Citations

Full opinion text

PRELIMINARY PRINT Volume 605 U. S. Part 1 Pages 168–203 OFFICIAL REPORTS OF THE SUPREME COURT May 29, 2025 Page Proof Pending Publication REBECCA A. WOMELDORF reporter of decisions NOTICE: This preliminary print is subject to formal revision before the bound volume is published. Users are requested to notify the Reporter of Decisions, Supreme Court of the United States, Washington, D. C. 20543, pio@supremecourt.gov, of any typographical or other formal errors. 168 OCTOBER TERM, 2024 Syllabus SEVEN COUNTY INFRASTRUCTURE COALITION et al. v. EAGLE COUNTY, COLORADO, et al. certiorari to the united states court of appeals for the district of columbia circuit No. 23–975. Argued December 10, 2024—Decided May 29, 2025 Under federal law, new railroad construction and operation must frst be approved by the U. S. Surface Transportation Board. 49 U. S. C. § 10901. In 2020, the Seven County Infrastructure Coalition applied to the Board for approval of an 88-mile railroad line connecting Utah's oil- rich Uinta Basin to the national freight rail network, facilitating the transportation of crude oil to refneries along the Gulf Coast. As part of its project review, the Board prepared an environmental impact state- ment (EIS) that addressed signifcant environmental effects of the proj- ect and identifed feasible alternatives that could mitigate those effects, as required by the National Environmental Policy Act (NEPA). The Board issued a draft EIS and invited public comment. After holding six public meetings and collecting more than 1,900 comments, the Board Page Proof Pending Publication prepared a 3,600-page EIS that analyzed numerous impacts of the rail- way's construction and operation. Relevant here, the EIS noted, but did not fully analyze, the potential environmental effects of increased upstream oil drilling in the Uinta Basin and increased downstream re- fning of crude oil. The Board subsequently approved the railroad line, concluding that the project's transportation and economic benefts out- weighed its environmental impacts. Petitions challenging the Board's action were fled in the D. C. Circuit by a Colorado county and several environmental organizations. The D. C. Circuit found “numerous NEPA violations arising from the EIS.” 82 F. 4th 1152, 1196. Spe- cifcally, the D. C. Circuit held that the Board impermissibly limited its analysis of the environmental effects from upstream oil drilling and downstream oil refning projects, concluding that those effects were rea- sonably foreseeable impacts that the EIS should have analyzed more extensively. Based on the defciencies it found in the EIS, the D. C. Circuit vacated both the EIS and the Board's fnal approval order. Held: The D. C. Circuit failed to afford the Board the substantial judicial deference required in NEPA cases and incorrectly interpreted NEPA to require the Board to consider the environmental effects of upstream and downstream projects that are separate in time or place from the Uinta Basin Railway. Pp. 177–192. Cite as: 605 U. S. 168 (2025) 169 Syllabus (a) NEPA ensures that agencies and the public are aware of the envi- ronmental consequences of certain proposed infrastructure projects. As a purely procedural statute, NEPA “does not mandate particular results, but simply prescribes the necessary process” for an agency's environmental review of a project. Robertson v. Methow Valley Citi- zens Council, 490 U. S. 332, 350. Some federal courts reviewing NEPA cases have assumed an aggressive role in policing agency compliance with NEPA, and have not applied NEPA with the judicial deference demanded by the statutory text and the Court's cases. When, as here, a party argues that an agency action was arbitrary and capricious due to a defciency in an EIS, the “only role for a court” is to confrm that the agency has addressed environmental consequences and feasible alternatives as to the relevant project. Strycker's Bay Neighborhood Council, Inc. v. Karlen, 444 U. S. 223, 227. Further, the adequacy of an EIS is relevant only to the question of whether an agency's fnal decision (here, to approve the railroad project) was rea- sonably explained. Judicial deference in NEPA cases extends to an agency's determina- tion of what details are relevant in an EIS. While NEPA requires an EIS to be “detailed,” 42 U. S. C. § 4332(2)(C), and the meaning of “de- tailed” is a legal question, see Loper Bright Enterprises v. Raimondo, Page Proof Pending Publication 603 U. S. 369, 391–392, what details need to be included in any given EIS is a factual determination for the agency. The textual focus of NEPA is the “proposed action”—the project at hand—not other sepa- rate projects. § 4332(2)(C). Courts should defer to agencies' discre- tionary decisions about where to draw the line when considering indi- rect environmental effects and whether to analyze effects from other projects separate in time or place. See Department of Transportation v. Public Citizen, 541 U. S. 752, 767. In sum, when assessing signifcant environmental effects and feasible alternatives for purposes of NEPA, an agency will invariably make a series of fact-dependent, context- specifc, and policy-laden choices about the depth and breadth of its in- quiry—and also about the length, content, and level of detail of the re- sulting EIS. Courts should afford substantial deference and should not micromanage those agency choices so long as they fall within a broad zone of reasonableness. Even a defcient EIS does not necessarily re- quire vacating an agency's project approval, absent reason to believe that the agency might disapprove the project if it added more to the EIS. Cf. 5 U. S. C. § 706. Pp. 177–185. (b) Contrary to the D. C. Circuit's NEPA analysis, the Board's deter- mination that its EIS need not evaluate possible environmental effects from upstream and downstream projects separate from the Uinta Basin 170 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Syllabus Railway complied with NEPA's procedural requirements, particularly NEPA's textually mandated focus on the “proposed action” under agency review. While indirect environmental effects of the project it- self may fall within NEPA's scope even if they might extend outside the geographical territory of the project or materialize later in time, the fact that the project might foreseeably lead to the construction or in- creased use of a separate project does not mean the agency must con- sider that separate project's environmental effects. See Public Citi- zen, 541 U. S., at 767. This is particularly true where, as here, those separate projects fall outside the agency's regulatory authority. Pp. 186–191. (c) NEPA does not allow courts, “under the guise of judicial re- view” of agency compliance with NEPA, to delay or block agency projects based on the environmental effects of other projects separate from the project at hand. Vermont Yankee Nuclear Power Corp. v. Natural Resources De fense Council, Inc., 435 U. S. 519, 558. P. 192. 82 F. 4th 1152, reversed and remanded. Kavanaugh, J., delivered the opinion of the Court, in which Roberts, C. J., and Thomas, Alito, and Barrett, JJ., joined. Sotomayor, J., fled Page Proof Pending Publication an opinion concurring in the judgment, in which Kagan and Jackson, JJ., joined, post, p. 192. Gorsuch, J., took no part in the consideration or decision of the case. Paul D. Clement argued the cause for petitioners. With him on the briefs were Matthew D. Rowen, Kevin Wynosky, Jay C. Johnson, and Fred R. Wagner. Deputy Solicitor General Kneedler argued the cause for federal respondents urging reversal in part. With him on the briefs were Solicitor General Prelogar, Assistant Attor- ney General Kim, Colleen E. Roh Sinzdak, Robert J. Lund- man, Justin D. Heminger, Anika Sanders Cooper, and Bar- bara Miller. William M. Jay argued the cause for respondent Eagle County et al. With him on the brief were Jordan Bock, Nathaniel H. Hunt, Beth Oliver, and Christina Hooper. Kirti Datla fled a brief for environmental respondents. With her on the brief were Benjamin Chagnon, Linnet Cite as: 605 U. S. 168 (2025) 171 Counsel Davis-Stermitz, Eric Glitzenstein, Wendy Park, and Ed- ward B. Zukoski.* *Briefs of amici curiae urging reversal were fled for the State of Loui- siana et al. by Elizabeth B. Murrill, Attorney General of Louisiana, J. Benjamin Aguiñaga, Solicitor General, Kelsey L. Smith, Deputy Solicitor General, and Caitlin A. Huettemann, Assistant Solicitor General, and by the Attorneys General for their respective States as follows: Steve Mar- shall of Alabama, Treg Taylor of Alaska, Tim Griffn of Arkansas, Ashley Moody of Florida, Christopher M. Carr of Georgia, Raúl R. Labrador of Idaho, Theodore E. Rokita of Indiana, Brenna Bird of Iowa, Russell Cole- man of Kentucky, Lynn Fitch of Mississippi, Andrew Bailey of Missouri, Austin Knudsen of Montana, Michael T. Hilgers of Nebraska, Drew H. Wrigley of North Dakota, Dave Yost of Ohio, Gentner Drummond of Okla- homa, Alan Wilson of South Carolina, Marty Jackley of South Dakota, Jonathan Skrmetti of Tennessee, Ken Paxton of Texas, Jason Miyares of Virginia, Patrick Morrisey of West Virginia, and Bridget Hill of Wyo- ming; for the State of Utah by Sean D. Reyes, Attorney General of Utah, and Stanford E. Purser, Solicitor General; for the American Exploration and Mining Association et al. by Michael R. Huston, Christopher D. Page Proof Pending Publication Thomas, and Andrea J. Driggs; for the American Forest Resource Council et al. by Ivan L. London; for the Americans for Prosperity Foundation et al. by Michael Pepson and Dan Greenberg; for the Association of Amer- ican Railroads by Daniel Saphire; for the Center for American Liberty by Harmeet K. Dhillon; for the Center for Environmental Accountability by Paul E. Salamanca; for the Chamber of Commerce of the United States of America et al. by Kyle D. Hawkins, Michael B. Schon, Andrew R. Varcoe, Stephanie A. Maloney, Ellen Steen, and Travis Cushman; for Energy Transfer LP by William S. Scherman and Matthew X. Etchemendy; for Law Professors by Mario A. Loyola and Richard A. Epstein; for the NACCO Natural Resources Corp. by Charles T. Wehland and Jeffery D. Ubersax; for NextDecade LNG, LLC, by Richard M. Loeb and Andrew D. Silverman; and for U. S. Sen. John Barrasso et al. by Michael Busch- bacher. Jeffrey S. Rasmussen fled a brief for the Ute Indian Tribe of the Uintah and Ouray Reservation et al. urging vacatur. Briefs of amici curiae urging affrmance were fled for the State of Colorado et al. by Philip J. Weiser, Attorney General of Colorado, Natalie Hanlon Leh, Chief Deputy Attorney General, Shannon W. Stevenson, So- licitor General, Kurtis T. Morrison and Scott Steinbrecher, Deputy Attor- neys General, Carrie Noteboom, Assistant Deputy Attorney General, Cory Haller, Assistant Solicitor General, and Brea Hinricks, Assistant 172 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court Justice Kavanaugh delivered the opinion of the Court. Some 55 years ago, Congress passed and President Nixon signed the National Environmental Policy Act, known as NEPA. For certain infrastructure projects that are built, funded, or approved by the Federal Government, NEPA re- quires federal agencies to prepare an environmental impact statement, or EIS. The EIS must address the signifcant environmental effects of a proposed project and identify fea- sible alternatives that could mitigate those effects. NEPA was the frst of several landmark environmental laws enacted by Congress in the 1970s. Subsequent stat- utes included the Clean Air Amendments of 1970, the Clean Water Act of 1972, and the Endangered Species Act of 1973, among others. Attorney General, by Brian Schwalb, Attorney General of the District of Columbia, and by the Attorneys General for their respective States as follows: William Tong of Connecticut, Kathy Jennings of Delaware, Page Proof Pending Publication Kwame Raoul of Illinois, Aaron M. Frey of Maine, Andrea Joy Campbell of Massachusetts, Dana Nessel of Michigan, Keith Ellison of Minnesota, Aaron D. Ford of Nevada, Matthew J. Platkin of New Jersey, Letitia James of New York, Ellen Rosenblum of Oregon, Peter Neronha of Rhode Island, Charity R. Clark of Vermont, and Robert W. Ferguson of Washing- ton; for Colorado Communities by William S. Eubanks II, Matthew R. Arnold, and Barbara Green; for the Constitutional Accountability Center by Elizabeth B. Wydra and Brianne J. Gorod; for Former Council on Envi- ronmental Quality Offcials by Sean H. Donahue, Megan M. Herzog, Keri R. Davidson, and David T. Goldberg; for the Howard University School of Law Civil Rights Clinic by Amit Jain; for the Institute for Policy Integ- rity at New York University School of Law by Jason A. Schwartz; and for 30 Members of the U. S. House and Senate by Xiao Wang and Cale Jaffe. Briefs of amici curiae were fled for the American Petroleum Institute et al. by Hadassah M. Reimer, Sarah Bordelon, and Tina R. Van Bockern; for the American Planning Association by John M. Baker and Katherine M. Swenson; for the Anschutz Exploration Corp. by Tina R. Van Bockern and Mark D. Gibson; for Former Senior Federal Offcials by Beth C. Neit- zel; for the Interstate Natural Gas Association of America et al. by Donald P. Salzman and James P. Danly; and for the Property and Environment Research Center by Jonathan Wood. Cite as: 605 U. S. 168 (2025) 173 Opinion of the Court Unlike those later-enacted laws, however, NEPA imposes no substantive environmental obligations or restrictions. NEPA is a purely procedural statute that, as relevant here, simply requires an agency to prepare an EIS—in essence, a report. Importantly, NEPA does not require the agency to weigh environmental consequences in any particular way. Rather, an agency may weigh environmental consequences as the agency reasonably sees ft under its governing statute and any relevant substantive environmental laws. Simply stated, NEPA is a procedural cross-check, not a substantive roadblock. The goal of the law is to inform agency decisionmaking, not to paralyze it. In this case, the U. S. Surface Transportation Board con- sidered a proposal by a group of seven Utah counties for the construction and operation of an approximately 88-mile railroad line in northeastern Utah. Under federal law, the Board determines whether to approve construction of new Page Proof Pending Publication railroad lines. The railroad line here would connect Utah's oil-rich Uinta Basin—a rural territory roughly the size of the State of Maryland—to the national rail network. By doing so, the new railroad line would facilitate the transpor- tation of crude oil from Utah to refneries in Louisiana, Texas, and elsewhere. And the project would bring signif- cant economic development and jobs to the isolated Uinta Basin by better connecting the Basin to the national economy. For that proposed 88-mile Utah railroad line, the Board prepared an extraordinarily lengthy EIS, spanning more than 3,600 pages of environmental analysis. The Board's EIS addressed the environmental effects of the railroad line. But the U. S. Court of Appeals for the D. C. Circuit nonethe- less faulted the EIS for not suffciently considering the envi- ronmental effects of projects separate from the railroad line itself—primarily, the environmental effects that could ensue from (i) increased oil drilling upstream in the Uinta Basin 174 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court and (ii) increased oil refning downstream along the Gulf Coast of Louisiana and Texas. On that basis, the D. C. Circuit vacated the Board's EIS and the Board's approval of the 88-mile railroad line. As a result, construction still has not begun even though the Board approved the project back in December 2021. We reverse. First, the D. C. Circuit did not afford the Board the substantial judicial deference required in NEPA cases. Second, the D. C. Circuit ordered the Board to ad- dress the environmental effects of projects separate in time or place from the construction and operation of the railroad line. But NEPA requires agencies to focus on the environ- mental effects of the project at issue. Under NEPA, the Board's EIS did not need to address the environmental ef- fects of upstream oil drilling or downstream oil refning. Rather, it needed to address only the effects of the 88-mile railroad line. And the Board's EIS did so. Page Proof Pending I Publication Under federal law, new railroad construction and opera- tion must frst be approved by the U. S. Surface Transporta- tion Board. 49 U. S. C. § 10901. After receiving an applica- tion for a new railroad line, the Board issues a public notice and initiates an agency proceeding to review the proposal; alternatively, the Board may streamline approval through a statutory exemption process. §§ 10101, 10502, 10901. In addition, for covered projects, NEPA compels the Board to prepare an environmental impact statement, or EIS. In 2020, the Seven County Infrastructure Coalition—a group of seven Utah counties—applied to the Board for ap- proval of an 88-mile railroad line in northeastern Utah. The new railroad line would connect the Uinta Basin with the interstate freight rail network—and via that network, to re- fneries in Louisiana, Texas, and other destinations. The Uinta Basin contains signifcant quantities of crude oil and other fossil fuels. The Uinta Basin Railway would Cite as: 605 U. S. 168 (2025) 175 Opinion of the Court provide oil producers a more effcient option for transporting oil out of the Basin to refneries. As of now, oil from the Basin is carried by trucks that must navigate mountain passes on narrow roads, a diffcult and slow journey in any season. The Board's environmental review of the Uinta Basin Rail- way followed standard NEPA procedures. In October 2020, the Board issued a draft EIS and invited public comment. During the public comment period, the Board held six public meetings and collected more than 1,900 comments. In Au- gust 2021, the Board published its fnal EIS. All told, the Board's fnal EIS clocked in at more than 3,600 pages. The EIS identifed and analyzed numerous “signif- cant and adverse impacts that could occur as a result” of the railroad line's construction and operation—including disrup- tions to local wetlands, land use, and recreation. App. 121; see id., at 94–105, 121–126, 206–347. The EIS likewise ad- Page Proof Pending Publication dressed several “minor impacts,” such as air pollution and big-game movement around the construction site. Id., at 126; see id., at 126–134, 251–259, 309–325. The EIS also noted, but did not fully analyze, the potential effects of increased upstream oil drilling in the Uinta Basin and increased downstream refning of crude oil carried by the railroad. Id., at 135, 348–482, 511–516, 520–534, 539–543. As to the environmental effects of upstream oil drilling, the EIS explained why further analysis of those “potential future, as yet unplanned, oil and gas development projects” was not needed. Id., at 520. To begin with, the project at issue was an 88-mile railroad line, not an oil well or a drilling permit in the Uinta Basin. Moreover, the Board possesses “no authority or control over potential future oil and gas de- velopment” in the Basin. Id., at 522. Future projects would be “subject to the approval processes of other federal, state, local, and tribal agencies.” Ibid. In any event, the environmental effects of future oil and gas development in 176 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court the Basin are “speculative” and attenuated from the project at hand. Id., at 525; see id., at 525–527 (citing Department of Transportation v. Public Citizen, 541 U. S. 752, 767–768, 770 (2004)). As for the environmental effects of downstream oil refn- ing projects, the Board recognized that “trains originating on the proposed rail line would transport crude oil to mar- kets in other regions of the United States,” such as Louisiana and Texas, and that oil refning (and the associated effects on the environment) could increase in those locations as a result. App. 477; see id., at 477–482. But the identity of specifc destinations “would depend on the ability and will- ingness of refneries in other markets to receive rail cars carrying Uinta Basin crude oil and process the oil in their refneries.” Id., at 477. Moreover, the Board “would have no role in approving or regulating the production, refning, or use” of Uinta Basin crude oil. Id., at 540–541. So the Page Proof Pending Publication Board did not fully evaluate the effects of additional oil re- fning along the Gulf Coast. In December 2021, a few months after issuing the fnal EIS, the Board approved the construction and operation of the Uinta Basin Railway. Recognizing that “rail construc- tion projects are in the public interest,” the Board concluded that the new railroad line would “have substantial transpor- tation and economic benefts,” and that those benefts out- weighed the environmental impacts identifed in the EIS. App. to Pet. for Cert. 121a, 119a; see id., at 118a–121a. In the wake of the Board's fnal approval, a Colorado county and several environmental organizations sued by fl- ing petitions for review in the U. S. Court of Appeals for the D. C. Circuit. The D. C. Circuit found “numerous NEPA violations aris- ing from the EIS.” Eagle Cty. v. Surface Transp. Bd., 82 F. 4th 1152, 1196 (2023). In the court's view, the Board “failed” to take “the requisite `hard look' at all of the envi- ronmental impacts of the Railway.” Id., at 1175. Cite as: 605 U. S. 168 (2025) 177 Opinion of the Court Specifcally, the Court of Appeals held that the Board im- permissibly limited its analysis of upstream and downstream projects. The court concluded that the environmental ef- fects from oil drilling in the Uinta Basin and oil refning along the Gulf Coast were “ `reasonably foreseeable im- pacts' ” that the EIS should have analyzed more extensively. Id., at 1177. The court rejected the Board's argument that those effects would arise from other projects (upstream oil drilling, downstream oil refning, and the like) that are sepa- rate from the current project and regulated by other agen- cies. Id., at 1177–1180 (citing Sierra Club v. FERC, 867 F. 3d 1357, 1372–1375 (CADC 2017) (Sabal Trail)). Based on the defciencies it found in the EIS, the Court of Appeals vacated the EIS and the Board's fnal approval order. 82 F. 4th, at 1196. The Coalition and the Uinta Basin Railway sought review in this Court, and we granted certiorari. 602 U. S. 1038 (2024). Page Proof Pending II Publication For certain infrastructure projects that are built, funded, or approved by the Federal Government, NEPA requires federal agencies to prepare an environmental impact state- ment, or EIS, identifying signifcant environmental effects of the projects, as well as feasible alternatives. The law en- sures that the agency and the public are aware of the envi- ronmental consequences of proposed projects. Properly ap- plied, NEPA helps agencies to make better decisions and to ensure good project management. Importantly, however, NEPA is purely procedural. In ul- timately deciding whether to build, fund, or approve a proj- ect, an “agency is not constrained by NEPA from deciding that other values outweigh the environmental costs.” Rob- ertson v. Methow Valley Citizens Council, 490 U. S. 332, 350 (1989). Otherwise stated, NEPA “does not mandate partic- ular results, but simply prescribes the necessary process” for an agency's environmental review of a project. Ibid.; see 178 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court Department of Transportation v. Public Citizen, 541 U. S. 752, 756–757 (2004); Marsh v. Oregon Natural Resources Council, 490 U. S. 360, 370–372 (1989); Baltimore Gas & Elec. Co. v. Natural Resources Defense Council, Inc., 462 U. S. 87, 97–98 (1983); Strycker's Bay Neighborhood Council, Inc. v. Karlen, 444 U. S. 223, 227–228 (1980); Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U. S. 519, 558 (1978); Kleppe v. Sierra Club, 427 U. S. 390, 410, n. 21 (1976).1 Here, the Board's EIS evaluated the environmental effects of the proposed 88-mile railroad line in Utah's rural Uinta Basin. But the D. C. Circuit, following Circuit precedent applying NEPA, concluded that the EIS did not suffciently address the reasonably foreseeable environmental impacts of increased upstream oil drilling in the Uinta Basin, as well as the environmental effects of increased downstream oil refn- ing along the Gulf Coast. 82 F. 4th, at 1196. Page 1 Proof As it was phrased at the Pending Publication time of the Board's EIS (before a 2023 amend- ment to the statute, see n. 3, infra), NEPA directed federal agencies to “include in every recommendation or report on proposals for legisla- tion and other major Federal actions signifcantly affecting the quality of the human environment, a detailed statement by the responsible off- cial on— “(i) the environmental impact of the proposed action, “(ii) any adverse environmental effects which cannot be avoided should the proposal be implemented, “(iii) alternatives to the proposed action, “(iv) the relationship between local short-term uses of man's environ- ment and the maintenance and enhancement of long-term productivity, and “(v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented. “Prior to making any detailed statement, the responsible Federal offcial shall consult with and obtain the comments of any Federal agency which has jurisdiction by law or special expertise with respect to any environ- mental impact involved.” § 102(2)(C), 83 Stat. 853, as amended, 42 U. S. C. § 4332(2)(C) (2018). Cite as: 605 U. S. 168 (2025) 179 Opinion of the Court As we will explain, we disagree with the D. C. Circuit's decision on two grounds. First, the court did not afford the Board the substantial judicial deference required in NEPA cases. Second, the court incorrectly interpreted NEPA to require the Board to consider the environmental effects of upstream and downstream projects that are separate in time or place from the Uinta Basin Railway. A Since the early 1970s, federal courts have reviewed NEPA cases. Over time, some courts have assumed an aggressive role in policing agency compliance with NEPA. Other courts have adopted a more restrained approach. In light of the continuing confusion and disagreement in the Courts of Appeals over how to handle NEPA cases, we think it im- portant to reiterate and clarify the fundamental principles of judicial review applicable in those cases. As we will ex- Page Proof Pending Publication plain, the central principle of judicial review in NEPA cases is deference.2 As a general matter, when an agency interprets a statute, judicial review of the agency's interpretation is de novo. See Loper Bright Enterprises v. Raimondo, 603 U. S. 369, 391–392 (2024). But when an agency exercises discretion granted by a statute, judicial review is typically conducted 2 Some have debated whether Congress and the President in 1970 actu- ally intended or anticipated judicial review of agency compliance with NEPA. See R. Lazarus, The National Environmental Policy Act in the U. S. Supreme Court: A Reappraisal and a Peek Behind the Curtains, 100 Geo. L. J. 1507, 1515 (2012) (describing the history). In any event, an early D. C. Circuit case concluded that an agency's compliance with NEPA was judicially reviewable. See Calvert Cliffs' Coordinating Comm., Inc. v. U. S. Atomic Energy Comm'n, 449 F. 2d 1109 (1971). And this Court's cases have treated NEPA compliance as judicially reviewable. That said, courts must conduct their review with signifcant deference to the agency. When reviewing compliance with NEPA, “courts are to play only a limited role.” Vermont Yankee Nuclear Power Corp. v. Natural Resources De- fense Council, Inc., 435 U. S. 519, 558 (1978). 180 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court under the Administrative Procedure Act's deferential arbitrary-and-capricious standard. Under that standard, a court asks not whether it agrees with the agency decision, but rather only whether the agency action was reasonable and reasonably explained. See Motor Vehicle Mfrs. Assn. of United States, Inc. v. State Farm Mut. Automobile Ins. Co., 463 U. S. 29, 43 (1983); FCC v. Prometheus Radio Proj- ect, 592 U. S. 414, 423 (2021). When a party argues that an agency action was arbitrary and capricious due to a defciency in an EIS, the reviewing court must account for the fact that NEPA is a purely proce- dural statute. Under NEPA, an agency's only obligation is to prepare an adequate report. “NEPA requires no more.” Strycker's Bay Neighborhood Council, 444 U. S., at 228. Unlike a plethora of other federal environmental statutes (such as the Clean Air Act, the Clean Water Act, etc.), NEPA imposes no substantive constraints on the agency's ultimate Page Proof Pending Publication decision to build, fund, or approve a proposed project. So when reviewing an agency's EIS, “the only role for a court” is to confrm that the agency has addressed environmental consequences and feasible alternatives as to the relevant project. Id., at 227; see Vermont Yankee, 435 U. S., at 551, 555. Because an EIS is only one input into an agency's deci- sion and does not itself require any particular substantive outcome, the adequacy of an EIS is relevant only to the ques- tion of whether an agency's fnal decision (here, to approve the railroad) was reasonably explained. In short, when determining whether an agency's EIS com- plied with NEPA, a court should afford substantial deference to the agency. In practice, judicial deference in NEPA cases can take sev- eral forms. For example, NEPA says that the EIS should be “detailed.” 42 U. S. C. § 4332(2)(C). Of course, the meaning of “detailed” is a question of law to be decided by a court. Loper Bright, 603 U. S., at 391–392. But what de- tails need to be included in any given EIS? For the most Cite as: 605 U. S. 168 (2025) 181 Opinion of the Court part, that question does not turn on the meaning of “de- tailed”—instead, it “involves primarily issues of fact.” Marsh, 490 U. S., at 377. The agency is better equipped to assess what facts are relevant to the agency's own decision than a court is. As a result, “agencies determine whether and to what extent to prepare an EIS based on the useful- ness of any new potential information to the decisionmaking process.” Public Citizen, 541 U. S., at 767 (emphasis added). So the question of whether a particular report is detailed enough in a particular case itself requires the exer- cise of agency discretion—which should not be excessively second-guessed by a court. Brevity should not be mistaken for lack of detail. A relatively brief agency explanation can be reasoned and detailed; an EIS need not meander on for hundreds or thousands of pages. So courts should not insist on length as a prerequisite for fnding an EIS to be detailed.3 The EIS also must identify signifcant environmental im- pacts and feasible alternatives. But there too, an agency Page Proof Pending Publication exercises substantial discretion. An agency must make pre- dictive and scientifc judgments in assessing the relevant im- pacts (what are the likely impacts; do they rise to the level of “signifcant”?) and alternatives (what are the potential al- ternatives; are they really “feasible”?). As this Court has said, “the term `alternatives' is not self-defning,” and “[c]om- mon sense” should be brought to bear. Vermont Yankee, 3 Indeed, federal law now strictly prohibits an agency's EIS from going on endlessly. In 2023, two years after the Board issued its fnal EIS for the Uinta Basin Railway, Congress passed and President Biden signed an Act amending NEPA meaningfully titled the “Building United States Infrastructure through Limited Delays and Effcient Reviews Act of 2023.” Pub. L. 118–5, Div. C, Tit. III, § 321, 137 Stat. 38–39. Under that BUILDER Act, an EIS “shall not exceed 150 pages” and must be com- pleted in “2 years” or less. Id., at 41–42 (42 U. S. C. §§ 4336a(e)(1)(A), (g)(1)(A)). That Act strongly reinforces the basic principles that NEPA, correctly interpreted, already embodied but that have been too often over- looked. The analysis in this opinion thus applies to NEPA as amended by the BUILDER Act. 182 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court 435 U. S., at 551. Black-letter administrative law instructs that when an agency makes those kinds of speculative as- sessments or predictive or scientifc judgments, and decides what qualifes as signifcant or feasible or the like, a review- ing court must be at its “most deferential.” Baltimore Gas & Elec., 462 U. S., at 103; see Marsh, 490 U. S., at 378; State Farm, 463 U. S., at 43. In preparing an EIS, an agency also must determine the scope of the environmental effects that it will address. The textual focus of NEPA is the “proposed action”—that is, the project at hand. 42 U. S. C. § 4332(2)(C) (2018). The agency therefore will obviously seek to assess signifcant effects from the project at issue. But how far will the agency go in considering the indirect effects that might occur outside the area of the immediate project—for example, due to emissions or run off from the project carried elsewhere by air or water? And will the agency evaluate the environmental effects from Page Proof Pending Publication other future or geographically separate projects that may be initiated (or expanded) as a result of or in the wake of the current project? And what if another agency also possesses regulatory authority over a related project? In analyzing those scope questions, it is critical to disag- gregate the agency's role from the court's role. So long as the EIS addresses environmental effects from the project at issue, courts should defer to agencies' decisions about where to draw the line—including (i) how far to go in considering indirect environmental effects from the project at hand and (ii) whether to analyze environmental effects from other projects separate in time or place from the project at hand. On those kinds of questions, as this Court has often said, agencies possess discretion and must have broad latitude to draw a “ `manageable line.' ” Public Citizen, 541 U. S., at 767 (quoting Metropolitan Edison Co. v. People Against Nu- clear Energy, 460 U. S. 766, 774, n. 7 (1983)). To tie all of this together: When assessing signifcant envi- ronmental effects and feasible alternatives for purposes of Cite as: 605 U. S. 168 (2025) 183 Opinion of the Court NEPA, an agency will invariably make a series of fact- dependent, context-specifc, and policy-laden choices about the depth and breadth of its inquiry—and also about the length, content, and level of detail of the resulting EIS. Courts should afford substantial deference and should not micromanage those agency choices so long as they fall within a broad zone of reasonableness. As the Court has empha- sized on several occasions, and we doubly underscore again today, “inherent in NEPA . . . is a `rule of reason,' which ensures that agencies determine whether and to what extent to prepare an EIS based on the usefulness of any new poten- tial information to the decisionmaking process.” Public Citizen, 541 U. S., at 767. A reviewing court may not “sub- stitute its judgment for that of the agency as to the environ- mental consequences of its actions.” Kleppe, 427 U. S., at 410, n. 21. Some courts have strayed and not applied NEPA with the Page Proof Pending Publication level of deference demanded by the statutory text and this Court's cases. Those decisions have instead engaged in overly intrusive (and unpredictable) review in NEPA cases. Those rulings have slowed down or blocked many projects and, in turn, caused litigation-averse agencies to take ever more time and to prepare ever longer EISs for future projects. The upshot: NEPA has transformed from a modest proce- dural requirement into a blunt and haphazard tool employed by project opponents (who may not always be entirely moti- vated by concern for the environment) to try to stop or at least slow down new infrastructure and construction proj- ects. Some project opponents have invoked NEPA and sought to enlist the courts in blocking or delaying even those projects that otherwise comply with all relevant substantive environmental laws. Indeed, certain project opponents have relied on NEPA to fght even clean-energy projects— from wind farms to hydroelectric dams, from solar farms to geothermal wells. See, e. g., Brief for Chamber of Com- 184 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court merce of the United States of America, et al. as Amici Cu- riae 19–20. All of that has led to more agency analysis of separate projects, more consideration of attenuated effects, more ex- ploration of alternatives to proposed agency action, more speculation and consultation and estimation and litigation. Delay upon delay, so much so that the process sometimes seems to “borde[r] on the Kafkaesque.” Vermont Yankee, 435 U. S., at 557. Fewer projects make it to the fnish line. Indeed, fewer projects make it to the starting line. Those that survive often end up costing much more than is antici- pated or necessary, both for the agency preparing the EIS and for the builder of the project. And that in turn means fewer and more expensive railroads, airports, wind turbines, transmission lines, dams, housing developments, highways, bridges, subways, stadiums, arenas, data centers, and the like. And that also means fewer jobs, as new projects be- Page Proof Pending Publication come diffcult to fnance and build in a timely fashion. A 1970 legislative acorn has grown over the years into a judicial oak that has hindered infrastructure development “under the guise” of just a little more process. Id., at 558. A course correction of sorts is appropriate to bring judicial review under NEPA back in line with the statutory text and common sense. Id., at 525. Congress did not design NEPA for judges to hamstring new infrastructure and construction projects. On the contrary, as this Court has stressed, courts should and “must defer to `the informed discretion of the responsible federal agencies.' ” Marsh, 490 U. S., at 377. Critically, as the Government and the Coalition explained at oral argument, courts not only must defer to the agency's reasonable choices regarding the scope and contents of the EIS, but also must keep in mind that review of an agency's EIS is not the same thing as review of the agency's fnal decision concerning the project. See Tr. of Oral Arg. 31–32, 70–71. That, too, follows from NEPA's status as a purely procedural statute. The ultimate question is not whether Cite as: 605 U. S. 168 (2025) 185 Opinion of the Court an EIS in and of itself is inadequate, but whether the agency's fnal decision was reasonable and reasonably ex- plained. Review of an EIS is only one component of that analysis. Even if an EIS falls short in some respects, that defciency may not necessarily require a court to vacate the agency's ultimate approval of a project, at least absent rea- son to believe that the agency might disapprove the project if it added more to the EIS. Cf. 5 U. S. C. § 706. For exam- ple, in a case like this one, even if the EIS drew the line on the effects of separate upstream or downstream projects too narrowly, that mistake would not necessarily require a court to vacate the agency's approval of the railroad project. Cf. Vermont Yankee, 435 U. S., at 558.4 In other words, as this Court has said before, NEPA does not authorize a court to “ `interject itself within the area of discretion . . . as to the choice of the action to be taken' ” by the agency. Strycker's Bay Neighborhood Council, 444 Page Proof Pending Publication U. S., at 227–228 (quoting Kleppe, 427 U. S., at 410, n. 21). NEPA's procedural mandate helps “to insure a fully in- formed and well-considered decision, not necessarily a deci- sion the judges of the Court of Appeals or of this Court would have reached had they been members of the decisionmaking unit of the agency.” Vermont Yankee, 435 U. S., at 558. The “role of a court in reviewing the suffciency of an agency's consideration of environmental factors is a limited one.” Id., at 555. The bedrock principle of judicial review in NEPA cases can be stated in a word: Deference. 4 When, unlike this case, an agency denies approval of a project, the denied applicant may ordinarily challenge the denial under the APA or the relevant agency's governing statute. The denied applicant may argue, among other things, that the agency acted unreasonably in denying ap- proval by weighing environmental consequences too heavily in light of the agency's governing statute and other relevant factors, or perhaps that the agency erred because the governing statute did not allow the agency to weigh environmental consequences at all. NEPA does not alter those judicial inquiries. 186 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court B Even apart from failing to afford suffcient deference to the Surface Transportation Board, the D. C. Circuit's deci- sion was mistaken on the merits under NEPA. The D. C. Circuit erroneously required the Board to address environ- mental effects from projects that are separate in time or place from the 88-mile railroad project at hand—that is, ef- fects from potential future projects or from geographically separate projects. Moreover, those separate projects fall outside the Board's authority and would be initiated, if at all, by third parties. In its EIS, the Board determined that upstream oil drilling in the Uinta Basin and downstream oil refning along the Gulf Coast were separate from the construction and opera- tion of the 88-mile railroad line. The Board's EIS explained that the “proposed rail line and any future oil and gas devel- opment projects are not two phases of a single action,” but Page Proof Pending Publication “separate, independent projects.” App. 523. Those other projects, the Board reasoned, should not be considered “part of the proposed action assessed in the EIS.” Ibid. The Board concluded that its EIS need not evaluate the possible environmental effects from separate upstream or down- stream projects.5 The Board's approach complied with NEPA and this Court's longstanding NEPA precedents. Importantly, the textually mandated focus of NEPA is the “proposed ac- 5 Even though not mandated by NEPA to do so, the Board did identify some of the potential effects and marginal risks from projects separate from the 88 miles of additional railroad track in rural Utah. See, e. g., App. 354–358 (forecasting the number of oil wells that could be added in the Uinta Basin as a result of increased production spurred by the new railway); id., at 420–423, 539–542 (evaluating effects from increased oil refning along the Gulf Coast). The Board should not necessarily earn bonus points for studying more than NEPA demanded. But it should defnitely not receive a failing grade just because its 3,600-page EIS was less thorough in analyzing the effects from other projects than the Court of Appeals might have preferred. Cite as: 605 U. S. 168 (2025) 187 Opinion of the Court tion”—that is, the project at hand—not other future or geo- graphically separate projects that may be built (or expanded) as a result of or in the wake of the immediate project under consideration. 42 U. S. C. § 4332(2)(C) (2018); see Aber- deen & Rockfsh R. Co. v. Students Challenging Regulatory Agency Procedures (SCRAP), 422 U. S. 289, 322–324 (1975); Kleppe, 427 U. S., at 398–402. Therefore, when the effects of an agency action arise from a separate project—for exam- ple, a possible future project or one that is geographically distinct from the project at hand—NEPA does not require the agency to evaluate the effects of that separate project. To be clear, the environmental effects of the project at issue may fall within NEPA even if those effects might extend outside the geographical territory of the project or might materialize later in time—for example, run-off into a river that fows many miles from the project and affects fsh populations elsewhere, or emissions that travel downwind Page Proof Pending Publication and predictably pollute other areas. Those so-called indi- rect effects can sometimes fall within NEPA, as the Govern- ment explained at oral argument. See Tr. of Oral Arg. 59–63. But if the project at issue might lead to the construction or increased use of a separate project—for example, a housing development that might someday be built near a highway— the agency need not consider the environmental effects of that separate project. To put it in legal terms, the separate project breaks the chain of proximate causation between the project at hand and the environmental effects of the separate project. See Public Citizen, 541 U. S., at 767 (citing Metro- politan Edison, 460 U. S., at 774, and n. 7). The effects from a separate project may be factually foreseeable, but that does not mean that those effects are relevant to the agency's decisionmaking process or that it is reasonable to hold the agency responsible for those effects. Cf. Public Citizen, 541 U. S., at 766–767. In those circumstances, “the causal chain is too attenuated.” Metropolitan Edison, 460 U. S., at 774. 188 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court In other words, there is no “ `reasonably close causal relation- ship' ” between the project at hand and the environmental effects of those other projects. Public Citizen, 541 U. S., at 767 (quoting Metropolitan Edison, 460 U. S., at 774). Moreover, and importantly, the Board here possesses no regulatory authority over those separate projects. The Board does not regulate oil drilling, oil wells, oil and gas leases, or oil refneries. The Board approves railroad lines. See 49 U. S. C. §§ 10101, 10901. Other agencies possess au- thority to regulate those separate projects and their environ- mental effects. As this Court stated in one of the more im- portant sentences in the NEPA canon, “where an agency has no ability to prevent a certain effect due to its limited statu- tory authority over the relevant actions, the agency cannot be considered a legally relevant `cause' of the effect.” Pub- lic Citizen, 541 U. S., at 770. In other words, agencies are not required to analyze the effects of projects over which Page Proof Pending Publication they do not exercise regulatory authority. For that reason as well, there is no “ `reasonably close causal relationship' ” between the 88-mile railroad project at hand and the envi- ronmental effects of the separate oil drilling and oil refning projects. Id., at 767 (quoting Metropolitan Edison, 460 U. S., at 774); see also Robertson, 490 U. S., at 350–353; Ver- mont Yankee, 435 U. S., at 550–551, 558. To be sure, NEPA mandates that an agency “consult with” other agencies as appropriate. 42 U. S. C. § 4332(2)(C). But there is a vast difference between, for example, an agency's consulting with the Forest Service to determine the effects of a railroad line that would pass through a national forest and an agency's asking another agency to assess how 88 miles of additional track in rural Utah would contribute to emissions or climate change along the Gulf Coast. Indeed, “no rule of reason worthy of that title would require an agency to prepare an EIS” addressing effects from another project that is separate in time or place from the project at hand—particularly when it would require the agency to Cite as: 605 U. S. 168 (2025) 189 Opinion of the Court speculate about the effects of a separate project that is out- side its regulatory jurisdiction. Public Citizen, 541 U. S., at 767–768 (citing Aberdeen & Rockfsh R. Co., 422 U. S., at 325). In this case, the Uinta Basin Railway was the relevant project. NEPA therefore required the Board to consider the environmental effects of that 88-mile railroad line's con- struction and operation. To the extent that the new 88-mile railroad line could disrupt the habitat of protected species, or the new rail embankments could cause soil erosion into local bodies of water, or trains on the new line could pollute the air, NEPA dictated that the Board evaluate those effects. And consistent with NEPA, the Board here did comprehen- sively evaluate those effects, including via consultation with other agencies. As the D. C. Circuit itself recognized, the Board explained that “construction and operation of the Rail- way” would affect “water resources, air quality, [and] special status species like the greater sage-grouse.” 82 F. 4th, at Page Proof Pending Publication 1168. But nothing in NEPA required the Board to go fur- ther and study environmental impacts from upstream or downstream projects separate in time or place from the 88- mile railroad line's construction and operation. Under NEPA, it also bears emphasis, a mere “ `but for' causal relationship is insuffcient to make an agency responsi- ble for a particular effect.” Public Citizen, 541 U. S., at 767. Likewise, the fact that other projects might foreseeably be built or expanded in the wake of the current project does not, by itself, make the agency responsible for addressing the environmental effects of those other projects. The agency may draw what it reasonably concludes is a “ `manageable line' ”—one that encompasses the effects of the project at hand, but not the effects of projects separate in time or place. Ibid. (quoting Metropolitan Edison, 460 U. S., at 774, n. 7). True, a new airport may someday lead to a new stretch of highway; a new pipeline to a new power plant; a new housing development to a new subway stop. But the environmental effects of the project at hand constitute NEPA's textual 190 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Opinion of the Court focus. An agency need not assess the environmental effects of other separate projects simply because those projects (and effects) might not materialize but for the project at hand, or are in some sense foreseeable. Simply stated, a court may not invoke but-for causation or mere foreseeability to order agency analysis of the effects of every project that might somehow or someday follow from the current project. See Public Citizen, 541 U. S., at 767– 768; Metropolitan Edison, 460 U. S., at 774–775. NEPA calls for the agency to focus on the environmental effects of the project itself, not on the potential environmental effects of future or geographically separate projects. A relatively modest infrastructure project should not be turned into a scapegoat for everything that ensues from upstream oil drill- ing to downstream refnery emissions. As Justice Rehn- quist underscored in Vermont Yankee, NEPA is not a “game” where project objectors can engage in “unjustifed obstruc- Page Proof Pending Publication tionism”—here, for example, by raising a slew of remote ef- fects that they think “ `ought to be' considered.” 435 U. S., at 553–554. To be sure, in certain circumstances, other projects may be interrelated and close in time and place to the project at hand—a residential development next door to and built at the same time as a ski resort, for example. See, e. g., Rob- ertson, 490 U. S., at 338–340. The question then is whether that is a single project within the authority of the agency in question. There may be a gray area in defning the project at hand. Even in those circumstances, however, a court's review still must remain deferential, as we explained in Part II–A above. In other words, even if the reviewing court in such a case might think that NEPA would support drawing a different line, a court should defer to an agency so long as the agency drew a reasonable and “ `manageable line.' ” Public Citizen, 541 U. S., at 767 (quoting Metropolitan Edi- son, 460 U. S., at 774, n. 7). All of that is to again underscore that a difference may exist between what an agency should Cite as: 605 U. S. 168 (2025) 191 Opinion of the Court do as a matter of good policy and best practices under NEPA, and what a reviewing court may subsequently order an agency to do under NEPA. In this case, in any event, the NEPA question is not close. The Board did not need to evaluate potential environmental impacts of the separate upstream and downstream projects. As to other projects upstream, the EIS rightly explained that the environmental consequences of future oil drilling in the Basin are distinct from construction and operation of the railroad line. App. 525–527. As for other projects down- stream, the Board likewise correctly explained that any envi- ronmental effects from highly regulated oil refneries along the Gulf Coast are well outside the scope of the 88-mile rail- road project in rural Utah. Id., at 420–423, 539–542.6 An agency may decline to evaluate environmental effects from separate projects upstream or downstream from the project at issue. Public Citizen, 541 U. S., at 770. Here, Page Proof Pending Publication the Board's EIS concluded that the “proposed rail line and any future oil and gas development projects are not two phases of a single action,” but “separate, independent proj- ects.” App. 523. So the Board concluded that they need not be considered “part of the proposed action assessed in the EIS.” Ibid. Absolutely correct. 6 In addition, inherent in Board approval of railroad lines is the under- standing that any new freight railroad may transport different kinds of cargo over an approved line—from corn to cars to coal and the like. See Brief for Association of American Railroads as Amicus Curiae 2, 8–9. As common carriers, railroads subject to the Board's jurisdiction are required to provide “transportation or service on reasonable request” to any person or commodity. 49 U. S. C. §§ 11101(a), 10102(9). Railroad lines approved by the Board cannot decline to provide “common carrier” transport based on the product or commodity to be carried. § 11101(a). For that addi- tional reason, the EIS here correctly explained that the Board was “not required to analyze impacts related to the destinations or end uses of any such products or commodities” transported by the 88-mile railroad line, including Uinta Basin crude oil. App. 422; see Department of Transpor- tation v. Public Citizen, 541 U. S. 752, 766–770 (2004). 192 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Sotomayor, J., concurring in judgment * * * In deciding cases involving the American economy, courts should strive, where possible, for clarity and predictability. Some courts' NEPA decisions have fallen short of that objec- tive. The proper judicial approach for NEPA cases is straightforward: Courts should review an agency's EIS to check that it addresses the environmental effects of the proj- ect at hand. The EIS need not address the effects of sepa- rate projects. In conducting that review, courts should af- ford substantial deference to the agency as to the scope and contents of the EIS. Plaintiffs' policy objections to this 88-mile Utah railroad may or may not be persuasive. But neither “the language nor the history of NEPA suggests that it was intended to give citizens a general opportunity to air their policy objec- tions to proposed federal actions. The political process, and not NEPA, provides the appropriate forum in which to air Page Proof Pending Publication policy disagreements.” Metropolitan Edison, 460 U. S., at 777. Citizens may not enlist the federal courts, “under the guise of judicial review” of agency compliance with NEPA, to delay or block agency projects based on the environmental effects of other projects separate from the project at hand. Vermont Yankee, 435 U. S., at 558. We reverse the judgment of the Court of Appeals and re- mand the case for further proceedings consistent with this opinion. It is so ordered. Justice Gorsuch took no part in the consideration or de- cision of this case. Justice Sotomayor, with whom Justice Kagan and Justice Jackson join, concurring in the judgment. The National Environmental Policy Act improves agency decisionmaking by requiring agencies to consider environ- mental impacts for which their decisions would be responsi- Cite as: 605 U. S. 168 (2025) 193 Sotomayor, J., concurring in judgment ble. I agree with the Court that the Surface Transportation Board would not be responsible for the harms caused by the oil industry, even though the railway it approved would de- liver oil to refneries and spur drilling in the Uinta Basin. I reach that conclusion because, under its organic statute, the Board had no authority to reject petitioners' application on account of the harms third parties would cause with products transported on the proposed railway. The majority takes a different path, unnecessarily grounding its analysis largely in matters of policy. Accordingly, I write separately to ex- plain why the result in this case follows inexorably from our precedent. I A The Uinta Basin spans thousands of square miles across northwestern Utah and Colorado. Bookended by the Uinta Mountains in the north and the Roan Cliffs in the south, the Page Proof Pending Publication Basin is hard to access and has few residents. The Basin, however, contains “ `extensive deposits of valuable miner- als,' ” including large reserves of “waxy crude,” a form of petroleum known for its thick consistency at ambient tem- peratures. 82 F. 4th 1152, 1165–1166 (CADC 2023). For over a decade, oil producers have transported this oil out of the Basin in heated tanker trucks, to be sold to refneries in Utah and beyond. Petitioners, the Seven County Infrastructure Coalition and the Uinta Basin Railway, LLC, plan to build a railway connecting the Uinta Basin with the Union Pacifc Railroad Company station in Kyune, Utah, and from there to the na- tional rail network. As the Coalition recognizes, “the Rail- way's predominant and expected primary purpose would be” to enable Basin oil producers to transport, with greater ease and in greater quantities, waxy crude to refneries in the Gulf Coast. Ibid. Nearly all the waxy crude transported by train out of the Uinta Basin would continue its travels 194 SEVEN COUNTY INFRASTRUCTURE COALITION v. EAGLE COUNTY Sotomayor, J., concurring in judgment over the Union Pacifc track from Kyune to Denver, which runs through Eagle County, Colorado, and closely abuts the Colorado River. B No person may “construct an additional railroad line” or “provide transportation over . . . an extended or additional railroad line” without a certifcate of approval from the Sur- face Transportation Board. 49 U. S. C. § 10901(a). Appli- cants can fle a formal application for such a certifcate, § 10901(c), or they can seek approval through an abbreviated exemption process, § 10502(a). In either case, the Act ex- presses a clear presumption in favor of approving railways. See ibid. (exemptions must be granted “to the maximum ex- tent” consistent with law); § 10901(c) (the Board “shall” issue a certifcate “unless” inconsistent with public convenience and necessity). In May 2020, petitioners requested permission to build the Page Proof Pending Publication Railway by way of the exemption procedure. Because the proposed railway constitutes a “major Federal actio[n] sig- nifcantly affecting” the environment, the National Environ- mental Policy Act (NEPA) required the Board to prepare a “detailed” statement addressing its environmental impacts. 42 U. S. C. § 4332(C). The Board conditionally approved petitioners' request based on the Rai