By the Court. Ingraham, First J.

The plaintiff seeks to recover from the defendant under the mechanics’ lien law for work done by him for the contractor with the owner.

The referee has found—

That the defendant (the owner) made.a contract with George W. Burwick to erect on his land an addition to liis brewery.

That there was no stipulation in respect to the sum or price to be paid'except that the labor was to be by days’ work.

That the plaintiff did furnish the materials as claimed by him.

•■. And that before the building was completed Burwick.absconded and discontinued the work. ‘

■. -Erom the evidence,; it. appears that the work'was abandoned before the'building was inclosed.

The right of .the plaintiff to .recover depends- upon the question whether-the contractor had a claim-which be. could. have enforced’against-the owner at any-time before he absconded. If there was nothing then due from the owner, there is no fund' out. of-which the claim can be collected- from the defendant.

If- there was any contract in the case (as to which I express no opinion, the referee having -found that there was one) it was an entire contract-, and not divisible as to the time of payment. The agreement was,-to erect an addition, to a building without any specification as to the time of' payment. The law in such case requires, the whole work to be done before the contractor can .call for his payment.

A mere voluntary payment on-.-account does not alter, the rights of. the-parties. -Performance of the entire contract was a condition precedent to payment, and the plaintiff, was bound to show such performance before the defendant became liable to make payment to the contractor. (McMillan v. Varderlip, 12 J. R. 166; Jennings v. Camp, 13 J. R. 94; Faxon v. Mansfield, 2 Mass. R. 147; Stephens v. Beard, 4 Wend. 604; Mead v. Degolyer, 16 Wend. 635; Champlin v. Rowley, 18 Wend. 187; Mains v. Haight, 14 Barb. 76.)

. There are cases.-where a substantial compliance has been held sufficient to take the case out of the rule, but I know, of no case where that has been extended to cases of contracts left half- finished, and exposing . the contracting parties to-serious loss and .injury from such abandonment. -. In the language-of Judge Spencer It-was-never-intended to embrace the case of a willful dereliction of the contract whenpartlv exeeuted by one of the parties. without the. assent and .against the will of the other.” ......

-In White v. Hewitt, 1 E. D. Smith, 395, this question-distinctly arose, and the court-say : It is-nqt law that a. party...con-, tracting to perform a specific job may.-prosecute it,so far as he thinks proper, and then abandon it unfinished without the fault or assent of the party with whom he contracts, and then sue and recover for so much labor as he has chosen to devote to the undertaking. (See also Neville v. Frost, 2 E. D. Smith, 62.)

The omission to state the compensation in the contract does not alter the rule. The defendant would be bound to pay what the work and materials were worth, but he had a right to insist that the contract should be first completed. If the contractor wanted any other terms of payment, he should have stipulated for them in his contract.

The judgment should be reversed.

Judgment reversed, and cause referred back to the refereé; costs to abide the event; and either party to be allowed to produce further testimony.