Citations

Full opinion text

ORDER GRANTING DEFENDANT LOCKHEED’S, MOTION FOR SUMMARY JUDGMENT, INTER ALIA McDONALD, Senior District Judge. BEFORE THE COURT are Defendant Lockheed Martin Corporation’s Motion For Summary Judgment Or, In The Alternative, Summary Adjudication Of Plaintiffs CERCLA And MTCA Causes Of Action (Ct.Rec.238), and Plaintiff City Of Moses Lake’s Motion For Summary Judgment Of Liability Under CERCLA And MTCA Against Defendant Lockheed Martin Corporation (Ct.Rec.242). Oral argument was heard on September 29, 2006. Steven G. Jones, Esq., argued for City Of Moses Lake (“Moses Lake”). Robert W. Loewen, Esq., argued for Lockheed Martin Corporation (“Lockheed”). I. BACKGROUND On December 30, 2005, this court issued an order granting summary judgment to the United States defendants on Moses Lake’s Federal Tort Claims Act (FTCA) claims, finding those claims were barred by the two year FTCA statute of limitations. (Ct.Rec.180). On May 4, 2006, this court issued an order granting summary judgment to defendants Boeing Company (“Boeing”) and Lockheed on the common law tort claims asserted against them by Moses Lake (nuisance, trespass and negligence), finding those claims barred by applicable Washington statutes of limitations (Ct.Rec.234). Moses Lake has also brought cost recovery and contribution claims under the Comprehensive Environmental Response, Compensation and Liability Act (“CERC-LA”), 42 U.S.C. § 9601 et seq., and under Washington’s Model Toxics Control Act (“MTCA”), RCW Chapter 70.105D. These claims are asserted against the United States, Boeing and Lockheed. Lockheed now seeks summary judgment on the cost recovery claims, contending that as to it, those claims are barred by the statutes of limitations applicable to CERCLA and MTCA claims. Lockheed also contends that certain response costs alleged to have been incurred by Moses Lake after 1994 are not recoverable under either CERCLA or MTCA because they were not “necessary.” Moses Lake has filed a cross-motion for summary judgment, asking this court to find as a matter of law that Lockheed is liable as an “operator” and/or as an “arranger” under CERCLA and MTCA. II. FACTS The City of Moses Lake is located near the former Larson Air Force Base (“LAFB”). During World War II and the Cold War, LAFB was used to assemble, station, and maintain hundreds of military aircraft. As a contractor for the United States Air Force, Boeing assembled and maintained these aircraft. LAFB was also surrounded by intercontinental ballistic missiles (“ICBMs”) manufactured by Glen L. Martin Company, a predecessor to Lockheed. ICBMs and their components were assembled, fueled and maintained at LAFB and its associated facilities. After closing LAFB, the United States conveyed almost all of the land and properties that comprised LAFB to Moses Lake in 1966. In a separate transaction in June 1967, the United States conveyed LAFB’s drinking water system, a sewer system, and a waste water treatment plant. The drinking water system originally consisted of five wells (ML 21, ML 22, ML 23, ML 28, and ML 29, a.k.a. “The Larson System”), now situated within a City-defined water distribution zone known as “the Larson Zone.” In 1982, Moses Lake constructed a sixth Larson Zone well known as ML 24. In 1988, Moses Lake was informed by the Washington Department of Social and Health Services (“DSHS”), now known as the Department of Health (“DOH”), that samples taken from three of its wells tested positive for trichloroethylene (“TCE”). Moses Lake learned of the contamination through required testing and regulatory action under what is commonly known as the Safe Drinking Water Act (SDWA), 42 U.S.C. § 300f, et seq. The testing of the wells through 1988-89 showed levels of TCE in wells ML 21, ML 22, and ML 28 at concentrations above the MCL (maximum contaminant level) of 5 ppb (parts per billion). As a result of a July 1988 meeting between DOH and Moses Lake, DOH determined that Moses Lake should sample the three wells on a quarterly basis and notify the public of the contamination. DOH advised Moses Lake that the adequacy of the casing and sealing of the three wells should be examined. Also in July 1988, a meeting was held in Moses Lake with participants from the United States Environmental Protection Agency (“EPA”), DOH, and the Washington State Department of Ecology (“DOE”) discussing TCE in the three City wells. DOH again recommended Moses Lake investigate well casing and sealing. The need for public notification and partial well sealing was reiterated by DOH in a follow up letter to Moses Lake. Although Moses Lake initially objected to both DOH recommendations, it did take ML 22 out of service in August 1988, and on December 14, 1988, published a press release advising the public of the TCE contamination and that it was “continu[ing] to work with DSHS, EPA and Ecology to monitor the city’s water supply to determine the source of the contamination.” In 1988, Moses Lake was provided information about the initial stages of a CERC-LA investigation. In September 1988, DOE issued a Preliminary Assessment Report for Grant County Municipal Airport discussing the TCE contamination in relation to former occupants of the airport and concluding that DOE’s work should be coordinated with DOH’s ongoing investigation of drinking water contamination and the investigation by the U.S. Army Corps of Engineers (“USACE”) into past practices at LAFB. In November 1988, DOE provided Moses Lake with the EPA’s Potential Hazardous Waste Site Disposition Report which recommended the USACE conduct an historic site investigation of LAFB activities. DOE and DOH officials met with the City and explained this report would further the CERCLA investigation process. On January 5, 1989, the Acting Municipal Services Director for Moses Lake provided the City Manager a plan, known as the “Larson Potable Water Supply Project” (aka “the Larson Project”), outlining the steps necessary to reduce the levels of TCE in the wells to below the MCL, while still maintaining adequate water production capacity. The plan provided that the City would line and seal the upper portions of ML 22 so that the well could draw water from the deeper, “clean” portion of the aquifer. The City would study other forms of treatment and monitoring for the other aging municipal wells. The plan also provided that anticipated lost production capacity due to the proposed sealing would be addressed by constructing an additional well, repairing an old well (ML 29), and constructing a reservoir to create additional storage capacity. In July 1989, Moses Lake applied for a $1.4 million loan from the State of Washington Public Works Trust Fund to construct “a reservoir, well and associated water lines on the Larson system.” The application was prepared for the 1990 funding cycle and the loan was granted. By the end of 1989, the City’s Municipal Services Director recommended the City retain a consultant to assist in the review of CERCLA documents and “identify the course of the contamination for potential future litigation.” In January 1990, the USACE determined that what was to become known as the Moses Lake Wellfield Contamination Superfund Site (“Site”) was eligible for funding for further environmental investigation as a Formerly Used Defense Site (“FUDS”) under the Defense Environmental Restoration Program (“DERP”). 10 U.S.C. § 2701. In January 1991, Moses Lake hired a consulting firm, Golder & Associates (“Golder”), to undertake an investigation to assess the contamination to the extent possible and to propose options to assure a clean water supply to the Larson System. In March 1991, Moses Lake was told the USACE had budgeted approximately $1 million for an environmental investigation at LAFB, and that the USACE anticipated starting the investigation, at the earliest, in October 1991. Also, in March 1991, USACE’s lead civil investigator at the site, John Vogel, informed Moses Lake he had hired Dames & Moore to drill 20 monitoring wells to determine the extent of the TCE contamination, and that the work would begin in July or August 1991. The USACE initially targeted four possible TCE source areas for investigation, but told the City in May 1991 that its original plan “had been modified to include a wider evaluation of potential contaminant sources in the Larson area .... [and][i]f source areas are found in this initial program that can be traced to the military, then additional investigations would be undertaken.” On October 28, 1991, Golder delivered its Report to the City of Moses Lake on Hydrogeological Evaluation of Larson Area, Moses Lake, Washington. In or about March 1992, Vogel proposed the USACE take an “intermediate remedial action” (“IRA”) and construct extensions to two of the City’s wells so water could be drawn from the lower areas of the aquifer believed to be free of TCE contamination. In a press release, the USACE advised that it was requesting Department of Defense (“DOD”) funds to reconstruct or replace two city wells and to treat the water from two other public wells. Vogel recommended the IRA be funded by the USACE, consistent with his conclusion the DOD was at least partially responsible for contaminating the wellfield. Vogel requested funding in the amount of $1,630,200. In June 1992, EPA wrote to support the USACE’s proposal. Vogel obtained local approval from the USACE’s Seattle District for this proposed IRA and then submitted his recommendation and the funding request to senior USACE officials. The USACE managers at the Missouri River Division rejected Vogel’s request in June 1992 and instead said the USACE would commence identification of and negotiation with other potentially responsible parties (“PRPs”) at the Site. On April 14, 1992, the Moses Lake City Council adopted Resolution No. 1675, “A Resolution Declaring An Emergency And Waiving The Statutory Bidding Requirements Because Of The Emergency.” In this resolution, Moses Lake acknowledged: (1) that its municipal water system was contaminated with TCE levels above the MCL set by EPA; (2) that it had been attempting to determine the source of the contamination and, along with state and federal agencies, examining methods for eliminating the contamination; and (3) that DOE would “not allow use of Well 28 until the upper water sources are prevented from entering the well.” The City Council declared an emergency to address the contamination and the fact “there may not be enough water to supply the population in the [Larson Subdivision] area during the summer if Well 28 is not rehabilitated as soon as possible.” ML 28 was sealed off permanently from the upper aquifer between April and November 1992. In October 1992, EPA placed the wells, the adjacent privately owned Skyline Water System, and a number of individual residential wells, on the CERCLA National Priorities List (“NPL” or “Superfund”) to be collectively addressed by EPA as the “Moses Lake Wellfield Contamination Superfund Site.” 42 U.S.C. § 9605(a)(8). The EPA contacted PRPs pursuant to CERC-LA § 104(e), 42 U.S.C. § 9604(e). Both Boeing and Lockheed were named as PRPs and were contacted by EPA. Moses Lake retained legal counsel who, in August 1993, wrote a letter to Boeing requesting that Boeing execute a tolling agreement “[i]n order to preserve the City’s claims.” Boeing entered into a tolling agreement with Moses Lake. Lockheed, however, never entered into a tolling agreement with Moses Lake. Between 1989 and 1994, Moses Lake sealed and lined the shallow zones of ML 21, ML 22 and ML 28, and constructed the new reservoir (Reservoir No. 7). With the completion of these projects, Moses Lake closed out its Public Works Trust Fund loan. Since the discovery of TCE in ML 21, ML 22 and ML 28, the Larson System wells have been tested routinely. Sampling data maintained by DOH shows that since 1992, the levels of TCE in ML 21 and ML 28 have decreased to below the MCL or to “non detect.” For the last ten years, ML 21 and ML 28 have been at “non detect” for TCE. Because ML 22 was taken out of service by Moses Lake, DOH test results end in 1991. At that time, ML 22 was just slightly above non-detect and less than 1 ppb for TCE. For the ten year period from 1994 to 2004, ML 24 and ML 29 tested at non-detect for TCE, and for the same ten year period, TCE levels in ML 23 were less than 2 ppb with several non-detect values. Between 1988 and 1992, ML 24 always tested at non-detect levels, and ML 23 and ML 29 never exceeded the MCL, unlike ML 21, ML 22 and ML 28. In 1997, Moses Lake installed a new water main on Patton Boulevard to provide an additional, larger connection between ML 28 and Reservoir 7. This enabled simultaneous operation of ML 24 and ML 28 at a greater flow rate than was previously possible. In 1997, the Moses Lake City Council approved a plan to connect the Knolls Vista water zone to the Larson Zone. Construction of the Knolls Vista intertie began in July 1997 and was completed in March 1998. Beginning in 1995, the EPA began negotiating a proposed agreement with Moses Lake to connect the Skyline Water System customers to Moses Lake’s water system. Under the terms of the proposed agreement, Moses Lake was to receive additional water rights, would charge the Skyline residents a higher commercial rate, and would receive from the EPA an agreement that Moses Lake would be protected from any litigation concerning TCE contaminated water in the area. The USACE was responsible for design and construction, and Moses Lake charged the USACE fees and received reimbursement for review and approval of USACE’s plans and specifications. The EPA selected another alternative in 1999 which was to construct a new well in the Skyline area that would draw water from the deeper aquifer (Roza 2). The new well was drilled in 2001, but was found to be contaminated with TCE at levels equal to or slightly above the MCL. EPA proposed that a second well be drilled. EPA received comments from Skyline residents opposing the connection of the City’s water system with the private Skyline Water System. On May 28, 2002, EPA received a letter from Moses Lake’s consultant (Golder), complaining about the already completed well. Moses Lake’s comments were received after the EPA had already made the decision to drill the second well. Moses Lake has not experienced any TCE contamination problem in its wells as a result of the drilling of the second Skyline well. Since Moses Lake filed this lawsuit in October 2004, it now alleges it has incurred “necessary” response costs with regard to the current construction of a new reservoir (Reservoir 9) and modification of Reservoir No. 7. Reservoir 9 is being built to in order to improve the water pressure in the Larson area. Reservoir 7 needs to be raised to the elevation at which the new Reservoir 9 is being built so that the new reservoir will work properly (increase the water pressure). The City now apparently also alleges that the rebuild of ML 23 in 1999 was a “necessary” cost in response to the TCE contamination of the Larson Zone wellfield. III. DISCUSSION A. Summary Judgment Standard The purpose of summary judgment is to avoid unnecessary trials when there is no dispute as to the facts before the court. Zweig v. Hearst Corp., 521 F.2d 1129 (9th Cir.), cert. denied, 423 U.S. 1025, 96 S.Ct. 469, 46 L.Ed.2d 399 (1975). Under Fed. R.Civ.P. 56, a party is entitled to summary judgment where the documentary evidence produced by the parties permits only one conclusion. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Semegen v. Weidner, 780 F.2d 727, 732 (9th Cir.1985). Summary judgment is precluded if there exists a genuine dispute over a fact that might affect the outcome of the suit under the governing law. Anderson, 477 U.S. at 248, 106 S.Ct. 2505. The moving party has the initial burden to prove that no genuine issue of material fact exists. Matsushita Elec. Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). Once the moving party has carried its burden under Rule 56, “its opponent must do more than simply show that there is some metaphysical doubt as to the material facts.” Id. The party opposing summary judgment must go beyond the pleadings to designate specific facts establishing a genuine issue for trial. Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In ruling on a motion for summary judgment, all inferences drawn from the underlying facts must be viewed in the light most favorable to the nonmovant. Matsushita, 475 U.S. at 587, 106 S.Ct. 1348. Nonetheless, summary judgment is required against a party who fails to make a showing sufficient to establish an essential element of a claim, even if there are genuine factual disputes regarding other elements of the claim. Celotex, 477 U.S. at 322-23, 106 S.Ct. 2548. B. Statutes of Limitations — Costs Incurred Between 1989 and 1994 An action for cost recovery under CERCLA must be brought “within 3 years after completion of [a] removal action” or “within 6 years after initiation of physical on-site construction of the remedial action.” 42 U.S.C. § 9613(g)(2)(A)-(B). A lawsuit seeking recovery of “remedial action costs” under MTCA “must be brought within three years from the date remedial action confirms cleanup standards are met.” RCW § 70.105D.080. Lockheed contends Moses Lake’s response actions were completed by 1994, when potable water was restored in the Larson Zone. Since Moses Lake’s lawsuit was not filed until October 18, 2004, and since it had no tolling agreement with Lockheed, Lockheed asserts the lawsuit is barred under the applicable CERCLA and MTCA statutes of limitations. 1. CERCLA Moses Lake’s CERCLA cost recovery action is brought under 42 U.S.C. § 9607 which provides “a cause of action for private parties to seek recovery of cleanup costs.” Key Tronic Corp. v. United States, 511 U.S. 809, 818, 114 S.Ct. 1960, 128 L.Ed.2d 797 (1994). (See Paragraph 6.2 of First Amended Complaint, Ct. Rec. 182). § 9607(a) specifies that those persons potentially responsible for the pollution in question (otherwise known as “Potentially Responsible Parties” or “PRPs”) are liable for “all costs of removal or remedial action incurred by the United States Government or a State or an Indian tribe not inconsistent with the national contingency plan” and “any other necessary costs of response incurred by any other person consistent with the national contingency plan.” 42 U.S.C. § 9607(a)(l)-(4)(A) and (B) (emphasis added). Relying on California Department of Toxic Substances v. Neville Chemical Company, 358 F.3d 661, 663 (9th Cir.2004), Moses Lake contends the statute of limitations has yet to accrue on its CERCLA cost recovery action and will not accrue until the EPA issues its Record of Decision (“ROD”) setting forth the “remedial action plan” for the Moses Lake Wellfield Contamination Superfund Site (“Site”). Neville was a cost recovery action brought by the State of California, not by a private party, such as a municipal corporation like the City of Moses Lake. In Neville, the defendant maintained that its “initiation of physical on-site construction of the remedial action” occurred in April 1994 when it started excavating extraction wells and therefore, the six year statute of limitations for “remedial action” commenced on that date. The State of California argued that no “remedial action” could have occurred until the final “remedial action plan” was approved by its Department of Toxic Substances Control on May 8, 1995 and therefore, the limitations period commenced on that date. The Ninth Circuit Court of Appeals sided with the State and held the limitations period could not accrue until final adoption of the “remedial action plan” required by CERCLA. The court noted CERCLA’s definition of “remedial action” as “actions consistent with permanent remedy taken instead of or in addition to removal actions,” 42 U.S.C. § 9601(24), and concluded that “[f]or an action to be ‘consistent with permanent remedy,’ a permanent remedy must already have been adopted.” Id. at 667. According to the court: Neither party can know for sure whether a given action is consistent with permanent remedy until that permanent remedy is determined. The first point at which both parties can be certain that any construction is consistent with a permanent remedy is when a permanent remedy is actually selected. In this case, as in most cases, the permanent remedy was selected when the final RAP [Remedial Action Plan] was approved. Id. In other words, “[initiation of physical on-site construction of the remedial action can only occur after the remedial action” is adopted. Id. at 671. In a footnote, the court observed that in cases where private parties conduct the clean-up of a site without governmental or agency oversight and then pursue response costs under CERCLA, “there will most likely still be a remedial action plan in place.” Id. at n. 3, citing 40 C.F.R. § 300.700 (providing that private parties should follow the public notice and comment procedures required of government actors). Since, however, no non-governmental response cost suit was before the court, it declined to address the limitations period applicable to such suits. Id. Lockheed contends that Neville has no application to the case at bar because what Moses Lake, as a “private party,” did between 1989 and 1994 constituted “removal action,” not “remedial action.” “Removal action” is subject to a three year limitations period commencing upon completion of said action. Furthermore, even if what Moses Lake did constituted “remedial action,” Lockheed contends it was independent of EPA’s ongoing “remedial action” and was taken pursuant to Moses Lake’s own “remedial action plan” which was “in place” no later than 1994. Thus, Lockheed says the six year limitations period applicable to “remedial action” commenced no later than 1994 and expired in 2000, well before the present lawsuit was filed by Moses Lake. Whether a response action is a “removal action” or a “remedial action” is a question of law for the court. Carson Harbor Village, Ltd. v. Unocal Corporation, 287 F.Supp.2d 1118, 1157 (C.D.Cal.2003). “Provision of alternative water supplies” can constitute either “remedial action” as defined in 42 U.S.C. § 9601(24), or “removal action” as defined in 42 U.S.C. § 9601(23). In United States v. W.R. Grace & Co., 429 F.3d 1224 (9th Cir.2005), the Ninth Circuit Court of Appeals held that EPA’s characterization of a cleanup as a “removal action” was supported by the administrative record and withstood scrutiny under the modified level of deference afforded by the Supreme Court’s decision in United States v. Mead Corp., 533 U.S. 218, 121 S.Ct. 2164, 150 L.Ed.2d 292 (2001). According to the court: The administrative posture of CERCLA presents two types of agency interpretations. One is the National Contingency Plan [NCP] which carries the force of law. The second relates to informal agency interpretations, which at a minimum receive respect, and depending on the interplay of Mead and Brand A, may even deserve Chevron deference. Whichever of these applies, we reach the same result: We hold that the EPA has rationally construed CERCLA and that construction deserves our respect. [Citation omitted]. As interpreted by the EPA, the removal/remedial distinction boils down to whether the exigencies of the situation were such that the EPA did not have time to undertake the procedural steps required for a remedial action, and, in responding to a time-sensitive threat, the EPA sought to minimize and stabilize imminent harms to human health and the environment. The EPA did so here. Id. at 1241. (Emphasis added). The one consistent thread in the decisions dealing with whether an action is “remedial” or “removal” in nature is that “removal actions generally are immediate or interim responses, and remedial actions generally are permanent responses.” Neville, 358 F.3d at 667, quoting Geraghty & Miller, Inc. v. Conoco, Inc., 234 F.3d 917, 926 (5th Cir.2000). See also Carson Harbor Village, 287 F.Supp.2d at 1158 (property owner’s cleanup of tar-like and slag materials was “remedial action” because there was no evidence that the materials posed the type of threat to human health and welfare that required immediate action); Advanced Micro Devices, Inc. v. National Semiconductor Corp., 38 F.Supp.2d 802, 810 (N.D.Cal.l1999)(removal actions are “short-term action[s] taken to halt the immediate risks posed by hazardous wastes”); Channel Master Satellite Systems, Inc. v. JFD, 748 F.Supp. 373, 385 (E.D.N.C.1990) (“The courts have consistently found that the removal category was to be used in that limited set of circumstances involving a need for rapid action, while non-urgent situations are to be addressed as remedial actions”). Lockheed asserts that Moses Lake’s “Larson Potable Water Supply Project” fits the definition of a “removal action” because what Moses Lake sought to do was to address the “immediate problem” of abating the TCE contamination above the MCL in its wells, rather than abating the contamination in the aquifer or the “Site” as a whole. In this regard, Lockheed notes that per Grace, the fact that some of the measures taken by Moses Lake might have effected a permanent solution for a particular location (i.e., the Larson Zone), does not mean those measures are not “removal actions.” 429 F.3d at 1247. In Grace, the “removal action” — removing exposed piles of vermiculite — did not fully eliminate the public health threat or amount to a full-blown remediation, Id., and Lockheed says the same is true here in that what Moses Lake did concerning its Larson System of wells did not eliminate the public health threat of the TCE contamination in the aquifer or amount to a full-blown remediation of the same. Rather, it is EPA’s Draft Proposed Plan and its eventual Final Proposed Plan which seek to remedy contamination of the aquifer — the “Site” — as a whole. As compared to EPA’s Proposed Plan for a “permanent” solution to the TCE contamination in the aquifer, what Moses Lake did between 1989 and 1994 in abating the contamination in its Larson Zone wellfield certainly bears all of the hallmarks of a “removal action” — an interim response to minimize and stabilize imminent harms to human health. This is so whether or not Moses Lake’s action between 1989 and 1994 is viewed as an independent interim action, or as part and parcel of EPA’s broader “remedial action” to remedy contamination of the aquifer— the “Site” — as a whole. And whether it was independent interim action, or part and parcel of EPA’s broader “remedial action,” a CERCLA lawsuit to recover costs incurred in connection with such “removal action” would need to have been commenced no later than 1997, three years after completion of the “removal action” in 1994. The only way Moses Lake can successfully argue that its October 2004 lawsuit is timely is to rely on Neville and contend that what it did between 1989 and 1994 constitutes “remedial action” that is not independent of EPA’s final “remedial action plan” for the entire Moses Lake Well-field Contamination Superfund Site. If that is the case, the limitations period will not commence until EPA issues its ROD approving the final “remedial action plan” for the Site. Lockheed asserts that even if Ne-ville’s rule applies to cost recovery actions by private parties and what Moses Lake did between 1989 and 1994 constitutes “remedial action,” Moses Lake’s lawsuit is still untimely because that action was not taken pursuant to EPA’s “remedial action plan” to clean up the Site as a whole, but was taken pursuant to the City’s own “remedial action plan” (the “Larson Potable Water Supply Project”) to clean up its individual wells. Lockheed contends Moses Lake’s “remedial action plan” was effectively the 1991 Golder Report. If the six year limitations period for “remedial action” commenced in 1991, it expired well before Moses Lake filed this lawsuit in 2004. If Neville’s rule does not apply to cost recovery actions brought by private parties, Lockheed contends the limitations period commenced in 1989 with the initiation of physical on-site construction of the “remedial action,” and the lawsuit is even more untimely. Moses Lake asserts it has never adopted its own “remedial action plan,” but from the very beginning when TCE was discovered at the Site, has “worked at the direction of and in cooperation with federal and state agencies to investigate and address that contamination.” While Moses Lake may have cooperated with federal and state agencies in investigating and addressing the contamination of its Larson Zone wells, and was willing to entertain and follow recommendations from those agencies, the undisputed facts reveal that Moses Lake charted its own course in taking action to restore safe drinking water in its wells. It is undisputed that Moses Lake did not conduct its abatement projects pursuant to any enforcement orders, consent decrees, administrative orders or interagency agreements with the EPA, USACE, or Washington’s DOE [Department of Ecology]. Moses Lake concedes it proceeded on its own because it believed that neither state or federal agencies were acting quickly enough. According to Brian Hinthorne, the City’s Project Engineer for the Larson Project, Moses Lake “was faced with a situation where it had lost a well because it had tried to seal off the contaminated zones, two or more of the City’s wells were contaminated and there wasn’t any action by ... federal or state agencies to provide clean water to the affected water system.” (Costanzo Deck, Ct. Rec. 249, Ex. 20, Hinthorne Dep. at 100:19-101:10). Moses Lake “made [its] own decisions based on what information was out there.” (Id. at 104:19-20). In its December 30, 2005 order granting summary judgment to the United States on Moses Lake’s FTCA claims, this court found that: The remedial measures commenced by Moses Lake indicate it was not banking on any assurances be the United States that there would be federal funding. Moses Lake started to abate the nuisance (the contamination of ML 21, ML 22, and ML 28) before federal funding was proposed and continued to abate it after funding was rejected by the USACE. (Ct. Rec. 180 at p. 19). In its brief submitted in response to Lockheed’s motion, Moses Lake confirms this is true: “After Vogel’s supervisors at the Corps rejected his proposal to have the Corps pay for the remediation of the City’s wells, the City had no choice but to spend its own money to seal off the wells in the Roza 1 aquifer and to drill into the Roza 2 aquifer in the hope of obtaining an alternative water supply that was not contaminated by TCE.” (Ct. Rec. 261 at p. 6). There is no genuine issue of material fact that Moses Lake’s “Larson Potable Water Supply Project” was accomplished without governmental or agency oversight, confirmed by the fact that Moses Lake seeks recovery of costs under CERCLA as a “private party.” As such, if what Moses Lake did between 1989 and 1994 constitutes “remedial action” under CERCLA, the six year limitations period commenced no later than 1991 with the issuance of the Golder study which was Moses Lake’s “remedial action plan” for abating TCE contamination in its Larson Zone wellfield. 2. MTCA Moses Lake’s “Third Cause of Action” is for “Cost Recovery And Contribution Under MTCA Against Boeing And Martin.” The MTCA provides: A person may bring a private right of action, including a claim for contribution or for declaratory relief, against any other person liable under RCW 70.105D.040 for the recovery of remedial action costs. ... Recovery of remedial action costs shall be limited to those remedial actions that, when evaluated as a whole, are the substantial equivalent of a department-conducted or department-supervised remedial action. RCW § 70.105D.080. (Emphasis added). A claim under MTCA for recovery of cleanup costs must be brought within three years “from the date remedial action confirms cleanup standards are met.” Id. Relying on Pacific Sound Resources v. Burlington Northern Santa Fe Railway Corp., 125 P.3d 981, 130 Wash.App. 926 (2005), Moses Lake contends that like the limitations period on its CERCLA cost recovery claim, the limitations period on its MTCA cost recovery claim will not commence, at the earliest, until EPA issues its ROD approving a final “remedial action plan” for the Moses Lake Wellfield Contamination Superfund Site. Pacific Sound was an action for recovery of cleanup costs under the MTCA brought by the Port of Seattle (“Port”), a municipal corporation, and Pacific Sound Resources (“PSR”), a non-profit corpora-. tion. The Washington Court of Appeals, Division I, was confronted with the issue of what type of remedial action “confirms when cleanup standards are met.” The court of appeals rejected reliance on approval of the RI/FS (Remedial Investigation/Feasibility Study) as the remedial action that “confirms cleanup standards are met,” and concluded that the earliest decision triggering the statute of limitations was EPA’s issuance of a ROD on September 30, 1999. According to the court: Because the RI/FS is not an official action by the lead agency, adoption of the RI/FS as a remedial action did not trigger the running of the statute of limitations in this case. We conclude the earliest official agency action that could have triggered the statute of limitations was on September 30, 1999 when EPA formally selected cleanup levels and remedies in the ROD. Consequently, PSR and the Port timely filed their lawsuit on September 25, 2002. Id. at 940-41, 125 P.3d 981. Pacific Sound involved governmental or agency oversight from the beginning of the cleanup. In August 1984, the EPA issued an administrative order directing PSR to investigate contamination at the facility. In January 1990, EPA issued another order to PSR directing it to prepare an RI/FS. As part of the RI/FS, PSR conducted extensive investigations, including soil and groundwater sampling. In March 1990, PSR notified EPA it did not have sufficient funds to complete the RI/FS. Because PSR could not continue with cleanup efforts, EPA assumed primary responsibility for the Site under CERCLA. In May 1994, EPA listed the site on the NPL for cleanup under CERCLA. In August 1994, PSR and EPA entered into a consent decree which required PSR to contribute all its assets to the PSR Environmental Trust and to pay for cleanup actions at the site. The Port subsequently agreed, pursuant to an administrative order, that it would assume responsibility to continue cleanup efforts at the site, including completing the RI/FS. On September 30, 1999, EPA issued a ROD. Based on the RI/FS analysis, EPA formally adopted a cleanup plan for the entire site and selected containment remedies in the ROD. On September 25, 2002, PSR and the Port sued several defendants, including Burlington Northern Santa Fe Railway Corp., for cleanup costs contribution under the MTCA. The “remedial action” undertaken by Moses Lake between 1989 and 1994 was “independent” of any governmental or agency oversight. It was an “independent remedial action,” defined by MTCA as “remedial actions conducted without department [Department of Ecology] oversight or approval, and not under an order, agreed order, or consent decree.” RCW 70.105D.020(8). Lockheed argues that unlike Pacific Sound where EPA action was needed to define the “cleanup standards” that must be “met” to trigger the statute, the only relevant standard in the case at bar-providing water to the Larson Zone that met the MCL — was verified by the City and the DOH when they determined that water from the Larson Zone could be safely distributed to the public. This court agrees. Lockheed observes that RCW 70.105D.080 does not mention a lead agency in its formula for triggering the statute of limitations. The statute does not say anything about the Department of Ecology or any other governmental agency “con-firmfing] cleanup standards are met.” An action must be brought “within three years from the date the remedial action confirms cleanup standards are met.” The nature of the “remedial action” serves to confirm whether cleanup standards are met. If there is no agency oversight or approval because the remedial action undertaken is “independent,” an official agency decision is not necessary to trigger the statute of limitations. An official agency decision was necessary to trigger the statute of limitations in Pacific Sound because that case did not involve “independent remedial action.” In Pacific Sound, the court of appeals noted that “development of the cleanup standards begins with the RI/FS” and that “cleanup standards are not officially adopted until the remedy is selected in the Cleanup Action Plan (‘CAP’) under the MTCA or in the ROD under CERCLA.” 130 Wash.App. at 937, 125 P.3d 981. Consequently, until the cleanup standards were officially adopted, it was not possible to determine if remedial action confirmed those standards had been met. Since the case at bar involves an “independent remedial action,” it was not necessary to wait for an official adoption of cleanup standards in a CAP or a ROD in order to commence the running of the statute of limitations. Washington Administrative Code (“WAC”) regulations define “cleanup standards” as the standards adopted under RCW 70.105D.030(2). WAC 173-340-200. The Department of Ecology is required to “[pjublish and periodically update minimum cleanup standards for remedial actions at least as stringent as the cleanup standards under section 121 of the federal cleanup law, 42 U.S.C. See. 9621, and at least as stringent as all applicable state and federal laws, including health-based standards under state and federal law.” RCW 70.105D.030(2)(e). (Emphasis added). An MCL of 5 ppb of TCE was the applicable “cleanup standard” when Moses Lake undertook “independent remedial action” between 1989 and 1994 to restore safe drinking water in its Larson System of wells, and it remains the standard. This “cleanup standard” did not need to be “confirmed” by EPA or DOE at the time Moses Lake undertook its “independent remedial action.” It was and remains the standard officially adopted by the State of Washington since it is undisputed that Moses Lake is in compliance with all DOH regulations and has been authorized by DOH to deliver water from its Larson Zone wells to its customers since it completed the rehabilitation of ML 21 in April 1994. (City’s Response To Lockheed’s Statement of Material Facts No. 38, Ct. Rec. 262 at p. II). Moses Lake’s cost recovery action under MTCA seeking to recover costs from Lockheed incurred between 1989 and 1994 is barred by the applicable three year statute of limitations. The reasoning is the same as that which supports the conclusion that the CERCLA cost recovery action for those costs is barred by the applicable CERCLA statutes of limitations: the action was undertaken by Moses Lake independently, without governmental or agency oversight or approval, and therefore, an official agency decision at some subsequent date is not necessary to commence the running of the limitations period. More specifically, commencement of the limitations period for the purposes of either CERCLA or MTCA does not require awaiting EPA’s issuance of a ROD identifying its selected remedy for the Moses Lake Wellfield Contamination Superfund Site. 3. Conclusion Statutes of limitations are about “fairness” to the parties. While Moses Lake certainly acted appropriately in promptly restoring safe drinking water in the Larson System of wells, it is not an “unfair” result that Moses Lake is time-barred from recovering response costs from Lockheed related to that effort. In October 1992, Lockheed had been named a PRP by EPA with regard to the Site. Moses Lake had to know that Lockheed was a party potentially responsible for the TCE contamination in its Larson System of wells. Boeing had also been named a PRP and Moses Lake negotiated a tolling agreement with Boeing. For whatever reason, a tolling agreement was not negotiated with Lockheed. As such, it was incumbent upon Moses Lake to commence a CERC-LA/MTCA cost recovery action against Lockheed as soon as possible, but no later than April 1997 to preserve the MTCA action and also the CERCLA action, if what Moses Lake did between 1989 and 1994 constituted “removal” instead of “remedial action.” If it was “remedial action,” Moses Lake needed to commence the CERCLA cost recovery action no later than October 1997, six years after its “remedial action plan,” the Golder Study, was issued. C. “Necessary” Response Costs After 1994 Under CERCLA, 42 U.S.C. 9607(a)(l)-(4)(B), Moses Lake seeks recovery of “any other necessary costs of response incurred by any other person consistent with the national contingency plan.” As part of its prima facie case, Moses Lake bears the burden of establishing that the release or threatened release of a hazardous substance “has caused the plaintiff to incur response costs that were ‘necessary’ and ‘consistent with the national contingency plan.’ ” Carson Harbor Village v. County of Los Angeles, 433 F.3d 1260, 1265 (9th Cir.2006). In determining whether response costs are “necessary,” the focus is “not on whether a party has a business or other motive for cleaning up the property, but on whether there is a threat to human health or the environment and whether the response action is addressed to that threat.” Carson Harbor Village, Ltd. v. Unocal Corp., 270 F.3d 863, 872 (9th Cir.2001). MTCA is consistent with CERCLA, allowing recovery of costs of “remedial action” to “identify, eliminate, or minimize any threat or potential threat posed by hazardous substances to human health or the environment.” RCW 70.105D.020(21). Lockheed contends response costs incurred by Moses Lake after 1994 were not “necessary” because by that time, Moses Lake had achieved the objectives of its Larson Project in that it had restored a potable water supply to its Larson Zone customers, and restored water quantity in the Larson Zone to pre-TCE levels (the levels existing prior to discovery of TCE in the wells). According to Lockheed, the posN1994 costs were not incurred in “response” to the contamination of the City’s wells, but were merely for standard improvements to the City’s water utility. Indeed, it is undisputed that the result of the Larson Project was a “more than adequate potable water supply.” Capacity data Plaintiff submitted to the DOH in its 1994 Water System Plan, which DOH approved, confirmed that water quantity in the Larson Zone had been restored to pre-TCE levels. Moses Lake’s 2001 Water System Plan confirmed that the Larson Zone had the most surplus water capacity above and beyond the maximum daily demand of any of Moses Lake’s water zones. (City’s Response To Lockheed’s Statement Of Material Facts Nos. 71, 117 and 118, Ct. Rec. 262 and 263 at pgs. 26 and 41). Finally, as already noted, none of the Larson Zone wells, nor any of the City’s wells for that matter, have tested above the MCL for TCE since 1994. Moses Lake contends it is premature for the court to entertain Lockheed’s motion with regard to “damages” since this case has been bifurcated into liability and damages phases, and the liability phase is not yet complete. What has been bifurcated are the liability and damages trials. This court did not bifurcate discovery with regard to liability and damages. Fact discovery, for both liability and damages, closes on November 3, 2006, and has been ongoing since December 2004. It is reasonable to believe that by now, all of the evidence related to specific costs, including installation of the supplemental water main on Patton Boulevard (completed in 1997), installation of the intertie to connect the Larson Zone to the Knolls Vista Zone (completed in 1998), construction of Reservoir No. 9 and modification of Reservoir No. 7 (construction started in 2000), and comment on the Skyline System well (2002), has been developed. As such, it is not unfair to put Moses Lake to its proof on this issue. 1. Lost Water Rights, Lost Water Capacity and Lost Revenues Moses Lake concedes it cannot seek recovery under CERCLA and MTCA for these items. Moses Lake contends damages for these items are recoverable under common law tort, but acknowledges the court has already granted summary judgment against Moses Lake on all of its tort claims. 2. Post-1994 Construction Projects Citing deposition testimony from City Engineer Gerry McFaul and City Water Manager William L. Maddox, Moses Lake says there is evidence in the record that the Patton Boulevard water line and the Knolls Vista intertie were constructed in response to the need to transfer water to the Larson Zone to remedy quantity problems resulting from TCE contamination. McFaul testified the purpose of the intertie “was to make sure that we could pump water from the Knolls Vista Zone up into the Larson Zone if we did not have enough water.” (McFaul Dep. at p. 47, Lines 23-25, Ex. 8 to Jones Declaration, Ct. Rec. 265), (Emphasis added). Maddox testified that the purpose of the intertie was “to move water to Larson, and to allow water to come into Knolls.” (Maddox Dep. at p. 118, Lines 9-11, Ex. 10 to Jones Declaration, Ct. Rec. 265). Neither McFaul or Maddox, however, testified that at anytime after 1994, the quantity of potable water in the Larson Zone has been an issue or that it has been less than what was available prior to the discovery of TCE in the Larson System of wells. Lockheed cites evidence that the purpose of the Patton Boulevard line and the intertie was to increase the supply of water to the Knolls Vista Zone, not the Larson Zone. Gary Harer, Moses Lake Municipal Services Director, testified that in 1996, the City was considering constructing a new well in the Knolls Vista Zone, or pumping ML 24 and ML 28 harder to get an additional supply of water to the Knolls Vista Zone. It is undisputed that with the addition of the Patton Boulevard line, it was no longer necessary to pump ML 24 and 28 harder because the flow from those wells had been increased. (City’s Response To Lockheed’s Statement Of Material Facts Nos. 122 and 123, Ct. Rec. 263 at pp. 43-44). It is undisputed that Knolls Vista has suffered from water shortages unrelated to TCE contamination since at least 1982, and in the early 1990s, had lost its primary well (ML 9) due a taste and odor problem caused by hydrogen sulfide. An intertie between the Larson Zone and the Knolls Vista Zone was considered a solution to the loss of ML 9, and the City’s Water System Plan recommended installing an intertie between the Knolls Vista and Larson Zones to improve the pressure at the fairgrounds located in the Knolls Vista Zone. In 1997, the Moses Lake City Council approved new residential developments and a five acre park with several ballfields to be constructed in the Knolls Vista Zone. At this same time, new industry demand Moses Lake had hoped for in the Larson Zone never materialized. The idea of an intertie between the Larson Zone and the Knolls Vista Zone had previously been rejected because of the perception that it would result in spreading TCE from the Larson Zone into the Knolls Vista Zone. It is undisputed that in four separate memo-randa to the City Council, Harer instructed the City Council that the purpose of the intertie was to serve the Knolls Vista Zone. Neither Harer, or anyone else, ever informed the City Council that the purpose of the intertie was to serve the Larson Zone. Furthermore, it is undisputed that even now, it is not possible to deliver water from the Knolls Vista Zone to the Larson Zone due to the Larson Zone’s higher hydraulic elevation. (City’s Response To Lockheed Martin’s Statement Of Material Facts Nos. 127, 128, 129, 130, 134, 136 and 137, Ct. Rec. 263 at pp. 45-52). While credibility is normally an issue which should not be resolved on summary judgment, “[i]n rare instances, credibility may be determined without an evidentiary hearing where it is possible to ‘conclusively’ decide the credibility question based on ‘documentary testimony and evidence in the record.’ ” Earp v. Ornoski, 431 F.3d 1158, 1169-70 (9th Cir.2005), quoting Watts v. United States, 841 F.2d 275, 277 (9th Cir.1988). This is one of those instances, even more so because this court is the trier of fact on CERCLA and MTCA liability and damages. The deposition testimony of McFaul and Maddox cited by Moses Lake does not suffice to raise a genuine issue of material fact that the Patton Boulevard line and the Knolls Vista intertie were constructed as a “necessary” response to the TCE contamination in the Larson Zone wells, specifically to get more water to the Larson Zone to make up for quantity lost because of TCE contamination and the subsequent rehabilitation projects undertaken to remedy that contamination (i.e., taking ML 22 out of service; sealing off ML 21 and 28 from the upper aquifer). Their testimony is conclusory and not supported by any documentation produced contemporaneously with the construction of the Patton Boulevard line and the Knolls Vista intertie. It is directly at odds with the contemporaneous documentation, as corroborated by Harer in his deposition testimony, revealing unequivocally that these projects were a response to chronic water shortage problems in the Knolls Vista and had nothing to do with TCE contamination in the Larson Zone wells. This is not surprising considering the undisputed fact that upon completion of the Larson Project in 1994, potable water quantity had been restored to pre-TCE levels and has not diminished since that time. Likewise, the rebuilding of ML 23 in 1999 was not undertaken in response to TCE contamination because by 1994, all of the wells had been cleaned up and potable water, in adequate quantity, had been restored to Larson Zone customers. As this court noted in its May 4, 2006 order: “ML 23 has never tested above the MCL, including at anytime after 1988.” (Ct. Rec. 234 at pp. 23-24). With regard to construction of the new Reservoir 9 and modification of Reservoir 7, Lockheed cites deposition testimony from Harer indicating that this is to increase the amount of pressure, is a matter of convenience, is not a health or safety issue, and the motivating factor is so the port district can persuade industries to build in the Larson Zone. Moses Lake presents no evidence to dispute this and instead resorts to a discussion of its pre-1994 projects which restored safe drinking water in the Larson Zone wells. (City’s Response To Lockheed Martin’s Statement Of Material Facts No. 146, Ct. Rec. 263 at pp. 55 — 56). The costs incurred by Moses Lake with regard to installation of the supplemental water main on Patton Boulevard, installation of the intertie to connect the Larson Zone to the Knolls Vista Zone, construction of the new Reservoir 9 and modification of Reservoir 7, and rebuild of ML 23, were not in response to TCE contamination in the City’s Larson Zone wellfield and therefore, were not “necessary.” 3. Costs In Providing Public Comment On The Skyline Proposal Moses Lake seeks to recover costs paid to its consultant, Golder, to prepare a letter complaining about EPA’s chosen remedy for the Skyline system, that being a new well. Moses Lake cites to deposition testimony from McFaul and Maddox that this action was taken to ensure that implementation of EPA’s plans would not adversely affect the City’s water system and would not allow contamination of the City’s wellfield by TCE coming from the Skyline wellfield. Moses Lake says that review of EPA’s remediation at the Skyline Water District benefitted the “entire cleanup” since Skyline is part of the overall Superfund Site and it “also served the purpose of facilitating a prompt and effective cleanup by ensuring that efforts taken at one area of the Site did not contribute to contamination at another, such as the City’s wells.” Lockheed argues fees paid to Golder to prepare comments pursuant to a standard public comment period were not response costs because neither “removal” or “remedial action” by Moses Lake was involved. Instead, says Lockheed, the comments were made to a “removal” or “remedial action” undertaken by EPA. Lockheed also contends that since public comment is not compelled, it is not “necessary.” All of this makes logical sense to the court and is supported by the fact that in the 25 plus years that CERCLA has existed, there has never been a case addressing the issue and finding that costs of making public comments either can or cannot be considered response costs. To be recoverable as response costs, consultant’s fees must be “closely tied to the actual cleanup, must benefit the entire cleanup and not cost allocation or liability shifting, and cannot be primarily protective of the plaintiffs interest.” Sealy Connecticut, Inc. v. Litton Industries, Inc., 93 F.Supp.2d 177, 190 (D.Conn.2000). Lockheed contends that in offering public comments about the well in the private Skyline district, Moses Lake expressed concern about its own interest, not that of the Skyline residents, and this is borne out by the fact that the well had already been completed when Moses Lake offered its comments. Moses Lake does not deny that its comments reflected concern about investment in its own Larson Zone wells, but says that does not matter because the comments were intended to benefit the cleanup of the Site as a whole. In support of its argument, Moses Lake cites In re Combustion, Inc., 968 F.Supp. 1112, 1115 (W.D.La.1996)(“[a]ctivities financed by private litigants that are closely tied to the actual cleanup, significantly benefit the entire cleanup, and serve a statutory purpose by facilitating a prompt and effective cleanup are the type of cost expenditures that CERCLA recognizes to be included in cost recovery actions”). As Lockheed notes, Combustion had nothing to do with offering public comment about an “already completed remedial action” (the Skyline well having already been drilled). In the Combustion case, the plaintiffs had “organized to conduct various investigations and assessments of the Combustion Site and subsequently financed and completed a removal action that cleared the Site process and pond areas of the sources or potential sources for releases of hazardous substances.” Id. at 1115. When Moses Lake, via Golder, offered comments on the already completed Skyline well, the Larson Potable Water Supply Project had long been completed and a safe and adequate amount of drinking water was being supplied to Larson Zone customers from the Larson Zone wells. That “cleanup” had been accomplished. The issue now, of course, is cleaning up the aquifer as a whole. The record indicates that Moses Lake’s comments were not closely tied to cleanup of the aquifer as a whole, but instead to preserving the cleanup of its own wells in the Larson Zone. (City’s Response To Lockheed Martin’s Statement Of Material Facts Nos. 166 and 167, Ct. Rec. 263 at pp. 61-62, and City’s Statement Of Material Facts T and W, Ct. Rec. 263 at pp. 69-71). Furthermore, it would be difficult to conclude the comments significantly benefitted the cleanup of the aquifer as a whole and facilitated a prompt and effective cleanup of the same when EPA has not yet even issued a final proposed plan, let alone a final “remedial action plan.” For all of these reasons, the court concludes as a matter of law that the costs of providing these public comments were not “necessary.” D. Declaratory Relief Because Moses Lake is time-barred from seeking recovery from Lockheed of costs incurred prior to 1994, and because certain response costs incurred after 1994 were not “necessary,” Lockheed is entitled to summary judgment on Moses Lake’s claims for declaratory relief under CERC-LA (42 U.S.C. § 9613(g)(2)) and MTCA (RCW 7.24.010 and RCW 70.105D.080) with regard to those particular costs. E. Liability Under CERCLA and MTCA The court will address Lockheed’s liability, even though Moses Lake’s action seeking recovery for costs incurred between 1989 and 1994 is time-barred, and certain costs incurred by Moses Lake after 1994 were not “necessary” and therefore, are not recoverable. The reason is that Moses Lake has also asserted contribution claims against Lockheed, seeking to have Lockheed pay its equitable share of any response costs for which Moses Lake may be found hable. While it appears Moses Lake has yet to be found liable for any response costs, this may well change with issuance of EPA’s final “remedial action plan” which is intended to address cleanup of the aquifer — the “Site” — as a whole. 1. Additional Facts In November 1957, the U.S. Air Force (“USAF”) completed construction of an 8-place hangar (also referred to as Building 5-820, Building 5820, and Building 8-20) on the Larson Air Force Base (“LAFB”). From approximately August 1960 to September 1962, Lockheed occupied a space in this hangar while acting as prime integrating contractor to the U.S. military for the initial activation of nine Titan 1 Intercontinental Ballistic Missiles (“ICBMs”). This “space” was the Combined Guided Missile Assembly and Technical Supply Facility, also known as the Missile Assembly and Maintenance Shop (“MAMS facility”). ICBM launch complexes (also known as “missile silos” or “silo sites”) were located outside of the LAFB near Warden, Royal City, and Batum, Washington. Support facilities at LAFB and the missile silos outside of LAFB became one of five sites constructed in the United States between the late 1950s and early 1960s to house and support Titan ICBMs, and was referred to as “T-4,” meaning the fourth Titan I facility that was constructed as part of the USAF Titan missile program. In January 1962, Lockheed delivered the first of at least nine Titan I missiles to LAFB. Lockheed returned to LAFB in May 1964 for a six week “Titan I update.” LAFB was eventually deactivated in 1966. The Titan I missile was fueled by a propellant mixture of liquid oxygen (LOX) and RP-1 fuel. Because hyrdocarbon deposits on components are combustible and potentially explosive when exposed to LOX, contractor and military specifications required that Titan I missiles’ RP-1 burning engines, parts, components and all related systems and subsystems be flushed and cleaned with TCE to remove any residual hydrocarbon deposits and vapors. The MAMS facility consisted of LOX pre-cleaning and cleaning facilities (also known as the hydro-pneumatic and propulsion shops), electrical shops, and a warehouse. The Lockheed layout entitled “Shop-Missile Assembly and Maintenance Layout, T-4, Squadron V,” specified that eight degreasers, one vapor degreaser, and one vent hood for a vapor degreaser were located in the hyrdo-pneumatie shop, and also specified that a decontaminating unit was located in the propulsion shop. The bill of materials specified in the Lockheed layout included the general layout of the MAMS facility, which included degreasers, and indicated that the materials listed were those that Lockheed installed in the hydro-pneumatic shop. The Lockheed schematic entitled “Equipment Installation — Shop, Missile Assembly and Maintenance Layout T-4, Squadron V (Layout Plan)” showed another version of the bill of materials which included a vapor degreaser and vapor de-greaser lip vent hood, as well as two trich-lor tanks identified by Lockheed drawing identification numbers. Lockheed designed and manufactured the “trichlor tanks” in the MAMS facility and was responsible for installing the tanks. Lockheed personnel served on committees that oversaw work for the Titan I Missile Program at LAFB and surrounding silo sites, including the Facility Transfer Board and Technical Approval Team. Lockheed develo