Citations

Full opinion text

OPINION GOETTEL, District Judge. This case involves the on-going efforts on the part of the state, environmental groups, and private plaintiffs to force a county landfill to comply with the federal environmental laws. The result has been a long and complicated battle fought on both legal and political fronts. From the outset, the county’s effort to obey the environmental laws has been less than vigilant. Indeed, early on, the county showed a reprehensible lack of concern over the state’s enforcement measures. However, it also appears that genuine efforts to address environmental concerns have been frustrated by political scuffles, the pressures of a mounting “garbage crisis,” and the very real limitations of a landfill facility built without an engineered liner. In the face of the parties’ inability to reach a practical technological solution, the legal battles continue. The plaintiffs Orange Environment (“OEI”) and Arthur E. and Sandra Soons filed this citizen suit pursuant to § 505(a) of the Clean Water Act (“the CWA”), 33 U.S.C. § 1365(a) and § 7002 of the Resource Conservation and Recovery Act (“RCRA”), 42 U.S.C. § 6972 on December 31, 1991. Defendants Orange County (“the County”), Joseph G. Rampe, County Executive, Orange County Department of Public Works, and J. Daniel Bloomer, Commissioner of the Department of Public Works, now move to dismiss several of plaintiff’s claims for lack of jurisdiction, pursuant to Fed.R.Civ.P. 12(b)(1), or, in the alternative for summary judgment, pursuant to Fed.R.Civ.P. 56(e). Plaintiffs cross-move for summary judgment. The crux of defendants’ motion is their claim that, at the time plaintiffs filed this suit, the New York Department of Environmental Conservation (“DEC”) was in the process of prosecuting an ongoing administrative action concerning the situation alleged in the complaint and that the DEC action divests this court of subject-matter jurisdiction. They also argue that DEC action and New York law supersede certain of plaintiffs’ RCRA claims and that the pendent state claims should be dismissed. After careful consideration of the applicable law and facts, we deny the parties’ cross-motions for summary judgment and grant in part and deny in part defendants’ motion to dismiss. FACTS A. Procedural Background On October 18, 1991, OEI served the County, the United States Environmental Protection Agency (“EPA”), and the DEC with a notice of intent to bring suit. On December 30, 1991, plaintiffs filed this lawsuit, pursuant to the citizen suits provisions in the CWA, 33 U.S.C. § 1365(a), and RCRA, 42 U.S.C. § 6972(a)(1)(A) and (B). The complaint alleged, inter alia, that defendants violated the CWA by discharging pollutants, including landfill leachate, into the Wallkill River and Cheechunk Canal without a required permit. 33 U.S.C. § 1311(a), 1342. In addition, the plaintiffs brought a citizen suit under a RCRA provision authorizing a civil action where the defendant is “alleged to be in violation of any permit, standard, regulation, condition, requirement, prohibition, or order which has become effective pursuant to this chapter.” 42 U.S.C. § 6972(a)(1)(A). Specifically, plaintiffs alleged that the defendants violated RCRA’s permitting requirements, id,., § 6925(a), and open dumping provisions, id., §§ 6944, 6945. They also alleged that a citizen suit was proper because the landfill’s continued release of hazardous pollutants represented an imminent and substantial endangerment to health and the environment in violation of 42 U.S.C. § 6972(a)(1)(B). Finally, the Soons alleged various state common law claims. On February 18, 1992, defendants moved to dismiss all the Soons’ claims. We denied defendants’ motion by bench decision on March 6,1992. On July 31,1992, we granted the Hudson Riverkeeper Fund, Inc.’s (“the Riverkeeper”) motion for leave to intervene. In the meantime, the County was seeking to expand the landfill into land which contained federally protected wetlands. In July of 1992, the County and the EPA entered into a CWA § 309(a), 33 U.S.C. § 1319(a), compliance order in which the County admitted to filling federal wetlands without a permit as part of its landfill expansion plan. The order allowed phased use of the landfill expansion area in exchange for off-site restoration of wetlands. In response to the order, OEI moved for a preliminary injunction, pursuant to Fed. R.Civ.P. 65, to prohibit resumption of construction of the landfill expansion. On September 15,1992, we consolidated the preliminary injunction hearing with the hearing on the requested permanent injunction and wetlands restoration. On December 4, 1992, plaintiffs and plaintiff-intervenor moved for partial summary judgment on the issue of whether the EPA compliance order obviated the County’s need to get a § 404 permit to fill the wetlands from the Army Corps of Engineers as required by the CWA, 33 U.S.C. § 1344. Defendants cross-moved for summary judgment on the issue. On January 20, 1993, we granted plaintiff and plaintiff-intervenor’s motion for partial summary judgment and held that the defendants were required to obtain a § 404 permit despite the EPA compliance order. See Orange Environment, Inc. v. County of Orange, 811 F.Supp. 926 (S.D.N.Y.1993). Because our decision effectively enjoined the defendants from farther expansion of the site until they received a § 404 permit, we dismissed OEI’s motion for preliminary injunction without prejudice. Soon thereafter, then County Executive Mary McPhillips announced her desire to abandon the expansion project and commenced settlement negotiations. However, in February of 1993, the County Legislature moved to intervene as a separate party defendant in order to appeal the January 20 decision. We denied the Legislature’s intervention motion. See Orange Environment, Inc. v. County of Orange, 817 F.Supp. 1051 (S.D.N.Y.1993). The Legislature appealed, and our decision was affirmed. See Orange Environment v. Orange County Legislature, 2 F.3d 1235 (2d Cir.1993). Despite, the Legislature’s unsuccessful appeal, it succeed in delaying the settlement negotiations until McPhillips was voted out of office. Her successor, Joseph Rampe has decided to continue litigation rather than settle this case. Defendants now move to dismiss plaintiffs’ remaining claims under the CWA and RCRA pursuant to Fed.R.Civ.P. 12(b)(1) or, in the alternative, for summary judgment pursuant to Fed.R.Civ.P. 56(c). Their motion does not address plaintiffs’ claims relating to the issue of the § 404 permit under the CWA and only asserts that plaintiffs claims grounded upon the discharge of leachate from the existing landfill should be dismissed. Plaintiffs oppose and cross-move for summary judgment. They seek (1) a determination pursuant to Fed.R.Civ.P. 56(d) of defendants’ liability for violation of the CWA and RCRA, (2) declaratory judgment that defendants have violated the CWA and the open dumping and imminent and substantial endangerment provisions of RCRA, 42 U.S.C. §§ 6945, 6972; 40 C.F.R. Part 257, and (3) a permanent injunction directing the defendants to-cease from further violations of RCRA or the CWA. B. Landfill Background The crux of defendants’ motion is that the State’s pre-existing, ongoing administrative actions with respect to the violations at issue in the complaint operate as a jurisdictional bar to plaintiffs’ citizen suit. In order to properly assess defendants’ claims we must, unfortunately, delve into the depths of the landfill and its history. 1. The Landfill Site The Orange County Landfill is located on approximately 301 acres in the Town of Goshen, Orange County, New York in the Wallkill River Valley. The landfill is surrounded on three sides by various parts of the Wallkill River. Further south, the Wall-kill flows into the Hudson River. The Cheeehunk Canal carries the major portion of the Wallkill’s flow past the landfill on its southeast side. The original riverbed of the Wallkill, or the Old Channel, flows along the landfill’s south and northwest sides. When the County built the original landfill, it did not construct a liner to prevent contamination from entering groundwater below the site or surface water adjacent to the site. However, a good portion of the landfill site lies over a layer of clay and silt which naturally occurs in the ground. Because fine grained deposits do not transmit fluids easily, naturally occurring clays underneath a landfill can retard the downward migration of leachate. Unfortunately, the clay/silt layer beneath the landfill is not of uniform depth or composition. In areas where the layer is absent, sand from a layer of sand and gravel underneath the clay/silt layer appears at the ground’s surface. In addition, pockets of sand, which may range from 0 to 15 feet, are found within the clay/silt layer. The significance of coarser deposits, such as sand and gravel, is that they may become saturated with fluid. Indeed, a portion of the sand/gravel layer below the landfill is saturated with water and constitutes part of the Southern Wallkill Valley Aquifer. ‘Windows” occur in areas where the clay/silt unit is absent and sand appears at the ground’s surface. Windows below the landfill can provide a pathway for leachate to enter the aquifer. Underneath the sand/gravel layer is a layer of bedrock. While the bedrock unit is generally composed of solid rock, it often contains fractures through which water can move. Domestic wells in the area surrounding the landfill tap the bedrock for water. Thus, sand deposits within the silt/clay unit can serve as conduits for contaminant migration away from a landfill down into ground water contained in bedrock fractures or sideways to surface waters contained in riverbeds. Other possible leachate pathways are contained in dolostone, a carbonate rock which occurs in bedrock. Interconnected pore spaces appear in dolostone which transmit water. Carbonate bedrock occurs at relatively shallow depth increasing the opportunity for contamination. 2. Landfill History On July 6, 1973, the County submitted plans for the landfill to the DEC which called for three separate landfill areas on the property to occupy a total of 245 acres. The DEC issued a permit to begin construction on May 23, 1974, and operation began in the landfill area nearest to the Cheeehunk Canal (“Fill Area 1”) on September 30, 1974. The County operated the landfill from 1974 to January 1992. During that time period, approximately seven million cubic yards of predominately municipal waste was deposited on a 75-acre portion of the property. Leachate was first detected in 1975 when the DEC recorded two observations of leach-ate at the landfill. Subsequent DEC reports show that leachate was also observed in 1976 and 1977 with one recorded instance of leachate entering a water course in 1976 and two in 1977. In 1976, monitoring wells around the landfill exhibited signs of groundwater contamination by iron, phenols and sulfates. While the engineer’s report noted that “the groundwater quality in the area is not that good,” it suggested that “something may be affecting the groundwater adjacent to monitoring well #3.” In 1980-81, DEC monitors visited the site and issued seven reports, five of which recorded leachate discharges into .the Wallkill and six of which recorded uncontrolled leach-ate at the site. In 1981, the DEC issued the County an operating permit until August 1983 under the new state landfill regulations. In addition to compliance with state regulations, the permit included twelve special conditions. Two conditions involved leachate. The permit required “[i]f leachate is generated in a an appreciable volume, a State Pollutant Discharge Elimination System Permit (“SPDES”), pursuant to Environmental Conservation Law, Article 17, Title 8, shall be required prior to its disposal in any manner other than spray irrigation.” It also stated that “[t]he Permittee shall design a perimeter leachate collection system acceptable to the Department. This system shall be implemented when a significant amount of leachate is generated at the site as determined by the Department. This shall be submitted to the Department by January 1, 1982.” On August 22, 1983 (ten days after its permit expired), the County asked the DEC to extend its permit which was done without public discussion or participation. By the spring of 1986, the County still had not submitted a leachate management design. On April 16, 1986, a DEC engineer wrote a letter to the County’s Commissioner of Public Works informing him that “the lagoons in the Orange County Sanitary which have been used to store leachate, [were] very near their capacity.” In the face of DEC penalties, she suggested that the County take steps to alleviate the situation immediately such as arranging to haul the leachate off-site. Enclosed with the letter was a permit application to transport the leachate off-site. In 1986, the DEC issued 10 site reports, all of which recorded uncontrolled leachate on or near the site, but only one of which recorded leachate entering the surface waters. a. 1986 Consent Order On December 31,1986, the County and the DEC executed a consent order relating to the County’s unpermitted use of the landfill since the permit expired on June 30, 1984. The order also contained DEC allegations that the County had violated New York regulations and its original operating permit by allowing leachate to drain or discharge into surface waters without an SPDES permit and that it had failed to comply with special permit conditions requiring it to carry out a groundwater monitoring program and submit design plans for a perimeter leachate collection system. Although the 1986 Order recited the E.C.L.’s penalty provisions, no penalties were assessed against the County. Instead, the order required that the County submit a lifespan determination report, sub-surface investigation report, and a proposal for interim leachate removal and disposal. The order provided that the interim leachate management .proposal would be in effect “until such time as a permanent leachate management system [was] in operation.” However, the order did not provide that a permanent management system be in operation by a specified time. The order also provided that an intermediate cover be installed over all surfaces where no additional waste would be deposited no later than 60 days after its effective date. It further required that the County submit a final closure plan no later than 120 days after the DEC approved the subsurface report. After obtaining extensions of its compliance deadlines, the County submitted an interim leachate management plan in February of 1987 which was revised and resubmitted in April of that year at DEC’S request. The DEC approved it, subject to some modification on May 16, 1987. The installation of the interim leachate collection system began in June of 1987, and its eastern side was complete by the summer of 1988. In November of 1987, the DEC filed an enforcement complaint against the County for violation of operating conditions at the landfill. The problems cited in the 1987 complaint had not been cleared up by early 1989, and on February 23, 1989, Paul Keller, Regional Director of the DEC sent a letter to the County stating he was “shocked to hear that leachate has again been observed discharging into the Wallkill River.” The letter chastised the County for its failure to fully implement the interim leachate management plan despite many reminders from the DEC. Keller wrote that the County’s assertions that it was not dealing with the leachate because it was awaiting DEC approval was false and “reflects a cavalier attitude which [was] extremely troubling.” Keller warned that the County’s “persistent failure to control the leachate” on its existing landfill jeopardized its application for an expansion permit. He also denied the County’s request to increase the height of the current elevation and recommended prompt further study of possible subsurface movement between the landfill and Wallkill riverbank. b. Landfill expansion In the meantime, the DEC was also considering the County’s permit application for a landfill expansion. The County first submitted an expansion application in 1984. Despite the County’s contention that it was entitled to landfill on the unused portion of the 300 acre parcel under the original 1974 permit, the DEC disagreed. It also maintained that the expansion was not “grandfathered” out of the state environmental impact review requirement. OEI participated in the permitting process as a party in interest and submitted a letter setting forth its concerns as early as 1984. In 1987, the County applied for a permit to construct a 154r-acre landfill expansion. A mandatory public hearing was held on issues relating to the extension application beginning on November 18, 1987. Although the hearing was originally consolidated with the pending enforcement action, the enforcement action was adjourned at the DEC’s request. The application was denied by the Commissioner of the DEC due to possible danger to the Southern Wallkill Valley aquifer and because inadequate consideration was given to alternative sites. The County then submitted a revised application for a smaller, 75 acre expansion. The DEC approved the revised application in December of 1988. In July of 1989, DEC issued permits for the construction and operation of the expansion. The construction permit created the Orange County Sanitary Landfill Interested Persons Board 'as a “continuing forum for communication between the Permittee and interested public.” It also required that the County fund an Environmental Monitor for the existing facility as well as the new expansion. Finally, the permits required that the County comply with the 1986 Order as well as a second Consent Order entered into in 1989. Sometime during the construction of the landfill, OEI notified the EPA that the landfill expansion was being built on federally-protected wetlands. In late 1991, this action was commenced. In January 1992, the County ceased construction of the expansion and hired a consultant to investigate the landfill site. In February 1992, the EPA notified the County that it was investigating the possible unpermitted filling of wetlands at the landfill expansion. Following negotiations, the EPA and the County entered into a Compliance Order in July 1992. On January 20,1993, we granted the plaintiffs’ motion for partial summary judgment and held that, despite the EPA Compliance Order, the County still had a duty to obtain a § 404 permit from the Army Corps of Engineers before commencing operations at the landfill expansion site. 33 U.S.C. § 1344. The County’s application is currently pending before the Army Corps of Engineers. e. 1989 Consent Order Meanwhile, the County and the DEC entered into a second Consent Order on July 7, 1989 concerning the violations at the existing landfill. The 1989 Order alleged five violations of the 1986 Consent Order, including failure to implement the revised leachate management plan and failure to meet the deadline for placement of an intermediate cover over the site despite the DEC’s grant of two extensions. (The intermediate cover was completed in July of 1987.) The Order also alleged several violations of the New York regulations governing landfills, including extension of the landfill without placement of a liner or the installation of a leach-ate collection and storage system and drainage of leachate into the Wallkill River without an SPDES permit. The County admitted to violation of the 1986 Order and to drainage of leachate without a permit. As consideration for the DEC’s withdrawal of its complaint, the County agreed to spend $300,000 in the acquisition of real property for an Environmental Credit Project. The DEC also assessed a $375,000 civil penalty against the County, $300,000 of which was suspended so long as the County complied with the Environmental Credit Project. The Order also included a stipulated penalty provision in which the County agreed to pay a $25,000 fine for any future unpermitted discharges of leachate into the Wallkill River or Cheechunk Canal. Finally, the Order required that the County cany out a bank stability analysis and gave DEC monitors access to the facility in order to inspect the site to ensure compliance with the order. From March 1990 to September 1991, DEC monitor William Myers was on-site three days a week and filled out a weekly monitoring report. In 1990, Myers identified 19 instances of leachate discharge into surface waters. However, no penalties were assessed against the County. Also in 1990, part of the existing leachate collection system on the eastern side of the site collapsed. In 1991, the DEC monitor identified 6 instances of leachate discharge into surface waters. It also found 64 violations for uncontrolled leachate on or near the site and for failure to minimize leachate and prevent its discharge into surface waters. These violations probably occurred in part due to the problems with the leachate collection system. The DEC issued seven stipulated penalties pursuant to the 1989 Order for the discharges into surface water. . On November 1, 1991, two weeks after OEI issued a notice of intent to bring suit, DEC’s Regional Director wrote that “neither the existing landfill closure, nor the completion of the expansion area has progressed satisfactorily.” Because “sufficient evidence existed to commence enforcement action,” the Director informed the County that it would soon present the County with a draft Consent Order to resolve the violations. Finally, the letter stated that the existing landfill could not be operated after December 31, 1991. d. 1992 Consent Order On January 15, 1992, the County and the DEC entered into a third consent order. The order recited unpermitted discharges of leachate in nine separate locations and vertical expansion of the landfill in violation of the 1986 Order. It also found that the landfill violated state regulations since January 1, 1991 for failure to confine blowing paper and litter and because of cracks, erosions and depressions in its intermediate cover. The order required that the County undertake an Environmental Credit Project which valued at least $75,000. It assessed $100,000 in civil penalties, but $75,000 was suspended so long as the County complied with the credit program. The order allowed the landfill to accept solid waste until January 1992 and required that it submit a closure plan as required by the 1986 Order although no deadline was set. Despite the fact that the landfill ceased to accept waste for disposal in January of 1992, the DEC report for that year documented 31 violations for failure to minimize leachate through drainage control. On October 23, 1992, the DEC sent a letter to the County assessing $25,000 of the suspended $75,000 penalty due to violations of the 1992 Order (leachate was observed flowing into the Wall-kill River on four occasions in September and October of 1992). As of December 1993, no project had been approved for the Environmental Credit Program. e. Classification as a hazardous waste site Meanwhile in April of 1992, the DEC classified the landfill as a class 2 inactive hazardous waste site. As a result of the classification, jurisdiction over the landfill closure was transferred from the DEC’s Division of Solid Waste to its Division of Hazardous Waste Remediation. While the new classification required that additional studies be performed, it also made state remediation funds available. See N.Y. E.C.L. § 27-1301 et seq. The DEC recognized the possibility that hazardous waste was present at the site at least as early as 1983 when it classified the landfill as a Class 2a inactive hazardous waste site. The classification indicated that the DEC suspected that hazardous waste had been disposed at the site and that further information was necessary. Pursuant to final classification, Gibbs & Hill, Inc. prepared a Phase I Hazardous Waste Site Investigation for the DEC in 1988. The Phase I study consisted of the compilation of existing information, a site inspection, and a review of monitoring data. Gibbs & Hill did not recommend a Phase II study, which generally involves site specific investigations and data collection, and no Phase II study was performed. By March of 1992, the landfill still retained its temporary 2a classification, and the County’s consulting engineers, C & S Engineers, suggested that the County contact the DEC to inquire as to the status of the review since the final classification of the landfill would have important implications on the reimbursement of closure investigation costs. Perhaps at the County’s prodding, the DEC reclassified the site a month later. Although New York state recognizes the landfill as an inactive hazardous waste site, it is not included on the EPA’s National Priorities List. Indeed, according to CERCLIS, a database maintained by the EPA which “supports and tracks the EPA’s site planning and tracking functions” under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), the only actions undertaken by the EPA at the landfill were a preliminary site assessment in 1980 and a site screening inspection in 1991. No further EPA studies were done, and the landfill is not listed on the EPA’s proposed or final National Priorities List of uncontrolled hazardous substances releases that are designated as priorities for long term remedial evaluation and response. f. Current status In January of 1993 a fourth Consent Order was entered into which requires that the County implement a full inactive hazardous waste disposal site remediation program and allows up to 75 percent reimbursement from the state. Perimeter leachate collection systems are in place along the northwestern, western and southwestern sides of the landfill. The collection systems are comprised of a buried perforated collection pipe and a runoff collection trench. The trench drains into a collection pond located in the southeastern corner of the site, and the leachate from the underground pipes is collected in storage tanks. The runoff from the collection pond and the leachate from the tanks are transported to the Newburgh sewage treatment plant. The County collects and treats approximately 1.8 million gallons of leachate per month. Despite the collection system, the 1993 DEC report documents 9 violations for leach-ate entering surface water, 13 violations for leachate outbreaks on side-slopes, and 21 instances of failure to minimize leachate through drainage control. A remedial investigation and feasibility study (“RI/FS”) is currently underway at the landfill, and a work plan has been approved by the DEC (work plans usually provide an evaluation of existing data and background information collected prior to an RI/FS and overview of the steps to be taken during the process). Because the RI/FS process may be quite lengthy, the County and the DEC have agreed to undertake an accelerated remedial action (“ARA”) program. In a record of decision issued in January of 1994 (“ROD”), the DEC explained when an ARA program might be necessary. It stated when the major source of contamination is clearly evident, the strategy for the remedial program is to conduct an early evaluation of actions that will quickly control the source of contamination. In this way, the NYDEC seeks to accelerate the remedial process by separately, designing and implementing a portion of the remedial action to address the threat. At the same time, an RI/FS will be completed to ensure that an effective overall remedy is chosen for the site. Pursuant to the ARA program, the DEC created a proposed remedial action plan which was presented at a public meeting on October 28, 1993 and conducted a focused feasibility study in order to examine proposed remedial alternatives. The remedy chosen by the DEC in the ROD is early capping pursuant to state specifications contained at 6 N.Y.C.R.R. Part 360. According to the ROD, the cap should prevent future SPDES violations and significantly reduce leachate generation. In April of 1994, the County’s environmental engineers prepared an “Interim Leachate and Stormwater Runoff Control Plan” which was designed to reduce or control landfill leachate and contaminated runoff prior to the completion of accelerated remedial action in accordance to the ROD. Prior to construction of the cap, the plan provides for the collection of surface leachate outbreaks, the repair of eroded areas, and the installation of leachate seep drains. Plaintiffs and defendants’ experts dispute whether or not the efforts undertaken by the DEC and the County will adequately address the leachate problem. ANALYSIS A. The Clean Water Act Defendants argue that plaintiffs’ citizen suit under the CWA must be dismissed due to the DEC’s diligent prosecution of an administrative action. Plaintiffs assert that (1) the CWA’s preclusion provisions do not apply because the DEC’s actions cannot properly be characterized as diligent, and (2) even if the preclusion provisions apply, their suit is only barred to the extent that it seeks civil penalties. To the extent that plaintiffs’ citizen suit is not precluded, the defendants argue that it is moot in light of the current efforts the County has undertaken to control the leachate problem. Plaintiffs have also cross-moved for summary judgment. 1. Applicability of Section 1319(g)(6) In 1987, Congress amended the Clean Water Act and added, inter alia, an “Administrative penalties” subsection to the CWA’s Enforcement section. In addition to giving the Administrator and Secretary of the Army, in consultation with the State in which a violation occurs, the power to impose administrative penalties, the subsection also provided that action undertaken by the EPA Administrator or Secretary under this subsection shall not affect or limit the Administrator’s or Secretary’s authority to enforce any provision of this chapter; except that any violation— ... (ii) with respect to which a State has commenced and is diligently prosecuting an action under a State law comparable to this subsection ... shall not be subject to a civil penalty action under subsection (d) of this section or section 1321(b) of this title or section 1365 of this title. 33 U.S.C. § 1319(g)(6)(A). Thus, the amendment precludes a citizen suit where a state is diligently prosecuting an administrative penalty enforcement action. The CWA’s preclusion provision further provides: The limitations contained in subparagraph (A) on civil penalty actions under section 1365 of this title shall not apply with respect to any violation which— (i) a civil action under section 1365(a)(1) of this title has been filed prior to the commencement of an action under this subsection, or (ii) notice of an alleged violation of section 1365(a)(1) of this title has been given in accordance with section 1365(b)(1)(A) of this title prior to commencement of an action under this subsection and an action under section 1365(a)(1) of this title with respect to such alleged violation is filed before the 120th day after the date on which such notice is given. Id. at § 1319(g)(6)(B). a. Prosecution under a comparable state law i. DEC action Section 1319(g)(6)(A)’s limitation on citizen suits requires state prosecution of the violation under a comparable state law. In this instance, the comparable state provisions would be New York’s Water Pollution Control law, Article 17 of the E.C.L. and the penalty provisions contained at Title 19 of Article 71. While the DEC’s enforcement efforts prior to October of 1991 focused on regulating the landfill as a solid waste management facility under Title 7 of Article 27 of the E.C.L., it is clear that the DEC was aware of leachate at the landfill and that part of its enforcement efforts were targeted directly at the leachate problem. Indeed, New York regulations governing solid waste facilities specifically prohibit the discharge of leachate into surface waters without an SPDES permit, 6 N.Y.C.R.R. § 360.8(a)(3), and it is clear that the DEC was concerned with the County’s noncompliance with part 360.8(a)(3). Further it appears that by 1989, the DEC was acting under its authority over both the Article 27 and Article 17. Indeed, a consent order entered into by the parties in 1989 specifically includes a charge and admission by the County that leachate discharges into the WallMll constituted a violation of N.Y. E.C.L. §§ 17-0501, 17-0701, 17-0803, and 17-0807. Thus, while the DEC may not have originally conceptualized its activities at the landfill as an enforcement action under Article 17, it appears that the water pollution issue was a major component of the action at its inception and that enforcement of Article 17 had become a major purpose for DEC action by 1989. ii. Comparable statute Defendants argue that the New York law and regulations concerning water pollution are essentially similar to the federal scheme. N.Y. E.C.L. § 71-1929(1) provides for the imposition of civil penalties for violation of or failure to perform a duty under the state water pollution control statute, including state permitting requirements. Although the statute technically provides that the penalties shall be recoverable in an action brought by the Attorney General, id. at § 71-1929(3), penalties may also be assessed by the Commissioner in the first instance which are subject to review in an Article 78 proceeding. See In the Matter of DVC Indust., Inc. v. Flacke, 86 A.D.2d 892, 447 N.Y.S.2d 523 (2d Dep’t 1982). We recognized that § 71-1929 was comparable to the CWA’s administrative penalty provisions contained at 33 U.S.C. § 1319(g) in New York Coastal Fishermen’s Ass’n v. New York Dep’t of Sanitation, 772 F.Supp. 162, 165 (S.D.N.Y.1991) (“NYCFA ”). Because we see no reason to depart from that holding, we proceed to the issue of whether or not the DEC’s actions constitute diligent prosecution. b. Diligent prosecution i. The DEC’s enforcement efforts When the DEC issued the landfill’s second permit in 1981, its monitors had already recorded leachate discharges into the Wallkill as well as uncontrolled leachate on-site. As a result, it conditioned the 1981 permit on the County’s submission of a perimeter leachate collection system design by January of 1982. The permit stated that the system would be implemented after a “significant amount of leachate [was] generated at the site.” In the spring of 1986, the DEC was aware that the lagoons used to store leachate were near capacity and that the County had failed to even submit a perimeter collection system design. As a stop gap measure, the DEC suggested that the County arrange to haul the leachate off-site for treatment. However, the County failed to take action to deal with the leachate. On December 31, 1986, almost five years after the County’s original deadline to submit a leachate collection system to the DEC had passed, the County and DEC entered into a consent order which gave the County thirty additional days to submit a proposal for leachate removal and disposal. Although the DEC stated that the leachate discharges into surface waters were in violation of state permitting requirements, it did not assess any penalties. In November of 1987, the DEC filed another enforcement complaint for the County’s violation of its operating permit including, inter alia, leachate discharges into the Wall-kill without an SPDES permit and delay in the implementation of the revised leachate management plan. In the spring of 1988, the DEC noted that leachate was discharging directly from storage lagoons into the Wall-kill River and chastised the County for failing to submit an application to treat the leachate off-site despite its receipt of the application materials two years prior. In February of 1989, the DEC wrote a second time to complain that leachate was again observed discharging into the Wallkill despite the partial construction of the perimeter collection system and the approval of the permit to haul leachate off-site. In July of 1989, the County and the DEC entered into a second consent order in which the County admitted allowing leachate from the facility to drain or discharge into the Wallkill without an SPDES permit. With respect to the leachate discharges and other violations of the landfill permit conditions and New York law regulating waste management and mineral resources, the DEC assessed a $375,000 penalty against the County, but waived $300,000 which was to be applied towards an environmental credit project. The County also stipulated that it would pay a $25,000 penalty per occurrence of any future unpermitted discharges. Despite a provision in the order requiring that the County give DEC monitors access to the landfill to ensure compliance with the order, there are no records of a DEC monitor until March of 1990. In 1990, the DEC monitor identified 19 instances of leachate discharge into the surface waters but no penalties were assessed against the County. In 1991, the monitor reported six instances of leachate discharge into surface waters as well as 64 violations for uncontrolled leachate on or near the site and for failure to minimize leachate and prevent its discharge into surface waters. While these violations were probably due in part to the collapse of a portion of the existing leachate collection system in 1990, the DEC did issue some stipulated penalties. On November 1, 1991, two weeks after OEI issued a notice of intent to bring suit the DEC informed the County that it was commencing a new enforcement proceeding, ii. Applicable case law Defendants argue that state agencies are entitled to “considerable latitude” in their enforcement efforts. They claim this standard is supported both by case law and by the CWA itself. The First Circuit has written “[wjhere an agency has specifically addressed the concerns of an analogous citizen’s suit, deference to the agency’s plan of attack should be particularly favored.” North & South Rivers Watershed Ass’n, Inc. v. Scituate, 949 F.2d 552, 557 (1st Cir.1991). The District Court of Connecticut similarly held that plaintiffs who assert that a state prosecution is not diligent bear a heavy burden. Connecticut Coastal Fishermen’s Ass’n v. Remington Arms Co., Inc., 777 F.Supp. 173, 183 (D.Conn.1991), aff'd in part and rev’d in part, 989 F.2d 1305 (2d Cir.1993). It held, “[t]he court must presume the diligence of the State’s prosecution of a defendant absent persuasive evidence that the State has engaged in a pattern of conduct in its prosecution of the defendant that could be considered dilatory, collusive or otherwise in bad faith.” Id. at 183. Defendants argue that the language of the CWA supports granting wide discretion to the state. The statute states that it is Congress’ policy and goal “to recognize, preserve, and protect the primary responsibilities and rights of the States to prevent, reduce, and eliminate pollution, to plan the development and use (including restoration, preservation, and enhancement) of land and water resources ...” 33 U.S.C. § 1251(b). We considered the issue of diligent prosecution in NYCFA, supra. In that case, we noted that the “main purpose behind that limitation of citizen suits is to permit the federal and state governments to exercise their powers to remedy violations of the Clean Water Act” and that “a citizen suit may not ‘seek to recover, fines and penalties that the government has elected to forgo.’ ” Id. at 165, quoting, Atlantic States Legal Found, v. Eastman Kodak Co., 933 F.2d 124, 127 (2d Cir.1991). Thus, we declined to interpret section 1319(g)(6)(A) to require the actual imposition of penalties before a citizen suit could be precluded because “[s]uch an interpretation would unnecessarily undermine state and local enforcement efforts.” NYCFA, 772 F.Supp. at 165. Plaintiffs argue that DEC’s actions in this case do not constitute diligent prosecution. They argue that the DEC was aware of leachate discharge as early as 1975, and, despite the DEC’s on-site monitor, violations still continue. They contend that the DEC has allowed the County to buy its way out of compliance by Environmental Credit Projects. Although violations were cited and fines were threatened, they were seldom levied. When the DEC did assess fines, they were usually waived. Defendants maintain that the DEC was diligently addressing the leachate problem since 1986 and that despite a failure to levy significant fines, the DEC’s involvement has been steadily increasing. They argue that the landfill was originally constructed without a liner at a time when leachate outbreaks were the norm. As such, they contend that the DEC sought to focus its efforts on insuring that the County took appropriate measures to alleviate the leachate problem rather than assessing heavy fines. They argue that it was permissible for the DEC to opt to “bridge the County” into compliance with the CWA rather than adopting a punitive stance. We note that the relevant inquiry for defendants’ motion to dismiss is not whether or not the DEC’s actions can currently be categorized as diligent, but whether or not they could be so categorized in late 1991. However, we also note that the standard for evaluating the diligence of the state in enforcing its action is a low one which requires due deference to the state’s plan of attack and that part of the DEC’s difficulty in the earlier stages of its enforcement efforts was caused by the recalcitrant and cavalier attitude adopted by the County. Indeed, it appears that the problem was not that the DEC was turning a blind eye to the County’s violation, but that the county consistently failed to comply with the terms of the Consent Orders. Because we think that the DEC’s actions and enforcement decisions are entitled to a good degree of deference, we find that § 1319(g)(6)(A) precludes a civil penalty action under the citizen suit provisions of the CWA. 2. Scope of Section 1819(g)(6) Defendants argue that if § 1319(g)’s requirements for preclusion are satisfied, it bars a citizen suit in its entirety. They claim that the section’s bar to a “civil penalty action ... under section 1365” incorporates all actions which arise under the CWA’s citizen suit provisions, including those seeking injunctive relief and that the word “action” is “a collective noun, inclusive of all claims for relief.” In support of its position, it cites the First Circuit’s decision in Scituate. The Scituate court based its interpretation of § 1319(g) on the language contained in § 1365 which does not distinguish between civil penalty actions and other civil actions. Section 1365 simply provides: (a) Except as provided in subsection (b) of this section and section 1319(g)(6) of this title, any citizen may commence a civil action on his own behalf— (1) against any person ... who is alleged to be in violation of [the CWA], 33 U.S.C. § 1365(a). Because civil penalty actions were not set forth separately in § 1365, the First Circuit concluded that a link exists between civil penalties and injunctive actions. Scituate, 949 F.2d at 556. See Gwaltney of Smithfield Ltd. v. Chesapeake Bay Foundation, 484 U.S. 49, 58, 108 S.Ct. 376, 382, 98 L.Ed.2d 306 (1987) (noting that “[t]he citizen suit provision suggests a connection between injunctive relief and civil penalties that is notably absent from the provision authorizing agency enforcement.”) We adopted the opposite interpretation of the scope of § 1319(g)’s bar on citizen suits in NYCFA, supra. We wrote: we note that the limitation of citizen suits previously discussed relates only to actions for civil penalties, not injunctive or declaratory relief. Thus, even if we had concluded that the state was diligently prosecuting an action against the defendants, injunctive relief would still be appropriate. NYCFA 772 F.Supp. at 169. The statement in NYCFA was technically dicta and did not form the basis of our holding since we held that the DEC had failed to diligently prosecute an action against the defendants. However, Judge Le-val reached a similar conclusion which formed the basis of his decision in Coalition for a Liveable Westside, Inc. v. New York Dep’t of Environmental Protection, 830 F.Supp. 194 (S.D.N.Y.1993). Judge Leval based his holding on the plain language of the provision which “precludes only citizen suits seeking civil penalties.” Id. at 196, (emphasis in original). In addition, he noted that the “sparse” legislative history of the amendment supported this interpretation. The Conference Committee Report states: No one may bring an action to recover civil penalties under section ... 505 of this Act for any violation with respect to which the Administrator has commenced and is diligently prosecuting an administrative civil penalty action.... [T]his limitation would not apply to (1) an action seeking relief other than civil penalties (e.g., an injunction or declaratory judgment) H.R.Conf.Rep. No. 1004, 99th Cong., 2d Sess. at 133 (1986). Judge Leval explicitly rejected the First Circuit’s holding in Scituate that section 1319(g)(6) barred all citizen actions. He found no basis for the First Circuit’s assertion that a more limited reading of § 1319(g)’s preclusion was irrational. He wrote: As written, § 1319(g)(6) ensures that an entity that has violated the CWA will not be subject to duplicative civil penalties for the same violation. On the other hand, the statute permits a federal district court to entertain an action for injunctive relief for situations where, for example, a permit holder may have paid the relevant civil penalties but continues to violate its permit limitations or where the injunctive relief obtained in the state proceedings turns out to be inadequate to address the violations at issue. Id. We think that the facts of this case fall squarely within the type of situation Judge Leval asserts the preclusion provision was drafted to protect. Plaintiffs assert that, while the DEC may have assessed some penalties against the County, the County continues to discharge leachate into the Wallkill without a permit under the CWA or state law. While plaintiffs should not be allowed to seek civil penalties for the same violations that the DEC is prosecuting, the DEC’s failure to secure the County’s compliance with the CWA has spurred the plaintiffs’ suit for declaratory and injunctive relief. In addition, we find that the language of the CWA simply does not support a broader interpretation of the preclusion provision. It unequivocally states that any violation “with respect to which a State has commenced and is diligently prosecuting an action under state law ... shall not be subject to a civil penalty action under ... section 1365 of this title.” 33 U.S.C. § 1319(g)(6)(A) (emphasis added). Thus, we hold that a limitation of § 1319(g)(6)’s preclusion provisions is both supported by the plain language of the statute and by the equities of the situation. As such, we grant defendants’ motion to dismiss plaintiffs claim for civil penalties under the CWA, but deny their motion as to plaintiffs claims for injunctive and declaratory relief. 3. Summary judgment In addition to the motion to dismiss, plaintiffs and defendants have cross-moved for summary judgment. Citing the recent case, Atlantic States Legal Found., Inc. v. Pan American Tanning, 993 F.2d 1017,1020 (2d Cir.1993), defendants argue that compliance with the CWA, even if it occurs after a citizen suit is filed, renders any claim for injunctive relief moot. See Atlantic States Legal Found., Inc. v. Eastman Kodak, 993 F.2d 124, 127 (2d Cir.1991). However, “[i]n seeking to have a case dismissed as moot ... the defendant’s burden ‘is a heavy one.’ The defendant must demonstrate that it is ‘absolutely clear ’ that the allegedly wrongful behavior could not reasonably be expected to recur.” Pan American Tanning, 993 F.2d at 1019, quoting Gwaltney, 484 U.S. at 66, 108 S.Ct. at 386. If a plaintiff can establish that the defendants’ violations are continuing or, if after some deference is given to the state authorities “the terms of the settlement are such that a realistic prospect of continuing violation exists,” the plaintiff can continue to pursue relief under the CWA. Eastman Kodak, 933 F.2d at 128. Defendants argue that the current remediation program undertaken by the County and the DEC represents a comprehensive program to address the control of leachate discharges which “dispositively addressed Plaintiffs’ claims, causing them to ‘cease’ without ‘likelihood of recurrence.’ ” While we agree with the defendants that plaintiffs’ claim for injunctive relief would be moot should it become “absolutely clear” that future violations of the CWA could not reasonably be expected to occur, we do not find that to be the case at this time. First, we note that latest available DEC report documented nine violations for leach-ate entering the surface waters and 34 other leachate related violations at the landfill in 1993. Second, while it appears that the DEC and the County are finally working towards a solution to the leachate problem, even defendant’s counsel will not unequivocally state that the leachate discharges will cease once the remediation plan is fully implemented. While the DEC has hailed the plan as the “most logical approach” and the defendants’ expert has concluded that it is the “best possible means of controlling leachate generation,” the CWA prohibits any discharge of any pollutant into navigable waters except as authorized by the Act. Gwaltney, 484 U.S. at 52, 108 S.Ct. at 378. While we have some sympathy with defendants’ argument that, in light of the practical reality that the landfill was not built over an engineered liner, 100% prevention of leachate discharges may be impractical, we cannot say that defendants have established (indeed defendants do not even appear to contend) that further CWA violations will not occur. Finally, even if we were confident that current remediation plan fully addressed the leachate problem so that no further CWA violations should occur after its implementation, given the County’s current track record for complying with DEC compliance orders, we would not be able to say that such .a result is absolutely certain. Indeed, arguably a good deal of the progress that has been made so far may have resulted from the plaintiffs’ suit. Were we to now hold that the plaintiffs’ suit is moot, we might remove the very pressure that has pushed the County this far prior to any substantial implementation of their remediation plan. Plaintiffs also contend that they are entitled to summary judgment based upon defendants’ past violations of the CWA. Essentially, plaintiffs argue that the documented, unpermitted leachate discharges into the Wallkill River contained in the DEC reports as well as the County’s admission that the discharges violated state prohibitions on the discharge of waste or pollutants from a point source without an SPDES permit establish that they are entitled to judgment as a matter of law. While defendants argue that genuine issues of material fact remain as to whether or not their past conduct violated the CWA, because we have already dismissed plaintiffs’ claim for civil penalties, we need not decide the issue. While past violations generally can form a basis on which to infer a likelihood of recurrence, defendants have submitted evidence that measures are currently being taken to alleviate the leachate problem. In the face of contrary indicators of the County’s future conduct, we cannot say that we are absolutely certain that no further violations of the CWA will occur, but we also cannot say that we are convinced that future violations will occur establishing a need for injunctive relief. As such, we must deny both the plaintiffs and defendants’ motions for summary judgment and await further evidence on the issue of whether or not injunctive relief would be appropriate. B. The Resource Conservation and Recovery Act ' 1. Citizen Suit Provisions RCRA provides for three different types of citizen suits. Plaintiff has alleged claims under the first two types (the third type is a suit brought against the Administrator of the EPA). Section 6972(a)(1)(A) allows suits against any person “who is alleged to be in violation of any permit, standard, regulation, condition, requirement, prohibition, or order which has become effective pursuant to this chapter.” 42 U.S.C. § 6972(a)(1)(A). Subsection (a)(1)(A) suits usually address violations of permits, standards, and regulations. Subsection (a)(1)(B) allows suits against any person “who has contributed or who is contributing to the past or present handling, storage, treatment, transportation, or disposal of any solid or hazardous waste which may present an imminent and substantial endangerment to health or the environment.” Id. at § 6972(a)(1)(B). 2. Plaintiffs’ RCRA Claims Plaintiffs’ complaint states four claims under RCRA. First, it alleges that defendants are operating a Temporary Storage or Disposal of Hazardous Waste Facility without a permit as required by § 6925. Second, the complaint alleges that the defendants have failed to comply with operating requirements and standards, pursuant to § 6924. Both plaintiffs’ first and second RCRA claim are brought pursuant to § 6972(a)(1)(A). Plaintiffs’ third claim is brought pursuant to § 6972(a)(1)(B) and alleges that defendants’ “failure to prevent discharges of contaminated materials presents or threatens to present an imminent and substantial endangerment to human health and the environment.” Plaintiffs’ fourth and last RCRA claim is brought under § 6972(a)(1)(A) and alleges that defendants’ operation of the landfill constitutes open dumping in violation of § 6945 and 40 C.F.R. § 257.2. 3. Claims One, Two and Four Defendants argue that plaintiffs’ claims under subsection (a)(1)(A) must be dismissed because New York state’s EPA authorized hazardous waste program supersedes the permit and notification requirements codified in subchapter III of RCRA. a. Permit requirements and standards RCRA requires that owners and operators of facilities for the treatment, storage, or disposal of hazardous waste must obtain permits pursuant to § 6925. It also requires that such individuals comply with standards promulgated by the EPA Administrator. 42 U.S.C. § 6924. However, § 6926(b) allows EPA authorized state hazardous waste programs to “carry out such program in lieu of the Federal program under [subchapter III] in such State and to issue and enforce permits for the storage, treatment, or disposal of hazardous waste (and to enforce permits deemed to have been issued under section 6935(d)(1) of this title)....” 42 U.S.C. § 6926(b). Subchapter III of RCRA covers hazardous waste management. The Second Circuit has held that an EPA authorized state hazardous waste program can supersede RCRA’s permit and notification requirements, so that a citizen suit pursuant to subsection (a)(1)(A) to enforce § 6925 and § 6930 is unavailable. Dague v. City of Burlington, 935 F.2d 1343 (2d Cir. 1991), rev’d in part, — U.S. -, 112 S.Ct. 964, 117 L.Ed.2d 130 (1992). See City of Health v. Ashland Oil, Inc., 834 F.Supp. 971 (S.D.Ohio 1993) (holding that “a citizen suit is not available in an authorized state for an alleged violation of a federal provision superseded by state law pursuant to 42 U.S.C. § 6926(b)”); Thompson v. Thomas, 680 F.Supp. 1, 3 (D.D.C.1987) (holding where the EPA has authorized a state to administer and enforce its own hazardous waste program, federal regulations promulgated under RCRA have been superseded and any alleged violations of state regulations must be brought in state court pursuant to state law). New York received final authorization under § 6926(b) to administer and enforce its own hazardous waste program on May 29, 1986. 57 Fed.Reg. 9978 (March 23, 1992). Plaintiffs concede that citizen suits can not be used to enforce RCRA’s permitting regulations. As such, we must grant defendants’ motion to dismiss plaintiffs’ first and second RCRA claims. b. Section 6945(a) Even if § 6926(b) is interpreted as precluding citizen suits to enforce federal permitting requirements and standards relating to hazardous waste, plaintiffs argue that their subsection (a)(1)(A) citizen suit is still viable to the extent that they seek to enforce RCRA’s open dumping provisions. Defendants concede that open dumping claims are not superseded by state hazardous waste programs adopted pursuant to § 6926(b). While § 6926(b) authorizes states to carry out their own hazardous waste management programs in lieu of the Federal program promulgated under subchapter III, RCRA’s open dumping provisions are found in sub-chapter IV, which seeks to develop and encourage methods to dispose of solid waste in an environmentally sound manner, 42 U.S.C. § 6941, and are not superseded by state programs authorized to carry out the goals of subehapter III. See Lutz v. Chromatex, 718 F.Supp. 413, 425-26 (M.D.Pa.1989) (denying a motion to dismiss as to plaintiffs’ open dumping claim since open dumping provisions are found in subehapter IV). Despite their concession, defendants argue that plaintiffs’ open dumping claim fails as a matter of law. As such, they contend that they are entitled to summary judgment. Plaintiffs have cross-moved for summary judgment as to the open dumping claim. We note that summary judgment is proper where “there is no genuine issue as to any material fact and ... the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). i. Open dumping provisions Section 6945(a) provides: any solid waste management practice or disposal of solid waste or hazardous waste which constitutes the open dumping of solid waste or hazardous waste is prohibited, except in the case of any practice or disposal of solid waste under a timetable or schedule for compliance under this section. The prohibition contained in the preceding sentence shall be enforceable under section 6972 of this title against persons engaged in the act of open dumping. 42 U.S.C. § 6945(a). The responsibility of promulgating regulations to determine which facilities will be classified as open dumps is delegated to the EPA Administrator. Id. at § 6944. The regulations provide that facilities failing to satisfy certain criteria set out at 40 C.F.R. Part 257 will be considered open dumps for purposes of RCRA. Id. at § 257.-1(a)(1). However, the regulations list several exceptions. Among them is an exception for “municipal solid waste landfill units” which are subject to revised criteria set out in part 258. Id. at § 257.1(c)(10). Defendants contend that their actions do not constitute open dumping because the landfill constitutes a municipal solid waste landfill (“MSWLF”) unit and their actions are in compliance with applicable regulations MSWLFs. In the alternative, they argue that they are operating under a timetable or schedule for compliance. ii. Applicable regulations Plaintiffs claim that the landfill is covered by part 257 of the regulations which sets forth the criteria for solid waste disposal and that the landfill violates part 257.3-3(a) and 257.3^(a), 40 C.F.R. §§ 257.3-3(a) and 257.3Hl(a). Part 257.3-3(a) provides “a facility shall not cause a discharge of pollutants into waters of the United States that is in violation of the requirements of the National Discharge Elimination System (“NPDES”) under section 402 of the Clean Water Act, as amended [33 U.S.C. § 1342].” Plaintiffs assert the continuing discharge of leachate into the Wallkill River without a § 402 permit constitutes an open dumping practice. Part 257.3-4(a) provides that a facility “shall not contaminate an underground drinking water source beyon