Citations

Full opinion text

STEPHEN H. ANDERSON, Circuit Judge. This is a diversity action alleging breach of a 20-year contract (July 7,1976 — July 6, 1996) for the purchase of natural gas under leases on properties located in Converse County, Wyoming. The plaintiffs’ complaint seeks, inter alia: (1) damages for alleged underpayment for delivered gas and for the defendants’ refusal to buy • gas after November 1993; (2) a declaratory judgment that following deregulation of natural gas prices the contract continued to obligate the defendants to pay for gas at the highest rate prescribed or permitted by Congress during regulation; and (3) a declaratory judgment that in addition to “native” gas produced from the plaintiffs’ wells, the defendants were required to take and pay for “makeup” gas — that is, gas purchased by the sellers from outside sources, injected into the field to maintain pressure for oil production, and then extracted from the field along with “native” gas and delivered to the defendants. The district court held that the defendants breached and wrongfully repudiated the contract in 1993, that the plaintiffs are entitled to damages from August 13, 1993, through the end of the contract term on July 6, 1996, and that the defendants were obligated to purchase makeup and all other gas, up to the contract limit of twelve million cubic feet per day, delivered by the sellers from August 1993 to the end of the contract term. However, the district court rejected the plaintiffs’ theory that the highest rates prescribed or permitted by Congress during periods of price regulation lived on after deregulation as the applicable contract price. Instead, the court determined sua sponte that the favored nations clause issue had been tried by implied consent, and held that the favored nations clause of the contract applied to set the contract price after August 1993. On its own motion, the court reopened the case for the introduction at a later date of evidence of damages under the favored nations clause. Following the subsequent reopened trial, the court ruled that the contract price for gas from August 13, 1993, through July 6, 1996, was set by reference to prices charged under two contracts introduced into evidence by the plaintiffs after the first trial. Applying those prices to the types and quantities of gas covered by rulings described above, and after subtracting amounts the plaintiffs actually received, the court awarded the plaintiffs damages in the amount of $15,551,455.00, plus costs. The court de-dined to award prejudgment interest. On appeal and cross-appeal, the parties, respectively, do not challenge the district court’s rulings that the plaintiffs are not entitled to damages for any period prior to August 13, 1993, and that the defendants wrongfully repudiated the contract in 1993, entitling the plaintiffs to damages for the remaining approximately two and a half years of the 20-year contract. All the other rulings are variously contested by one party or the other. After full consideration of the record, and for the reasons stated below, we affirm the district court’s rulings that the defendants breached and wrongfully repudiated the contract in 1993, and that the plaintiffs are entitled to damages from August 13, 1993, to July 7, 1996. We also affirm the district court’s ruling that the last, highest prices under government regulation did not survive deregulation as applicable prices for gas under the contract. We reverse the district court’s rulings that the favored nations clause of the contract applies and establishes damages, and that the defendants were obligated to purchase gas not attributable to lands committed to the contract by the plaintiffs, including “makeup gas.” Accordingly, we vacate the judgment, and remand the case for a determination, on evidence in the record pri- or to the court’s reopening order, of damages from August 13, 1993, to July 7,1996. Furthermore, because the district court’s conclusion that prejudgment interest was not warranted in this case was premised on its determination that plaintiffs’ damages were to be computed by reference to the favored nations clause, a determination we hold to be improper, we vacate the district court’s prejudgment interest determination and remand to the district court for a determination regarding whether prejudgment interest is warranted in light of our treatment of the case. BACKGROUND The district court thoroughly laid out the facts of this case, and the course of government regulation of interstate and intrastate natural gas prices under the Natural Gas Policy Act (NGPA), 15 U.S.C. §§ 3301-3432 (1982) (§§ 3311-3348 repealed 1989), in its published opinion on the parties’ cross-motions for summary judgment, Moncrief v. Williston Basin Interstate Pipeline Co., 880 F.Supp. 1495 (D.Wyo.1995), and in its Findings of Fact and Conclusions of Law issued on August 16, 1996, 3 J.A. 1170. We restate, summarize and add to those opinions only those facts and references to the NGPA which are necessary to our decision. W.A. Moncrief and Tex Moncrief were professional oil and gas businessmen, based in the Moncrief Building in Fort Worth, Texas, whose joint ventures in that business began in 1945 and eventually covered at least five states. In 1974, they joined with Woods Petroleum Co. (“Woods”) to drill 12 wells in the Powder River Basin in eastern Wyoming. One of those wells discovered an oil field which was designated as the Powell II Unit. The field was a retrograde gas-condensate field, that is, oil and gas existed in a gaseous state in the reservoir. The land overlying the reservoir was owned by other parties, to whom the Moncriefs and the other working interest owners paid production royalties. In 1976 the Moncriefs and Woods, which acted as the Moncriefs’ agent, entered into a 20-year contract with the Montana-Dakota Utilities Company (later named MDU Resources, Inc.) (hereinafter “MDU”) for the sale of natural gas produced from the Powell II Unit, with interests in specified sections in Townships 39 and 40 North, in Converse County, Wyoming. Interests in additional lands in Converse County were added to the contract by amendment in 1978 and 1979. MDU later formed Willi-ston Basin Interstate Pipeline Company (WBIPC) as a wholly-owned subsidiary, and assigned its gas contracts to it in 1985. I. Price The contract was entered into at a time of supply shortage and, therefore, in a seller’s market. Also, since intrastate sales of gas were unregulated at the time, Woods and Moncrief favored contracting with MDU since the sales could be for the intrastate Wyoming market and could command a higher price than was available for interstate sales. The pricing provisions of the contract reflect these circumstances. The contract provided what, for ease of reference, can be called a base price (¶¶ 7.1 and 7.2); two pi'ice escalator provisions — a regulated “area rate” clause (¶ 7.4) and a “favored nations” clause (¶ 7.6); and a clause providing for the renegotiation, at the seller’s option, of prices once government regulation of interstate gas prices ceased (¶ 7.5). Those provisions, in relevant part, are as follows: ARTICLE VII Price Buyer shall pay Seller for the gas delivered hereunder in accordance with the following schedule: 7.1 For the period commencing on the date of initial delivery of gas hereunder, until January 1, 1978, a price of $1 per million Btu. 7.2 The price shall be increased 1.5$ per million Btu on January 1, 1978 and on each subsequent January 1 during the term hereof. 7.4 If the Federal Power Commission, or any successor or other governmental authority having jurisdiction in the premises, shall at any time hereafter prescribe or permit, for the pricing area in which the properties are located, a higher just and reasonable area rate including all adjustments for the same type of gas as committed hereunder than the price herein provided to be paid, then the price hereunder shall be increased, effective as of the date such higher price is prescribed, to equal such higher rate. 7.5 In the event the regulation of the price at which natural gas is sold in interstate commerce ceases, then Seller shall have the right to request a redeter-mination of the prices at which natural gas is to be sold hereunder. Buyer shall notify Seller of the date of deregulation in writing and any request for redeter-mination shall be made to Buyer in writing and shall in the first instance be made during the six (6) month period immediately following the effective date of such deregulation, and subsequently during the six (6) month period immediately preceding each anniversary of the effective date of such deregulation. Buyer shall notify Seller thirty (30) days prior to each anniversary date of deregulation so that Seller may request rede-termination. If Seller shall make any such request, representatives of Buyer and Seller shall promptly meet and attempt to determine the fail' value of gas deliverable hereunder for the then remaining term of this Agreement commencing in the first instance on the date such request is made and subsequently on each anniversary of the effective date of such deregulation, but in no event shall the value so determined or to be determined pursuant to the further provisions of this paragraph result in a price which is less than the price otherwise applicable hereunder.... 7.6 In the event a bonifide [sic] utility company or other pipeline company enters into a gas purchase contract with any Seller for the purchase of gas of similar quality and quantity from lands located East of the Continental Divide in the State of Wyoming, whose terms call for a higher price to be paid from time to time than the then effective price contained herein, the prices herein contained shall be adjusted to reflect such higher prices on the date of first delivery of gas and from time to time thereafter, under the referenced contract. 8 J.A. 8538-40. Moncrief was never paid the base price. A short while after the contract was signed, the Federal Power Commission (FPC) increased its national rate for new interstate gas to $1.42 per million British thermal units (MMBtu), and MDU paid that rate when deliveries began. Two years later, Congress enacted the NGPA, which extended federal regulation to the intrastate natural gas market for the first time. In so doing, the NGPA divided the intrastate gas market into several categories, and made a distinction between gas brought into production after the statute’s passage, which was governed by § 102 of the new statute, and gas produced pursuant to an intrastate gas contract in existence in 1978, governed by § 105. Section 105 set a ceiling price for gas delivered under existing contracts, providing that the maximum lawful price for such gas was the regulated price set for new gas under § 102. After Woods insisted that it and Moncrief were entitled, under the contract, to an amount equal to the § 102 rate for new gas, MDU began paying the § 102 rate in October 1979 and continued doing so until January 1985, when most of the NGPA price regulations expired. See 15 U.S.C. § 3331(a) (1982) (repealed 1989). The § 102 rate in December 1984 was $3,845 per MMBtu, and MDU was paying that amount to Moncrief. The district court found most of the following facts. Anticipating deregulation, in June 1984 MDU sent a letter to its natural gas sellers, including Moncrief, proposing a price of $2.25 per MMBtu for deregulated gas effective January 1, 1985. Representatives of MDU and WBIPC later met with the sellers, and during those meetings WBIPC offered to pay $2.25 per MMBtu, inclusive of production tax reimbursement, for deregulated gas. WBIPC also offered an additional 50<t per MMBtu for natural gas produced during 1985 if the seller agreed to execute a contract amendment releasing MDU/WBIPC from any past claims under the contract and providing greater flexibility to WBIPC under the contract. Ronald Tipton of WBIPC met with the Moncriefs on August 8, 1984, and February 28, 1985, to discuss these proposals with respect to the contracts WBIPC had with W.A. Moncrief and Tex Moncrief. The Moncriefs did not agree to amend their contract but stated that they would not sue WBIPC. Starting in January 1985, the pipeline paid Woods $2.25 per MMBtu for Moncriefs interest in the gas purchased under the contract, and continued to pay that price during 1985 and 1986. On October 3, 1986, WBIPC sent a letter to Moncrief stating its intention to reduce the price that it was paying for natural gas effective January 1, 1987. On March 16, 1987, WBIPC sent another letter to Moncrief setting forth WBIPC’s proposal to pay $1.75 per MMBtu and requesting that Moncrief sign a proposed contract amendment that would offer WBIPC greater flexibility under the contract. WBIPC representatives Ronald Tipton and Dennis Haider met with Tex Moncrief on April 28, 1987, to discuss WBIPC’s proposal to pay $1.75 per MMBtu. At this meeting, Tex would not agree to the proposed contract amendment. During the 1984, 1985, and 1987 meetings with MDU and WBIPC representatives, neither W.A. Moncrief nor Tex Moncrief asseifed that the contract price remained at the last regulated price prior to deregulation of natural gas prices. During these meetings, neither W.A. Mon-crief nor Tex Moncrief stated that the price of the gas was a regulated price under NGPA § 105(b)(3). WBIPC paid Woods or its successors $1.75 per MMBtu for Moncriefs gas produced from January 1, 1987, through October 31, 1993. WBIPC provided monthly statements to Woods and its successors which showed the prices paid for the gas. Woods and its successors provided monthly settlement statements to Moncrief which showed or allowed Moncrief to determine the price WBIPC was paying for the gas. Moncrief had employees who reviewed the statements received from the operator and who were specifically charged with the responsibility to determine that the prices received for gas sales were correct under the applicable contracts. In addition, internal summaries 'of the operator reports and prices paid were prepared by Moncriefs employees. These reports were discussed with and readily available to Tex Moncrief. These payments were accepted by Woods (or its successors) and Moncrief without reservation or objection made to WBIPC as to the price paid. WBIPC relied upon Moncriefs acceptance of these prices paid by it from 1985 to 1993. From 1985 to August 1993, the Mon-criefs made no claim that any provision of their contract with MDU mandated prices higher than the $2.25/$1.75 per MMBtu paid by WBIPC, and WBIPC made no assertion that the price should be the lower contract base price. On August 9, 1993, Tex Moncrief sent a letter to WBIPC stating for the first time his position that the contract price in effect was the December 1984 NGPA § 102 price of $3,845 per MMBtu plus tax reimbursement. He sent a similar letter on August 12, 1993. Neither Moncrief nor WBIPC construed these letters as a request for price redetermination under ¶ 7.5 of the contract. On November 11, 1993, Moncrief sent a letter to WBIPC stating that the contract price after January 1,1985 was established under ¶ 7.6, the favored nations clause. Plaintiffs later abandoned that position in litigation and, in their Second Amended Complaint, they asserted, as alternative arguments, that the contract price of the gas was either the regulated § 102 price in December 1984 ($3,845), or the § 105(b)(3) ceiling price in December 1992 ($6,371). WBIPC, in turn, asserted that in and after 1985 the contract price was in actuality the base price which, with annual increases under ¶ 7.2, amounted to $1.23 per MMBtu in 1993. It also informed Mon-crief that effective November 1, 1993, it would no longer purchase gas under its existing contracts. This eventually resulted in the wrongful repudiation ruling by the district court which WBIPC does not appeal. II. Quantity The district court also found the following facts regarding the issue of “makeup” gas. In the late 1970s, MDU became aware of the Powell II Unit owners’ plans to repressure the gas reservoir by rein-jecting gas produced from the unit and from other sources. The reinjection plan called for a 14-year period of recycling and six to seven years of “blowdown” (production of the injected gas). The parties believed that reinjection would add to the oil and gas reserves ultimately recoverable from the reservoir. MDU urged the unit owners to buy natural gas for recycling rather than nitrogen, even though natural gas cost more, because the nitrogen would have presented a processing problem upon extraction. After balancing the costs and benefits of purchasing nitrogen, the unit decided to purchase outside gas for injection. On September 1, 1983, the Powell II Unit and the adjoining Spearhead Ranch Unit were terminated with the approval of the Bureau of Land Management. The lands from the Powell II and Spearhead Ranch Units were combined with other lands from the surrounding area to form the Powell Pressure Maintenance Unit (PPMU). At the same time, the PPMU owners started a repressurization program for secondary recovery of oil and natural gas liquids from the unit. Natural gas produced from the unit was processed to remove the liquid hydrocarbons and then injected or “recycled” back into the unit to maintain the reservoir pressure. As planned, the unit owners purchased makeup gas from outside the unit, which was injected into the reservoir to assist in maintaining the desired pressure level. Over 17.5 billion cubic feet of makeup gas was injected into the unit between September 1, 1983, and December 1, 1993. Mon-crief and the other PPMU owners did not pay severance or production taxes or royalties on the makeup gas withdrawn from the unit. In 1993, the PPMU owners elected to discontinue repressurization and begin blowdown of the unit. During blowdown, the operator stops injecting gas and allows the pressure to decline as gas is withdrawn from the unit. The operator of the Powell II Unit informed WBIPC of its plans for blowdown of the reservoir as early as 1991, but the pipeline did not assert that it was not obligated to take the gas injected from outside the unit until it answered in this lawsuit. WBIPC believed that the Powell II contract remained in effect and feared litigation if purchases ceased. Beginning in 1993, Moncrief tendered blowdown gas of six million cubic feet per day to WBIPC. WBIPC offered to cancel the contract based on the representation that the pipeline’s customers (including its parent) had discontinued purchases under Federal Energy Regulatory Commission (FERC) Order No. 636. WBIPC also claimed that the pipeline’s take obligation was to take only Moncrief s working-interest share of twelve million cubic feet per day. Moncrief disputed all these claims and demanded adequate assurances, which WBIPC refused to provide. WBIPC has refused to purchase gas from Moncrief since November 1,1993. DISCUSSION I. Price A. Did the District Court Properly Address the Merits of the Favored Nations Clause Claim? This action was commenced on November 9, 1993. Following extensive pretrial proceedings, the case was tried in a bench trial from January 10-19, 1996. In its opinion, issued on August 16, 1996, the district court ruled sua sponte that Mon-crief was entitled to damages under ¶ 7.6 of the contract, the favored nations clause, despite the fact that Moncrief did not present this theory in his Second Amended Complaint. The court reopened the case to receive “evidence that the parties may wish to present on this issue,” because the record did not contain any evidence which would permit the calculation of damages (if any) under the clause. 3 J.A. 1196. In these rulings the court did not invoke Fed. R.Civ.P. 15(b) nor did it conduct any analysis justifying the application of that rule. Rather, it explained the absence of evidence, and the basis for reopening the case, on the ground (unsupported by any reference to the record) that “the parties thought that the favored nations clause evidence had been excluded, inadvertently, by the Court in its summary judgment opinion.” 3 J.A. 1196. After allowing additional discovery, the court subsequently held further trial proceedings on April 27, 1997. In an opinion issued on June 26, 1997, it denied the defendants’ motion for reconsideration, and concluded that the plaintiffs’ complaint should be amended to conform to the evidence pursuant to Fed.R.Civ.P. 15(b), so as to include a claim under the favored nations clause of the contract. The court determined that the issue was tried by implied consent of the parties, and that the defendants were not prejudiced since they had been given ample post-trial discovery and preparation time, and there was an evidentiary hearing on the merits. The district court then ruled that a contract between Forest Oil Corporation and KN Energy, Inc. (the “Forest Contract”) for the purchase of gas at $4.38 per MMBtu qualified under ¶ 7.6, and established the Forest Contract price as the Moncrief contract price for the period from August 13, 1993, through September 30, 1993, when the Forest Contract was assigned to a subsidiary. It also ruled that a contract between Moncrief and ANR Pipeline Company, originating in 1980 and amended in 1989, for the purchase of gas at $3.50 per MMBtu, qualified under ¶ 7.6 and established the Moncrief contract price for the period from October 1,1993, to July 7,1996. On appeal, the defendants first argue that this issue is substantive, not procedural, and is governed by Wyoming law relating to the waiver, abandonment and release of claims. We disagree. The record relates most directly to the procedural posture of the case. Therefore we analyze this issue under the Federal Rules. Rule 15(b) provides in relevant part as follows: (b) Amendments to Conform to the Evidence. When issues not raised by the pleadings are tried by express or implied consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings. Such amendment of the pleadings as may be necessary to cause them to conform to the evidence and to raise these issues may be made upon motion of any party at any time, even after judgment; but failure so to amend does not affect the result of the trial of these issues. We review a district court’s decision to amend the pleadings to conform to the evidence under the abuse of discretion standard. See Rios v. Bigler, 67 F.3d 1543, 1551 (10th Cir.1995). Here, whether the district court abused its discretion by sua sponte introducing the favored nations clause claim and allowing further trial proceedings is best evaluated in the context of how the plaintiffs themselves proceeded as to that claim. In its 1995 summary judgment opinion the District Court specifically noted the changes in the plaintiffs’ claims, including the abandonment of any claim under the favored nations clause of the contract: Plaintiffs theories of recovery have been evolving. Moncrief's three different complaints in this action have reflected three different theories of recovery. Moncrief's initial complaint argued that the sellers owed a higher price based on the Section 7.6 “favored nation” clause of the contract. In this initial complaint, Moncrief also asserted that the natural gas sold under the contract was deregulated on January 1, 1985, and that, based on the terms of the contract, the applicable price was the last regulated price of $3,845 per MMBtu plus tax reimbursement. In the plaintiff’s First Amended Complaint he abandoned the application of the favored nations clame and concentrated on the last regulated price and his claim that the contract did not allow the contract price to decrease. In the First Amended Complaint, Tex Moncrief argued that deregulation of the contract price had occurred on January 1, 1985. Finally, the plaintiffs Second Amended Complaint, currently before the Court, proposes that the gas under the contract remained regulated after all. Moncrief now argues that the governing price comes from the Natural Gas Policy Act § 105(b)(3) which sets a ceiling price for “old gas.” According to this contention, the applicable price under the contract is set by 18 C.F.R. 271.101. Moncrief v. Williston Basin Interstate Pipeline Co., 880 F.Supp. 1495, 1504 (D.Wyo.1995) (emphasis added). This is an accurate description of the evolution of the plaintiffs’ claims, culminating with the Second Amended Complaint which then governed the proceedings. That complaint raises only the issue of, and seeks relief based on, regulated prices. The plaintiffs’ abandonment of a favored nations claim followed the defendants’ discovery requests relating to that claim after the initial complaint was filed. Plaintiffs’ counsel responded to those requests by telling defendants’ counsel that plaintiffs would drop their claim on that clause. Plaintiffs’ counsel then responded in writing to the discovery requests, stating that “Moncrief has chosen not to pursue his claim under the contract’s ‘favored nations’ clause.” 11 J.A. 4981-83. The plaintiffs then filed a motion for leave to amend their complaint, stating that “Moncrief has also amended his complaint to omit his claim under the contract’s ‘favored nations’ clause.... ” 1 J.A. 37. The motion to amend was granted by the magistrate judge, and the favored nations clause claim was absent from the first amended complaint as well as the second amended complaint. The absence of any favored nations clause claim by the plaintiffs is consistent in the plaintiffs’ pretrial memoranda, trial brief, and pretrial proposed findings of fact and conclusions of law, all of which pursued regulated price claims. The court’s pretrial conference order does not include any claim under the favored nations clause, and explicitly provided that the order controls and would not be amended except with consent of the parties unless “by order of the court to prevent manifest injustice.” 3 J.A. 1014. In his lengthy opening statement, plaintiffs’ counsel reconfirmed abandonment, stating that Mon-crief initially made a claim under the favored nations clause “which we later withdrfew]. We later abandoned that claim.” 5 J.A.2049. It is undisputed that plaintiffs’ counsel made no motion during trial, or at any time after trial, to amend its pleadings to reassert a claim under the favored nations clause of the contract. And, there was certainly no explicit consent by defense counsel that the issue could be reintroduced. As for the court’s reference to an alleged view by the parties that there was an inadvertency or some confusion in the ruling on summary judgment, no motion for reconsideration or clarification on the subject was filed by the plaintiffs after the ruling, at any time prior to trial (including contentions in pretrial orders), or after trial. In short, the court’s ground for reopening the trial — inadvertency or confusion regarding the district court’s summary judgment ruling — has never been reasserted again, including in the arguments on appeal. The district court held that the issue was tried by implied consent because defense counsel referred to the favored nations clause when examining some witnesses about the contract, and introduced exhibits D-61, D-63, D-64, D-119, D-119A, and D-121 which pertained to that clause. On appeal, plaintiffs’ counsel identifies some of those and other exhibits as well, including D-108, D-113, and D-118, along with sixteen references to portions of the trial testimony. In sum, out of literally hundreds of exhibits, the district court and the plaintiffs have identified about twelve which even mentioned favored nations issues, and a handful of instances where that subject came up during the examination of witnesses. We have reviewed all of these references to the favored nations clause. Whether viewed individually or collectively, they do not represent anything that can fairly be characterized as the introduction and trial of a favored nations price claim. See Hardin v. Manitowoc-Forsythe Corp., 691 F.2d 449, 457 (10th Cir.1982) (stating that “[ijmplied consent is found where the parties recognized that the issue entered the case at trial and acquiesced in the introduction of evidence on that issue without objection”). Some of these references are innocuous. Some are inextricably intertwined with historical facts explaining the course of the parties’ dealings, views, and conduct, both in-house and otherwise, and are entirely appropriate as part of describing the whole picture. An omitted claim does not require redaction of history. The balance of the material in question was obviously employed to discredit the plaintiffs’ arguments that the Moncriefs and their employees and experts always regarded the contract price to be the last regulated price, that regulated prices continued after 1984, and that prices were never supposed to decrease. Implied consent cannot be based upon the introduction of evidence that is relevant to an issue already in the case when there is no indication that the party presenting the evidence intended to raise a new issue. See Southwestern Stationery and Bank Supply, Inc. v. Harris Corp., 624 F.2d 168, 171 (10th Cir.1980); Ellis v. Arkansas Louisiana Gas Co., 609 F.2d 436, 440 (10th Cir.1979); see also 6A Charles Alan Wright, Arthur R. Miller, and Mary Kay Kane, Federal Practice and Procedure § 1493, at 32-35 (2d ed.1990). Indeed, “[w]hen evidence claimed to show trial of an issue by consent pursuant to Rule 15(b) is relevant to a separate issue already in the case, it would be unjust to the opposing party to consider a new theory of recovery after trial is complete.” Cook v. City of Price, Carbon County, Utah, 566 F.2d 699, 702 (10th Cir.1977). Admittedly, the defendants’ attempts to show that the prices they paid through 1984 reflected favored nations considerations rather than regulation as such, and that the plaintiffs ignored fluctuations in favored nations prices through 1992, are somewhat' problematic. See Exs. D-61, D-63, D-64, D-119, D-119-A; see also 5 J.A.2096-2100; 6 J.A. 2700-01. Both arguments necessarily subsume the unspoken but inevitable premise that favored nations prices were and continued to be relevant. But, even an acknowledgment that ¶ 7.6 continued to be a viable part of the contract (apparently a given) does not resolve anything. It simply provides, ar-guendo, the basis for a claim to be proved, not proof of the claim. If the claim asserted to have been tried by consent is that the applicable contract price from August 1993 to July 7, 1996, was set by a contract or contracts qualifying under ¶7.6, it faces an insurmountable obstacle. There is no evidence proving the claim. This deficiency is highlighted by the fact that the only competent evidence available to prove up the claim, and which was used by the court — qualifying comparison contracts and testimony and evidence concerning the qualifying contracts — was not introduced until the second trial, after the first trial was completed. Thus, even assuming hypothetically that the plaintiffs’ first complaint was reinstated at trial, the favored nations claim would have failed for lack of proof of a qualifying contract and damages, each a sine qua non of the claim. After both parties rested, at the trial held in January 1996, the district court would not have been able to fashion a judgment for the plaintiffs under ¶ 7.6. And, sua sponte reopening the case for a further trial to breathe life into a failed issue is not the purpose of or sanctioned by Fed.R.Civ.P. 15. That rule allows the pleadings to be amended to conform to the evidence already entertained by the court, not to evidence presented at a further trial. For these reasons we conclude that the district court abused its discretion by holding that a claim under the favored nations clause, ¶ 7.6, was tried by implied consent, and by sua sponte reopening the ease for a further trial on that subject, resulting in an award of damages. B. Did Regulated NGPA Prices Continue to Operate as the Applicable Contract Price After Deregulation? Throughout this case, the plaintiffs’ central argument as to rates has been that the contract'price continued to be the last and highest NGPA regulated rate cognizable under ¶ 7.4 of the contract. They assert that the district court erred in its rulings that the contract is unambiguous, that intrastate natural gas prices were deregulated on January 1, 1985, and that NGPA rates did not survive deregulation as the continuing price under the contract. The district court’s holding that the contract is unambiguous foreclosed consideration of parol evidence of the parties’ intent as to the meaning of the contract provisions in question. Nevertheless, although the district court stated that it did not consider such evidence in arriving at its decision, the court did receive parol evidence allegedly relevant to the parties’ intent as to the meaning of the contract, as well as the parties’ course of conduct, and that evidence is contained in the appellate record. We review de novo questions of contract ambiguity and legal interpretation, the meaning and effect of the NGPA, and Wyoming law. See Salve Regina College v. Russell, 499 U.S. 225, 239, 111 S.Ct. 1217, 113 L.Ed.2d 190 (1991) (stating that “courts of appeals review the state-law determinations of district courts de novo”); United States v. Fillman, 162 F.3d 1056, 1056 (10th Cir.1998) (stating that “[w]e review de novo the district court’s interpretation of a federal statute”); City of Wichita v. Southwestern Bell Tel. Co., 24 F.3d 1282, 1287 (10th Cir.1994) (stating that “[t]he determination of the ambiguity of a contract is a question of law reviewed de novo”). We review the district court’s findings of fact under the clearly erroneous standard. See Fed. R.Civ.P. 52(a); Candelaria v. EG & G Energy Measurements, Inc., 33 F.3d 1259, 1261 (10th Cir.1994). There is a highly contested issue in this case as to whether the government’s regulation of intrastate gas prices under the NGPA was discontinued by Congress as of January 1, 1985, or as of January 1,1993. But there is no claim that any NGPA regulation of prices cognizable under the contract existed after 1992. Since the only period at issue in this appeal is August 1993 through July 6, 1996, the contract’s expiration date, it is largely immaterial whether deregulation was effective on January 1, 1985, or January 1, 1993, unless the contract requires that regulated prices must continue as the contract price after deregulation. If, pursuant to this contract, regulated rates survived deregulation, then the date of deregulation becomes important because the regulated § 102 rate at the end of 1984 was $3,845 per MMBtu and the § 105(b)(3) ceiling rate at the end of 1992 was $6,871 per MMBtu. If relevant regulated rates did not survive deregulation under this contract, then we need not address whether deregulation ceased at the end of 1984 or 1992. Accordingly, the threshold question is whether regulated rates survived deregulation as the contract price for natural gas under the terms of the parties’ contract. Our inquiry must, of course, begin with the terms of the contract. 1. As indicated above, the district court found no ambiguity in the pricing provisions of the contract and held that regulated prices did not survive deregulation. It stated: Plaintiffs have urged that the contract did not provide for a fall in the contract price following deregulation, and, as a result, that the contract price remains at the highest regulated price. However, even if a gas contract does not explicitly provide for a lowering of a contract price, it is implicit in a price redetenni-nation clause like that found in Section 7.5. See, Prenalta Corp. v. Colorado Interstate Gas, No. C89-1010-B (Brim-mer, C.J.), rev’d on other grounds, 944 F.2d 677 (10th Cir.1991); Questar Pipeline Co. v. Grynburg, et al., No. 92-CV-265-J (Johnson, C.J.) and PG & E Resources Co. v. Questar Pipeline Co., No. 93-CV-063-J (Johnson, C.J.). Moreover, courts have also held that in gas purchase contracts, the escalated base contract price governs when deregulation occurs and the parties have failed to redetermine a new contract price. E.g., Colorado Interstate Gas v. Martin Exploration Management Corp., No. 85-CV-0399 (Dist. Ct. El Paso County, Colo. Dec. 15, 1988). Moncrief, 880 F.Supp. at 1520. Alternately arguing for interpretations in their favor based on lack of ambiguity, Br. for the Appellants at 25-30, or ambiguity, Appellants’ Reply Br. at 29, the plaintiffs offer a multitude of reasons why the district court erred in holding that regulated prices expired for contract purposes when they expired by statute. Their central thesis is that prices under this contract operated on an upward ratchet principle — they could only go up, never down. This position, they argue, is supported by the facts that the contract was made in a sellers’ market and “[o]ne principal purpose of the contract was to assure Mon-crief of the highest price he could collect for intrastate gas during the life of the contract.” D. Ct. Findings of Fact and Conclusions of Law, 3 J.A. 1186. They point to the unambiguous language of the escalator clauses, which refer only to price increases and upward adjustments to reflect “such higher prices” or “such higher rate.” 8 J.A. 3538, 3540 (¶¶7.4, 7.6). There are no provisions for lowering prices, and no market-out clause. In addition, plaintiffs assert that the contract was all the work of the defendants and should therefore be construed against them. The upshot of these arguments is that regulated rates purportedly served merely as a reference point or benchmark. Once that benchmark was established it took on (or always had) a life of its own as the contract price, unaffected by any later deregulation of the rate. As support for this benchmark principle, plaintiffs cite Amoco Prod. Co. v. Stauffer Chem. Co., 612 P.2d 463 (Wyo.1980), and this court’s opinion in Northwest Cent. Pipeline Corp. v. JER Partnership, 943 F.2d 1219 (10th Cir.1991). Other than these two cases, the plaintiffs cite no authority purporting to directly support their position. To the contrary, they recognize that the district court cases cited by the court here are directly against them and they ask us to “overrule” those cases. Appellants’ Reply Br. at 47. They also attempt to distinguish the district court cases on the ground that they were interpreting regulated interstate contracts “which had to accept federal pricing law.” Id. The plaintiffs’ reliance on JER underscores the point that contract cases turn on the particular facts of each case. Except for the first month, the contract involved in the JER case had, essentially, only two ways to determine price: a regulated rate or, if regulation ceased, then, at the seller’s option, a redetermined price under a specified formula. The district court in JER held that the contract was ambiguous as to price upon deregulation, because if regulation ceased, and the seller did not request a redetermination, there was no provision for a price. The court therefore resorted to extrinsic evidence to determine the intention of the parties. We upheld that decision, reasoning — on our way to deciding the case on extrinsic evidence grounds — that ambiguity exists where two rational but mutually exclusive choices are available. In this context we stated that [a] perfectly reasonable interpretation of this language (which the district court ultimately adopted) is that nothing happens to the contract price upon deregulation unless the seller requests redetermination. Otherwise the seller’s redetermination right would be rendered meaningless. JER Partnership, 943 F.2d at 1227. Unlike the contract in JER, the contract in this case does not present an unavoidable conundrum in the event of deregulation and the seller’s lack of request for a price redetermination. Both the base price provisions of ¶¶ 7.1 and 7.2 and the favored nations pricing provision of ¶ 7.6 continue to operate independently of deregulation and the operation of ¶ 7.4. And the contract does not state that the price must always stay at the highest regulated rate or other benchmark, nor does it say that regulated rates survive deregulation. These are merely argumentative inferences the sellers would have us draw. On the other hand, the contract does not state that upon deregulation prices must revert to those set under ¶¶ 7.1, 7.2 or 7.6 if the seller fails to request price redeter-mination. So there is some basis for the plaintiffs’ interpretation. Nevertheless, the rationales here are not equally plausible, as they were in JER where the provisions created a virtual impasse. Under the favored nations clause here, the price would adjust favorably to the highest qualifying prices (applying the plaintiffs’ own definition of “Seller” as any seller), thus satisfying the Moncriefs’ desire to get the highest applicable price being paid in the described geographic area. And, if prices fell (plaintiffs assert that in 1975-76 prices were 67$ per Mcf for interstate gas, and slightly above $1.00 per Mcf for intrastate free market gas, Br. for Appellants at 6), the escalated base price would protect them. Accordingly, fully taking into account the context in which this contract was negotiated, we agree with the district court that the contract can be interpreted within its four corners without ambiguity, and that regulated prices ceased to apply upon deregulation. However, deciding that the contract is ambiguous would not change the outcome, as we next discuss. 2. The plaintiffs alternatively argue that the contract is ambiguous and that the district court erred in failing to consider extrinsic evidence, inferring that we. should remand for a new trial on the question of regulated pricing under the contract. Here too, they cite JER, asserting that the case, in addition to declaring as a matter of law that regulated prices survive deregulation, also stands for the proposition that contractual ambiguity requires resort to extrinsic evidence, which they assert to be in their favor. The district court in JER, unlike the district court in this case, declared the contract to be ambiguous. It therefore admitted and considered extrinsic evidence on the meaning of the contract according to the parties. As to that evidence we stated: The district court found that, in the absence of a seller request for redeter-mination, the parties intended the last regulated price to be the contract price upon deregulation. Overwhelming evidence supported this conclusion. Indeed, Williams’s witnesses uniformly agreed that this was the parties’ intention. We cannot say that this finding was clearly erroneous. [T]he parol evidence was crystal clear: the parties intended the last regulated price to be the deregulated price unless the seller requested price redetermination. JER Partnership, 943 F.2d at 1228-29 (citation and footnote omitted) (emphasis added). That is not the situation in this case. The district court admitted extensive extrinsic evidence regarding contract negotiations and subsequent communications and conduct of the parties relating to the contract. In fact, the plaintiffs do not assert that they were prevented from introducing any extrinsic evidence, or that some specific relevant evidence exists and was proffered, but was foreclosed by a ruling of the court. Thus, we have the extrinsic facts before us. From our examination it is apparent that, unlike JER, the evidence is far from overwhelming or crystal clear in favor of the plaintiffs’ position that the parties intended regulated rates to survive deregulation. Indeed, plaintiffs point us to nothing in the record which directly addresses the parties’ intentions regarding the effect of deregulation on contract prices set by reference to the area rate clause. One internal communication in 1976 from Woods to Moncrief stated that MDU was offering an attractive base price and a good opportunity for price increases in the future. 8 J.A. 3516-18. Another, commenting on the draft contract, stated that “there are numerous price protection clauses that will permit us to be on a par with the highest price paid in the Powder River Basin by any bona fide purchaser. At the present time, the $1.00 per MMBtu price is the highest in Wyoming.” 8 J.A. 3525. Moreover, Claud Pickard, MDU’s gas-supply manager, testified at his deposition as follows: Q. [P1- Exh. 8] says there are numerous price protection clauses that will permit us to be par with the highest price paid in the Powder River Basin by any bona fide purchaser. Would you agree that that was an accurate statement of the contract? A. I would think so, uh-huh. Q. Was that the intent of the parties when they entered into the contract back in ’76? A. Well, I don’t think it ivas the intent of MDU to be the highest priced, but when you put a favored nations clause' in the contract, that’s the way it works. 5 J.A. 2397-98 (portions of Pickard’s deposition introduced at trial) (emphasis added). Pickard also testified, at trial, that the main purpose of intrastate contracts was to obtain higher prices under favored nations clauses, and that higher prices under the area rate clause or the favored nations clause would supersede the base price. 5 J.A. 2373-74, 2396. Apparently this testimony underlies the district court’s finding of fact that “Mon-crief and Woods believed that the price could not decrease from the highest rate achieved at any time during the contract.” 3 J.A. 1175. But, as the Pickard testimony quoted above indicates, it was not the intent of MDU to be the highest priced. Pickard then went on to state, nevertheless, that the favored nations clause works that way. None of this evidence, or any other, directly addresses what the parties intended to happen to regulated prices upon deregulation. Such evidence as there is refers consistently to prices paid to bona fide purchasers, a term used in the favored nations clause. This supports the defendants’, not the plaintiffs’, view. Neither Tex Moncrief nor Claud Pick-ard, the only witnesses at trial involved in negotiating the contract, had any recollection of the parties’ intent or discussions regarding the operation of the pricing clauses following deregulation. 5 J.A. 2260-62, 2267-70, 2298-2306, 2409-10. Moncrief did not testify that the price set under the area rate clause could not decrease after deregulation. 5 J.A. 2396. Thus, to reiterate the point, the evidence regarding the parties’ intent at the time of drafting, unlike the evidence in JER, is hardly overwhelming or crystal clear regarding prices on deregulation. The parties’ course of conduct, however, cuts directly against plaintiffs’ argument. The defendants paid amounts equal to the highest applicable regulated rates until the end of 1984 when they considered such prices to have been deregulated by Congress. At the time the regulated price was $3.845 per MMBtu. The defendants then notified the Moncriefs that the price would drop to $2.25. The Moncriefs refused to sign any contract amendment to that effect, but stated they would not sue, and they accepted, without protest, payments based on the $2.25 rate in 1985 and 1986. After a similar notification, the defendants dropped the price to $1.75 per MMBtu, which the Moncriefs accepted, without protest, from 1987 to 1993. Not once during this time did the Mon-criefs claim that the higher price paid in 1984 was required under the contract to continue. Nor did Woods or the other working interest owners who had contracts identical to the Moncrief contract claim that 1984 regulated prices must continue. See 6 J.A. 2966. In sum, as the district court found, the Moncriefs knowingly received prices lower than the 1984 regulated price for more than eight-and-a-half years, and collected approximately $1,244,000 at those rates, without once voicing the highest price/benchmark interpretation of the contract they now urge. Their explanation is that Moncrief was simply waiving contract rights month by month, Appellants’ Reply Br. at 41, 49, or that the defendants “laid low” knowing, apparently, that Moncrief was making a mistake, id. at 48.. These arguments do not square with the fact that the Moncriefs were and are experienced professionals in the oil and gas business. When parties on both sides of a contract are knowledgeable, experienced professionals, their course of dealing under the contract is more likely to show their intent as to the operation of the contract than to suggest mistake or ignorance. That is especially true here where the plaintiffs do not seriously advance the latter position, there is no evidence to support it, and the district court made express findings to the contrary. Thus, eight and one-half years of payments, knowingly received, essentially defeats the plaintiffs’ argument. It is true that the plaintiffs do point to some contrary evidence in the way of defendants’ filings with the FERC in 1987, in which higher applicable rates are mentioned. 9 J.A. 3851, 3863. Even crediting this evidence, however, it is impossible to conclude that the district court erred by rejecting the plaintiffs’ argument that the contract price could never decrease. Even if we assume, arguendo, that the contract was ambiguous on this point, the extrinsic evidence contained in the record, especially the parties course of performance over eight-and-one-half years, is too much against the plaintiffs to support a remand to the district court for fact findings based on parol evidence. 3. For the reasons stated above, we hold that, however viewed, the district court did not err in its conclusion that regulated rates did not continue to set prices under this contract after those rates were terminated by Congress. Accordingly, it is unnecessary to address whether deregulation, as it pertains to this contract, occurred on January 1, 1985, or on January 1, 1993. The only question we must address here concerns the proper price to be paid for the contract gas from August 1993 to July 6, 1996. C. What Price Applies? Our disposition of the issues above leads us back to the district court’s conclusion at the end of its summary judgment opinion — that the contract price after August 1993 should be set by reference to a fair value price. Paragraph 7.4 of the contract does not apply. Paragraph 7.6 was expressly abandoned as a claim. Paragraphs 7.1 and 7.2 have been set aside by the parties’ course of conduct just as surely as the plaintiffs’ argument regarding the survival of regulated rates was set aside by the same course of conduct. Thus, despite the district court’s finding that the plaintiffs’ letters in 1993 did not amount to a request for price redetermination under ¶ 7.5, the posture of the case places the parties constructively in that position, or simply at “a reasonable price” according to the open price provision of the Uniform Commercial Code. See Wyo. Stat. Ann. § 34.1-2-305; see also Koch Hydrocarbon v. MDU Resources Group, Inc., 988 F.2d 1529, 1535 (8th Cir.1993) (stating that if the contract was ambiguous as to the parties’ intent regarding price after deregulation, the contract price after deregulation should be set by applying § 2-305 of the Uniform Commercial Code). In the district court’s summary judgment opinion, it reserved the question of damages for trial. At trial both parties presented alternative theories of damages that included expert testimony on fair value price and market price. We therefore vacate the damage award, and remand the case to the district court to determine damages based on the testimony presented at the first trial. It goes almost without saying that any uncertainty in ascertaining exact amounts caused by the defendants’ repudiation must be resolved against them. II. Quantity We now turn to the issues surrounding the quantity of natural gas defendants were obligated to purchase under the contract. The quantity terms of the parties’ contract state that “Seller agrees to sell and deliver to Buyer, and Buyer agrees to purchase, receive and pay for the daily quantity of gas which is physically available to Buyer at the delivery point on each day of the term hereof,” up to a maximum of 12 million cubic feet per day. 8 J.A. 3536 (¶¶ 3.1, 3.2). The district court held, based on the language of these provisions, that defendants were obligated to purchase as much gas as plaintiffs made available at the delivery point, up to the stated maximum of twelve million cubic feet per day. Defendants assert that the district court’s holding erroneously obligates them to purchase two varieties of gas from lands not dedicated to the contract. First, defendants argue that the district court’s holding obligates them to purchase gas attributable to other areas of the PPMU, not originally part of the Powell II Unit or otherwise dedicated to the contract. Second,. defendants contend that the district court’s holding erroneously obligates them to purchase natural gas produced on lands outside the entire PPMU and not dedicated to the contract, purchased by plaintiffs, and injected into the PPMU reservoir for conservation purposes. We will address each of these assertions in turn. This portion of the district court’s holding was decided as a matter of law, and therefore our review here is de novo. A. Are Defendants Obligated to Purchase Only Gas Produced From Lands Dedicated to the Contract? There are generally two types of natural gas purchase contracts. The first is known as a warranty contract, under which the producer warrants to the purchaser that it will provide a certain amount of natural gas at the times and places specified under the contract. A warranty contract does not specify where the gas is to come from; it simply obligates the producer to come up with the specified amount of gas from any source and deliver it to the purchaser. See 8 Howard R. Williams et al., Oil and Gas Law 1162 (1997) (defining “warranty contract” as “[a] contract for the sale of gas wherein the producer agrees to sell a specific amount of gas and the gas delivered in satisfaction of this obligation may come from fields or sources outside the designated fields”); see also Florida Power & Light v. FERC, 598 F.2d 370, 375 (5th Cir.1979) (describing a warranty contract). The second is known as a dedication contract, wherein the producer “contracts to furnish the purchaser all the gas produced from specified reserves, thus ‘dedicating’ those reserves to the customer.” 8 Howard R. Williams et al., Oil and Gas Law 253 (1997); see also Louisiana Land & Exploration Co. v. Texaco, Inc., 478 So.2d 926, 927 (La.Ct.App.1985) (distinguishing a warranty contract from a dedication contract), rev’d on other grounds, 491 So.2d 363 (La.1986). By its own unequivocal terms, the parties’ contract was a dedication contract. The contract states that it covers certain lands only; these lands are specifically enumerated in Exhibit B to the contract. Paragraph 1.1 of the contract states that “Seller hereby commits to the performance of its obligations under this Agreement, all of Seller’s interest in gas produced from wells completed on the lands as previously set forth herein, and dedicated to this contract.... ” 8 J.A. 3535 (¶ 1.1) (emphasis added). This conclusion is supported by an examination of the parties’ course of dealing. See Wyo. Stat. Ann. § 34.1-2-202, comment 1(c) (Michie 1997) (allowing courts to examine the parties’ course of dealing even where the contract is unambiguous). When the contract was first signed in 1976, the lands dedicated to the contract included only plaintiffs’ interest in the Powell II Unit, as well as two other small parcels. On two occasions, in 1977 and 1978, the parties amended the contract to include other parcels. See R. Vol. 12, Supp.App., Tab 303. In 1979, the parties again amended the contract, this time to remove lands from the contract’s purview. Id. at Tab 304. If the contract were something other than a dedication contract, such amendments would have been wholly unnecessary. Under warranty contracts, it is irrelevant where the gas comes from, as long as the producer delivers it to the specified place on time. Dedication contracts, however, are intended to cover only gas produced from the specified parcels. Plaintiffs took great care in the early years of the contract to amend the contract to include additional production wells. This course of performance indicates that the parties understood the contract to be a dedication contract which applied only to gas produced from the lands dedicated thereunder. When the PPMU was created in 1983, it consisted of the Powell II Unit and several other parcels previously dedicated to the contract, as well as some lands not previously dedicated to the contract. R. Vol. 12, SuppApp., Tab 299. Plaintiffs argue that the establishment of the PPMU was an “expansion” of the Powell II Unit, as provided for in Exhibit B of the contract. Appellants’ Reply Br. at 4-6; 8 J.A. 3556 (stating that the contract covers plaintiffs’ interest in the Powell II Unit “as said Unit is approved by the United States Geological Survey and as such Unit is expanded or contracted from time-to-time by the U.S.G.S.”). We are not persuaded, The creation of the PPMU was a unitization of several parcels, not an expansion of the Powell II Unit. By creating the PPMU, the Bureau of Land Management (BLM) terminated both the Powell II Unit and the adjacent Spearhead Ranch Unit, owned by producers other than plaintiffs, and combined them into one unit for conservation purposes. Essentially, the BLM unitized all units in the same reservoir, including the former Powell II Unit, the former Spearhead Ranch Unit, and others, into one new unit, called the PPMU. This was not an expansion of the Powell II Unit as encompassed by the language in Exhibit B. The record demonstrates that even plaintiffs considered the action a “[ujnitization” rather than an expansion. 8 J.A. 3741 (a letter from Woods to all working interest owners in the Powell II Unit, and referring to the BLM action as “unitization”). Indeed, the unitization brought about by the creation of the PPMU is covered by another provision of the contract. In Article 111(A) of the contract, plaintiffs retain certain rights, including the right to “unitize or pool any of Seller’s lands committed hereunder with other properties of Seller or others in the same field.... ” 8 J.A. 3546 (¶ 3.1(e)) (emphasis added). In that event, the “Agreement will cover Seller’s production attrifoited to the said lands in the unit or units so formed.” Id. (emphasis added). ' Thus, under the unambiguous terms of the parties’ contract, a uniti-zation such as that effected by the creation of the PPMU does not incorporate the other lands within the unit into the contract’s coverage. Rather, the contract provides that in the event of unitization, the contract will cover only that portion of Seller’s production attributed to the contract lands within the new unit. We conclude, therefore, that only the specific lands enumerated in Exhibit B to the contract, and not the entire PPMU, were dedicated to the contract. Under the unambiguous terms of the parties’ dedication contract, most notably ¶ 3.1(e) of Article 111(A), plaintiffs were obligated to sell, and defendants obligated to purchase, only that portion of plaintiffs’ natural gas production attributable to the previously-dedicated contract lands. To the extent the district court’s holding is inconsistent with this conclusion, it is reversed. B. Are Defendants Obligated to Purchase Injected Gas? Next, we must determine whether defendants are obligated to purchase the 17.5 billion cubic feet of gas purc