize all LRT grade crossings: — Franklin Avenue — Franklin Street — Belmont Avenue — Grove Street • Allow right-turns only for westbound traffic on Watehung Avenue • Cul-de-sac Heckel Street at Franklin Street Detailed mitigation measures for all options are listed on Table 4-4; this post-mitigation LOS analysis indicates all intersections operate at the same or an acceptable level of service when compared to existing operation. (Technical Report 4-17 to 4-19). “An EIS need not be done ‘[i]f a mitigation condition eliminates all significant environmental effects.’ ” Virgin Islands Tree BOA v. Witt, 918 F.Supp. 879, 898 (V.I.1996) (citation omitted), affirmed, 82 F.3d 408 (3d Cir.1996); Roanoke River Basin Ass’n v. Hudson, 940 F.2d 58, 62 (4th Cir.1991), cert. denied, 502 U.S. 1092, 112 S.Ct. 1164, 117 L.Ed.2d 411 (1992). “[C]ourts permit the effect of mitigation measures to be considered in determining whether preparation of an EIS is necessary.” Friends of the Earth v. Hintz, 800 F.2d 822, 836 (9th Cir.1986) (citations omitted), affirmed, 800 F.2d 822 (9th Cir.1986). In the present case, the EA submitted to the FTA provides a detailed analysis of the traffic impacts of the project. The mitigation measures were included with the original proposal to the FTA and are comprehensive. They indicate that the project, with mitigation, will not create significant environmental impact even in the full build-out option. The sole impact on level of service in 2015 in the full build-out mode will be to shift the level of service to a “D” from a “C” classification in the peak hours of the evening, which is still acceptable and can not be considered significant. (Technical Report Table 4-4). The reference of the plaintiff to a study conducted for another rail fine and the traffic analysis provided for a retail store in Belle-ville are simply not sufficient to refute the EA’s thorough analysis. Accordingly, the Court finds reasonable the EA’s conclusion that the project will not cause significant environmental impacts in terms of traffic, (b) Pedestrian Safety Plaintiff objects that the project will endanger pedestrians. This argument deserves consideration as it is obvious that rail activity may pose hazards to pedestrians. The difficulty the Court has with plaintiffs position, however, is that the plaintiff offers nothing but its own, and the opinion of its engineer, final conclusion that such action poses any likelihood of significant environmental impact. Plaintiff and its expert offer no additional studies to support its conclusion. Rather, it relies on the very EA and Technical Report utilized by the FTA in making its decision, but reaches an opposite determination. “The burden of establishing substantial environmental issues is on the Plaintiffs.” Public Interest Research Group, 884 F.Supp. at 888 (citing Lower Alloways Creek, 687 F.2d at 742 n. 24). “ ‘An agency’s careful evaluation of the impact of its proposed action, its collection and review of evidence, and its reasoned conclusions as to what the dat[a] reveals would be for naught if by simply filing suit and supplying an affidavit by a hired expert, predicated upon the same facts relied upon by the agency but reaching a different conclusion, a litigant could create a controversy necessitating an EIS.’ ” Id. at 891 (quoting Greenpeace Action v. Franklin, 14 F.3d 1324, 1335 (9th Cir.1992)). Further, “[b]ecause analysis of the relevant documents ‘requires a high level of technical expertise,’ ” some deference should be accorded “ ‘the informed discretion of the responsible federal agencies.’” Marsh v. Oregon Natural Resources Council, 490 U.S. 360, 109 S.Ct. 1851, 104 L.Ed.2d 377 (1989)(quoting Kleppe v. Sierra Club, 427 U.S. 390, 412, 96 S.Ct. 2718, 49 L.Ed.2d 576 (1976)). In contrast to plaintiffs position, the Technical Report explains the foundation for its analysis and its conclusion: Grade crossing safety does not create a significant impact under any of the build alternatives. An analysis of grade crossing safety was conducted. Traffic counts were conducted at all grade crossing locations and preliminary grade crossing plans were developed by traffic engineers to confirm the feasibility of the crossings. Operational and traffic data from existing Newark City Subway light rail grade crossing experience were analyzed to confirm that proposed modification will ensure safe operations. (Technical Report at 4-16). The findings of the Technical Report were th