Citations
- 578 So. 2d 71
Full opinion text
CALOGERO, Chief Justice.
These are consolidated appeals from two district court decisions arising out of a rate case filed on July 25, 1986 with the Louisiana Public Service Commission by Gulf States Utilities Co. Gulf States sought to obtain rate support for River Bend 1, a $4.4 billion, 940 megawatt nuclear plant completed in 1986. Gulf States owns 70 per cent of the plant, reflecting an investment of $3 billion; the remaining 30 per cent is owned by Cajun Electric Power Cooperative. On December 15, 1987, after lengthy hearings, the Commission issued Order No. U-17282-C, in which it disallowed $1.4 billion of the company’s investment in River Bend upon a finding of imprudence, granted Gulf States a first year rate increase of $63 million, which represented a 12% return on equity, and adopted the framework of a phase-in plan for the remainder of the prudent portion of the investment. Gulf States sought to enjoin the part of the order limiting it to a first year return on equity of 12%. On February 18, 1988, Judge Brown of the 19th judicial district issued a preliminary injunction granting the company a first year rate increase of $92 million, reflecting a rate of return on equity of 14%. From that decision the Commission and the State through the Attorney General have perfected appeals. Gulf States also appealed the Commission’s imprudence disallowance. On October 11, 1989, after six weeks of hearings, Judge Landry, sitting as Judge Ad Hoc of the 19th judicial district court, rendered a decision upholding the Commission’s finding of imprudence, but also ordering the implementation of a “rate base exclusion plan” that would allow Gulf States to obtain revenue support for the imprudent part of its investment. From that decision, the Commission, the State, and the utility have appealed.
As will be evident from the lengthy discussion which follows, the issues presented for our determination in these appeals include: (1) whether Gulf States’ due process rights were violated by the manner in which the Commission conducted the hearing in this case, and the appropriate standard of review to be applied to Public Service Commission Order No. U-17282-C; (2) whether the Commission was unreasonable or arbitrary in finding that Gulf States’ 1979 decision to restart River Bend was imprudent; (3) whether the district court’s decision on the merits which' ordered the implementation of a “rate base exclusion plan” was a proper exercise of that court’s judicial authority; (4) and whether, in the injunction proceeding, the district court acted within its discretion in increasing Gulf States’ first year rate of return on equity from 12% to 14%.
As will also be evident from the following discussion, we find that Gulf States’ due process rights were not violated, and the appropriate standard of review in this case to be that articulated by this Court in numerous previous rate cases: Commission orders will be upheld unless they are arbitrary, capricious, or not reasonably supported by the evidence. We further find the Commission’s disallowance of $1.4 billion of Gulf States’ investment in River Bend as imprudent to be reasonably supported by the extensive record compiled in this case. Regarding the district court’s implementation of a rate base exclusion plan, we find that order to be a preemption of the Commission’s primary authority to set fair and reasonable rates. Once it had affirmed the Commission’s finding of imprudence, it was not within the court’s discretionary powers to ameliorate the effect of that determination. Finally, we find an injunction action in a rate increase case to be an improper proceeding in which to increase the rate of return on equity granted by the Commission, when the court has not found the lower rate to be confiscatory.
FACTS AND PROCEDURAL HISTORY
River Bend was planned in the early 1970s by Gulf States, a Texas corporation providing electrical service to both Louisiana and Texas residents, businesses, and industrial users. Until that time, the company had relied on gas-fired generators to provide an electric power supply to its customers. The company experienced a need for alternate power sources, however, as a result of a variety of factors, including severe natural gas curtailments, a load growth which had averaged approximately 11% annually for the preceding four decades, and new federal regulations. The decision to build River Bend was predicated on three extensive economic studies commissioned by Gulf States. Those studies, performed by Stone & Webster and Bechtel Corp., examined the total costs of producing energy from various types of generators over the lives of the units, and concluded that the nuclear option was economically preferable to the alternatives. That conclusion was supported by then current industry-wide data, internal studies, and publications of the Nuclear Regulatory Commission. The initial estimate of the cost of River Bend, made in 1971, was $307 million. Gulf States continued to evaluate other power sources as well, and by 1975, included both coal and nuclear fuel in its generation plans. In addition, it had begun acquiring lignite reserves in Texas and Louisiana. During this period, the company also entered into negotiations with Cajun Electric in an attempt to sell a portion of the proposed River Bend unit.
The decision to build River Bend was affected, however, by a significant drop in load growth on Gulf States’ system, resulting in part from the Arab oil embargo and the national recession of 1974-1975. In addition, in January 1977, the Louisiana Public Service Commission rejected the company’s application for a $23.8 million rate increase. The decrease in load growth and failure to secure rate relief led Gulf States to suspend the River Bend project in 1977. At that time, construction at the site had not begun, and the utility had invested approximately $350 million in preliminary expenditures. The suspension remained in effect for the next two years.
Gulf States’ load growth rebounded, however, to 12% in 1977 and 10% in 1978. Further, in 1978, Congress passed the Fuel Use Act, which mandated that no new gas-fired or oil generating plants could be built, and prohibited the use of natural gas in existing generating plants after 1989. Faced with a need to replace its gas-fired plants and a projected 5.9% compounded growth rate in service demand, Gulf States reevaluated its options. Studies performed by the company indicated a continued advantage for nuclear generation over coal, and in June 1977, Stone & Webster, River Bend’s contractor, presented an updated cost estimate for the plant of $1.3 billion.
During the spring of 1978, under a new Board Chairman, Gulf States began a program to determine the most advantageous way to accomplish fuel diversification. Management Analysis Co. completed an evaluation of Stone & Webster’s River Bend construction cost estimate, concluding that there was a 90% probability that River Bend would cost $1.7 billion or less, and a 50% probability that the cost would be $1.5 billion. An in-house analysis also calculated the construction cost to be $1.5 billion. In July 1978, Gulf States produced a study concerning the financial impact of various planning alternatives over a ten year period, which indicated that building River Bend, with a concurrent sale of a portion of the unit, was the best economic alternative.
In August 1978, the Board of Directors met to make a decision on River Bend. During that meeting, the Chairman concluded that the company would not be likely to receive rate relief from either the Louisiana or Texas regulators if River Bend were cancelled, and that the shareholders could not absorb $4 million in sunk and cancellation costs, even with the benefit of a 50% tax write-off. Following a discussion of all of its options, the Board concluded that a sale of the unit was one of its best alternatives. Gulf States' management therefore embarked on a national and international marketing effort to sell River Bend, an effort which was to prove unsuccessful. In the meantime, the company decided to evaluate the possibility of changing contractors for the project, and solicited bids from four major engineering/construction firms. The bids were evaluated by company committees and by two outside firms, Management Analysis Co. and NU-TECH. The NUTECH evaluation determined that construction cost estimates were in a range of $1.67 to $1.77 billion, while Management Analysis Co. concluded that there was a 90% probability that the construction cost would be in the range of $1.7 to $1.88 billion. Ultimately Stone & Webster was awarded the contract on a cost-plus basis.
On November 15, 1978, Gulf States filed testimony before the Public Service Commission and presented calculations showing River Bend to be an economical generating alternative to meet the increases in load growth expected during the next decade. The calculations were based on the company’s official estimate of the unit’s cost, $1.3 billion. In late November, the Nuclear Regulatory Commission published the results of a study of nuclear and coal costs that indicated some advantage for nuclear units. In December 1978, the Commission granted the company’s application for rate relief to support its River Bend construction program, based on Gulf States’ projected service demand. A certification order approving the construction had also been sought and received that year from the Texas Public Utility Commission.
In January 1979, Gulf States’ Chairman brought the River Bend project before the Board for a final decision. At that time, the company had an informal agreement with Cajun to sell it 30% of the unit. On February 8, 1979, the Gulf States Board met and approved the restart of the River Bend project. Site work resumed at that time, and the first structural concrete was poured in August 1979. On March 28, 1979, shortly after the decision to restart construction was made, but before significant site work had taken place, an extremely serious nuclear accident occurred at the Three Mile Island nuclear plant in Pennsylvania. A company task force evaluated the impact that the accident was likely to have on River Bend, and 5V2 weeks later issued a report which concluded that the accident’s effect would be minimal because of the dissimilarities between the types of reactors used in the respective plants. In August 1979, Cajun signed a formal agreement to purchase 30% of River Bend. The agreement, however, obligated Gulf States to buy back a decreasing amount of electricity from Cajun’s portion for the first 5 years of River Bend’s operation. In September 1979, the contractor, Stone & Webster, completed a comprehensive study, and predicted that River Bend would cost a total of $1.7 billion.
River Bend went into commercial operation on June 16, 1986, and on July 25, 1986, Gulf States filed an application with the Public Service Commission requesting a rate increase to recover the Louisiana portion of its $3 billion investment in the $4.4 billion plant. On December 15, 1987, after more than 40 days of hearings before a Hearing Examiner, the Commission issued an order finding that the company’s decision to restart the River Bend project in 1979 had been imprudent. Based on its consultants’ estimates of the cost of the alternatives that had been available to Gulf States, the Commission disallowed $1.4 billion of the $3 billion investment and excluded the Louisiana share of that amount (approximately $677 million) from the company’s Louisiana rate base. Further, the Commission granted a first year rate increase of $63 million, which represented a 12% return on the company’s equity, and approved the framework of a phase-in plan for the remaining Louisiana portion of the $1.6 billion investment which had been determined to be prudent.
Pursuant to LSA-R.S. 45:1192, Gulf States sought emergency relief from the order in the 19th judicial district court. On February 18, 1988, Judge William Brown issued an injunction granting the company a first year rate increase of $92 million, representing a 14% return on equity, and implementing a specific phase-in plan for the deferred portion of the prudent River Bend investment. Pursuant to La. Const, art. IV, § 21, that order is being appealed to this Court by the Commission and the Attorney General of Louisiana, who argue that the court erred in increasing the rate of return set by the Commission, and that a preliminary injunction action was not an appropriate proceeding in which to secure such an order.
In addition to seeking emergency injunc-tive relief, Gulf States appealed the Commission’s imprudence disallowance. That appeal was the subject of 6 weeks of hearings before Judge Paul Landry, sitting as Judge Ad Hoc of the 19th judicial district. During that proceeding, Gulf States presented an “inventory plan” for the resolution of the imprudence disallowance. Under the plan, the proportion of the plant’s capacity which is equivalent to the $1.4 billion excluded by the Commission from the rate base would become a deregulated asset. Gulf States would buy, or would sell off-system, energy from this capacity, thereby allowing the utility to obtain revenue support for the imprudent portion of its investment in River Bend. At the conclusion of the hearings, Judge Landry remanded the matter to the Commission for consideration of the new evidence adduced on appeal.
After further hearings, the Commission issued Order No. U-17282-D, reaffirming its imprudence disallowance, but also proposing a settlement offer. The offer included a “rate base exclusion plan,” somewhat similar to the “inventory plan” proposed by Gulf States. The Commission’s plan would guarantee the purchase of energy by Louisiana ratepayers from the excluded portion of the plant at a price of 4.6 cents per kilowatt hour. The offer also required the company to share with its ratepayers any profits earned on off-system sales of energy from the excluded portion of the plant or a sale of the plant itself, and to accept a rate of return of 12.75%. Finally, the offer provided that both parties would drop their respective appeals. The Commission’s order specified that if Gulf States rejected the rate base exclusion plan, the findings and conclusions of its previous order, No. U-17282-C, were to be reinstated. The plan was rejected by Gulf States, and the case returned to the district court for briefing and argument. On October 11, 1989, Judge Landry affirmed the Commission’s finding of imprudence, but also ordered the implementation of the rate base exclusion plan proposed earlier by the Commission. As noted above, Gulf States, the Commission, and the Attorney General have appealed that decision. Gulf States seeks a reversal of the Commission’s finding, affirmed by the district court, that its 1979 decision to restart River Bend was imprudent. Both the Commission and Attorney General appeal that part of the court’s order implementing the rate base exclusion plan. In addition, the Attorney General contends that the dis-allowance for the company’s imprudence should have been even greater than that imposed by the Commission.
Because the issues raised by the appeals of the two district court decisions are distinguishable, we will address them separately, in the following order: No. 90-CA-0445: I. Standard of Review and Due Process (page 9); II. Prudence (page 22); III. Rate Base Exclusion Plan (page 47); and No. 88-CA-0709: IV. Rate of Return on Equity (page 55).
90-CA-0445
I. STANDARD OF REVIEW AND DUE PROCESS
The standard of judicial review of rate-making determinations by the Public Service Commission has been described by this Court on numerous occasions. We have noted that:
While we thus have the power and it is undoubtedly our duty to set aside the rulings of the Commission where we believe them to be clearly wrong on the facts and/or the law, we nevertheless should accord great weight to the rulings of the Commission and should not overturn them in the absence of a clear showing of error. Courts should act slowly in substituting their own views and discretion for those of a body peculiarly constituted to act intelligently in such cases and primarily charged with doing so.
Southern Bell Telephone & Telegraph Co. v. Louisiana Public Serv. Comm’n, 239 La. 175, 118 So.2d 372, 378 (1960). We have also said that the Commission’s orders are presumed valid, Gulf States Utilities Co. v. Louisiana Public Serv. Comm’n, 364 So.2d 1266 (La.1978), and are not to be overturned absent a showing of arbitrariness, capriciousness, or abuse of authority by the Commission. Central La. Elect. Co. v. Louisiana Public Serv. Comm’n, 508 So.2d 1361 (La.1987); South Central Bell Telephone v. Louisiana Public Serv. Comm’n, 352 So.2d 964 (La.1977). Finally, this Court has found that a decision of the Commission will not be overturned absent a finding that it is clearly erroneous or is unsupported by the record. Central La. Electr. Co. v. Louisiana Public Serv. Comm’n, 437 So.2d 278 (La.1983); White v. Louisiana Public Serv. Comm’n, 259 La. 363, 250 So.2d 368 (1971).
Gulf States, however, contends that the traditional standard of review applicable to appeals from Commission rate orders is not appropriate in this case. The company argues that the procedures employed by the Commission deprived Gulf States of its due process rights to a full and fair hearing and a decision based upon the evidence adduced at the hearing. Specifically, the company avers that the Commissioners did not hear any of the testimony or read any of the transcripts of the proceedings, and that the Hearing Examiner who did hear all of the testimony did not prepare any findings or conclusions which could have formed the basis of an independent, unbiased order. The company further maintains that the Commission made no findings at the time the order was issued, but rather, 42 days later, issued a “Majority Opinion” authored by the Commission’s counsel and consultants who had acted as Gulf States’ adversaries during the hearings. The company also contends that the Commission’s counsel and consultant/witnesses inappropriately evaluated the credibility of witnesses and evidence in both the Majority Opinion and the Report of Special Counsel. Finally, Gulf States alleges that the Commission’s consultants were unqualified to give opinions on the varied subjects on which they testified, ignored or were ignorant of evidence favorable to Gulf States, and employed computerized analy-ses that were susceptible to manipulation.
Gulf States concludes that as a result of these procedural deficiencies, the Commission’s Order is not entitled to a presumption of validity, or to the deferential standard of review traditionally accorded its decisions. The utility argues that the correct standard of review is that found in LSA-R.S. 45:1192 and in the Louisiana Administrative Procedure Act, LSA-R.S. 49:964. The former provides that a court “may affirm ... change, modify, alter, or set aside, as justice may require” an order of the Commission. The latter states that the court may reverse or modify an order if, among other grounds, the decision is “made upon unlawful procedure.”
The Commission is constitutionally required to “adopt and enforce reasonable rules, regulations, and procedures necessary for the discharge of its duties.” La. Const. art. 4, § 21(B). Gulf States’ argument that the Commission’s order at issue was the result of unreasonable or “unlawful” procedure rests partly on the contention that the order deprives its shareholders of a property interest in violation of the Fifth and Fourteenth Amendments. The company maintains that a prudence inquiry involves substantial investor property rights, and that a finding of imprudence is tantamount to taking a portion of the plant for public purpose, without compensating the company or its investors. The existence of such a constitutionally protectable property interest triggers a substantive right of due process, which must provide the person whose interests are at stake an effective, efficient, and fair process. Goldberg v. Kelly, 397 U.S. 254, 90 S.Ct. 1011, 25 L.Ed.2d 287 (1970). The greater the substantive rights involved, the more closely the hearings must resemble a trial.
Gulf States also argues that because a prudence determination necessarily entails the application of the “reasonable man” standard to a discrete investment decision in the past, requiring the weighing of relevant facts and circumstances, it most closely resembles a determination of negligence in a tort suit. The inquiry concerns “adjudicative facts,” questions “of who did what, where, when, how, why, with what motive or intent,” which should ordinarily not be decided without providing the parties an opportunity for trial. 1 K. Davis, Administrative Law Treatise, § 7.02 at 413 (1958). Thus in a prudence case, the utility contends, ratemaking loses its legislative nature and becomes a judicial function. In administrative law terms, the Commission’s order is one of particular, rather than general applicability, and thus constitutes adjudication, rather than rulemaking. Gulf States asserts that it is is therefore entitled to the trial-like process required in an adjudicative proceeding, citing Londoner v. Denver, 210 U.S. 373, 28 S.Ct. 708, 52 L.Ed. 1103 (1908) and Bi-Metallic Co. v. Colorado, 239 U.S. 441, 36 S.Ct. 141, 60 L.Ed. 372 (1915).
We first address the argument that under administrative law principles, Gulf States was entitled to a hearing closely resembling a trial. It is true, of course, that ratemaking is often particular in its application, in that the regulatory authority must determine what rates a specific utility may charge, based on factors which are unique to that utility. However, the predominant weight of opinion views the rate-making process as legislative, because it looks to the future and changes existing conditions by making a new rule that prescribes future patterns of conduct. The theory that rulemaking may be distinguished from adjudication on the basis of its future effect was first articulated by Justice Holmes in Prentis v. Atlantic Coast Line Co., 211 U.S. 210, 226-27, 29 S.Ct. 67, 69, 53 L.Ed. 150 (1908):
[The proper characterization of an agency’s actions] depends not upon the character of the body but upon the character of the proceedings.... And it does not matter what inquiries may have been made as a preliminary to the legislative act. Most legislation is preceded by hearings and investigations. But the effect of the inquiry, and of the decision upon it, is determined by the nature of the act to which the inquiry and decision lead up.... The nature of the final act determines the nature of the previous inquiry. As the judge is bound to declare the law he must know or discover the facts that establish the law. So when the final act is legislative the decision which induces it cannot be judicial in the practical sense, although the questions considered might be the same that would arise in the trial of a case.
The U.S. Supreme Court has reaffirmed the Prentis mode of analysis, see District of Columbia Court of Appeals v. Feldman, 460 U.S. 462, 476-79, 103 S.Ct. 1303, 1311-13, 75 L.Ed.2d 206 (1983), and its conclusion that ratemaking is essentially a legislative function. See United States v. Jones, 336 U.S. 641, 652, 69 S.Ct. 787, 793, 93 L.Ed. 938 (1949); Colorado Interstate Gas Co. v. FPC, 324 U.S. 581, 589, 65 S.Ct. 829, 833, 89 L.Ed. 1206 (1945). In the recent case of New Orleans Public Service v. New Orleans, 491 U.S. 350, 109 S.Ct. 2506, 105 L.Ed.2d 298 (1989), the Court again reaffirmed the legislative nature of ratemak-ing. The Court found that the proceedings at issue, in which the New Orleans City Council determined that certain costs incurred by NOPSI in relation to Grand Gulf I nuclear plant could not be reimbursed through a rate increase, “were not judicial in nature.” Id. 109 S.Ct. at 2519. See also American Telephone & Telegraph Co. v. Federal Communications Comm’n, 602 F.2d 401, 410 n. 48 (D.C.Cir.1979); Wilson & Co. v. United States, 335 F.2d 788, 797 (7th Cir.1964).
This Court has also confirmed the legislative nature of ratemaking, even in cases involving the rates of particular utilities. In the early case of McNeely v. Town of Vidalia, 157 La. 338, 102 So. 422 (1924), the Court reasoned that
since public utilities are for all practical purposes public necessities, and virtual monopolies, it follows that the rates fixed for such necessities are in effect a tax upon the public for such public service.... The fixing of such rates is therefore essentially a legislative function....”
Id. 102 So. at 423 (emphasis in original). That conclusion has often been reiterated by the Court. See, e.g., Louisiana Power & Light Co. v. Louisiana Public Service Comm’n, 523 So.2d 850 (La.1988); South Central Bell Telephone Co. v. Louisiana Public Service Comm’n, 373 So.2d 478 (La. 1979); South Central Bell Telephone Co. v. Louisiana Public Service Comm’n, 352 So.2d 964 (La.1977).
Despite the legislative nature of rate-making, however, it is also true that a prudence inquiry involves “adjudicative facts,” which apply to and affect Gulf States specifically. The nature of the inquiry thus makes it appropriate for the Commission to hold an evidentiary hearing before making a determination of such significance to the company and its investors. See Patagonia Corp. v. Board of Governors of the Federal Reserve System, 517 F.2d 803 (9th Cir.1975); Appalachian Power Co. v. EPA, 477 F.2d 495 (4th Cir.1973); Schwartz, Administrative Law 204. Further, we agree with the company’s assertion that the property interest at stake is one to which due process concerns protected by the federal and state constitutions attach, see Duquesne Light Co. v. Barasch, 488 U.S. 299, 109 S.Ct. 609, 102 L.Ed.2d 646 (1989); South Central Bell Telephone Co. v. Louisiana Public Service Comm’n, 373 So.2d 478 (La.1979), and that the company is entitled to a hearing before being deprived of that interest. The issue thus becomes whether the kind of hearing provided by the Commission in this case violated Gulf States’ due process rights. The U.S. Supreme Court has established a three part balancing test to determine what safeguards are necessary when a constitutionally protectable liberty or property interest is at stake. A reviewing court must weigh the interests of the affected individual, the risk of erroneous decision making based on the procedures used, and the government’s interest in efficient resolution of the issues. Mathews v. Eldridge, 424 U.S. 319, 96 S.Ct. 893, 47 L.Ed.2d 18 (1976).
In this instance, in accordance with the Commission’s normal procedure in rate cases, hearings were conducted before a Hearing Examiner rather than the Commission members themselves, although Commissioner Louis Lambert also had himself appointed as an Examiner and, along with the administrative aides of other Commissioners, attended many hearing sessions. The Commission engaged two firms of attorneys to represent it at the hearings, and later hired a third firm as lead counsel. It also employed as experts a utility consulting firm, a nuclear specialist, and an engineering firm with extensive experience in nuclear prudence cases. During 40 days of hearings, approximately 53 witnesses were called and cross-examined concerning their live as well as prefiled depositions and statements. Several thousand pages of transcript were compiled, and several hundred exhibits entered into evidence. At the end of the hearings a Report of Special Counsel, principally written by the Commission’s consultants and special counsel, was presented to the Commission. The Report contained summaries of witnesses’ testimony and recommendations as to the disposition of the prudence issue. Following submission of the Report, Gulf States sought and was granted the opportunity to argue the matter, and a full day hearing was conducted before the Commission. Finally, 42 days after the Commission adopted Order No. U-17272-C, it issued a Majority Opinion, the content of which relied heavily on the Report of Special Counsel.
Gulf States contends that this process was fatally flawed because the Commissioners did not hear the testimony, either in person or through a report of the Hearing Examiner, and because the decision process was delegated to adversarial witnesses who prepared the Commission’s Order based on their own evaluations of opposing witnesses’ testimony. However, as the district court noted, the cases cited by the company in support of its contention that the procedure employed by the Commission was not sufficiently “trial-like” are distinguishable from the present case.
In Ohio Bell Telegraph Co. v. Public Utilities Comm’n, 301 U.S. 292, 57 S.Ct. 724, 81 L.Ed. 1093 (1937), on which Gulf States heavily relies, the Commission was called upon to value a telephone company’s property in order to decide what amount to include in the company’s rate base. Despite the submission of extensive evidence concerning the value of the property, the Commission determined its value by reference to certain journals and tax lists which it did not identify and which were not introduced into evidence. When the company sought the disclosure of the documents relied upon by the Commission, and an opportunity to rebut them, it was refused. The Court held, therefore, that the proceeding did not provide the fair hearing essential to due process.
In Morgan v. United States, 298 U.S. 468, 56 S.Ct. 906, 80 L.Ed. 1288 (1936), unlike the case at issue, the Secretary was required by statute to hold a “full hearing” before issuing rate orders. Although hearings were held before an examiner, the Secretary issued an order without having heard or read any of the evidence, and without having considered the briefs submitted by the plaintiff. The Court held that if “the one who determines the facts which underlie the order has not considered evidence or argument, it is obvious that the hearing [mandated by statute] has not been given.” Id. at 480-81, 56 S.Ct. at 911.
In Goldberg v. Kelly, 397 U.S. 254, 90 S.Ct. 1011, 25 L.Ed.2d 287 (1970), the issue before the Court was whether a state could terminate welfare payments without affording the recipient an opportunity for an evidentiary hearing prior to termination. The Court concluded that the stakes for the recipient were too high and the possibility for error too great' to allow termination without giving the recipient a chance to be fully informed of the case against him and the opportunity to contest its basis and to produce evidence in rebuttal.
In Patagonia Corp. v. Board of Governors of the Federal Reserve System, 517 F.2d 803 (9th Cir.1975), the court found that when there are contested questions of adjudicative fact, the party which may be adversely affected is normally granted a hearing in which that party has “the opportunity to confront witnesses and to hear and contest the evidence against him.” Id. at 816.
In KFC National Management Corp. v. N.L.R.B., 497 F.2d 298 (2d Cir.1974), the N.L.R.B. regional director had made an ex parte investigation into the plaintiff’s allegation of an unfair labor practice, and had concluded that it had no merit. When the plaintiff then petitioned the Board for review, its petition was denied by the vote of a three member panel, two members of which had never considered the case but had given their assistants general authorization to vote in their places. The Second Circuit held that this complete delegation of the Board’s statutory duty to decide the case constituted a “prima facie” demonstration of impropriety and allowed the court to inquire into the administrative process to insure that the decision-making was informed, unbiased, and personal.
In Carolina Power & Light Co. v. FERC, 716 F.2d 52 (D.C.Cir.1983), the Commission had issued an order refusing to allow the utility to pass along permanent disposal costs of spent nuclear fuel on the basis that reprocessing was a reasonably forseeable possibility. When the company petitioned for a rehearing to rebut the Commission’s finding concerning the availability of reprocessing, FERC denied the application, stating only that the petition presented no matters of law or fact which it had not previously considered. The court held that the Commission had failed to set forth a clear presentation of its reasoning, making it impossible for the court to intelligently perform its reviewing function.
In this case, Gulf States clearly was provided an evidentiary hearing in which it had a full opportunity to learn the extent of the case against it and the basis for that case, to present witnesses and introduce documents in support of its position, and to cross-examine Commission witnesses. Nor was there an abdication by the Commission of its decision-making duties of the sort condemned by the court in KFC National Management Corp. v. N.L.R.B., supra. Although the Commissioners did not personally hear all of the testimony, Commissioner Louis Lambert and representatives of the other Commissioners frequently attended the hearings. In addition, the Commissioners were provided with summaries of testimony which had been submitted previously to Gulf States for its review and approval of content. The company made no objection at that time to the use or the accuracy of the summaries. Further, although Gulf States now complains that the Commissioners neither heard all of the testimony nor read the transcript, it has not, in brief or oral argument, alleged to the district court or to this Court that the summaries were biased or misleading. Nor surely, given the volume of prefiled testimony, exhibits, and hearing transcript (the transcript alone numbered over 7,000 pages), could the company assert that the summaries were not helpful to the Commissioners in comprehending the complex, technical issues involved in the prudence inquiry.
Commission members also granted private audiences to company representatives, meetings which would clearly have been inappropriate in an adjudicative proceeding. Finally, in a departure from its usual procedure, following the submission of the report of special counsel, Gulf States was allowed to file exceptions to the report, and was granted a full day hearing before the full Commission to argue its case.
As Gulf States acknowledges, the Commission is permitted to delegate the hearing of oral testimony to an examiner, and the “sifting and analyzing” of the evidence to “competent subordinates.” Morgan v. United States, 298 U.S. 468, 56 S.Ct. 906, 80 L.Ed. 1288 (1936). The company complains, however, that the Hearing Examiner, the one person who did hear all of the evidence in the case, failed to prepare a report on his findings of fact. The Supreme Court has held that such a report is not essential to the validity of a hearing. Id. at 478, 56 S.Ct. at 910; see also N.L.R.B. v. MacKay Co., 304 U.S. 333, 58 S.Ct. 904, 82 L.Ed. 1381 (1938). Gulf States also contends that it was denied due process on the basis that the Commission’s Majority Opinion, which was not issued until 42 days after the Order, was authored by the Commission’s consultants and counsel who had acted as the company’s adversaries during the hearings. The Commission is statutorily permitted to retain special counsel, engineers, consultants, etc. to assist its economics and rate analysis division in “evaluating, reviewing, and representing the commission in matters affecting services and rates charged by public utilities to Louisiana consumers or the judicial review thereof.” LSA-R.S. 45:1163.3. The company’s contention that a violation of due process occurs when such staff members take an adversarial stance in hearings and then advise the Commission regarding its decision has been rejected by the federal courts.
In Wilson & Co. v. United States, 335 F.2d 788, 796 (7th Cir.1964), the court stated that
We hold that it was proper for members of the Commission’s Common Carrier Bureau who were counsel of record in the hearing before the Commission to participate in the decisional process that led to the orders under review; and that this conduct did not violate section 3(a) of the Administrative Procedure Act, ... the Commission’s own rules, as well as constitutional due process.
In American Telephone & Telegraph, 449 F.2d 439 (D.C.Cir.1979), the court observed that
The case law generally rejects the proposition that the combination of judicial and adversary functions is a denial of due process. This seems to be particularly true where the proceeding is rule making or rate making.
The Administrative Procedure Act is consistent with the jurisprudence on this issue. The Act specifically exempts proceedings involving rates of public utilities from the separation of functions requirement imposed on adjudicatory proceedings. See 5 U.S.C. § 554(d); see also Seacoast Anti-Pollution League v. Costle, 572 F.2d 872 (1st Cir.1978) (“The decision ultimately reached is no less the Administrators (sic) simply because agency experts helped him to reach it.”); 2 K. Davis, Administrative Law Treatise 84 (1958) (“The strength [of the administrative process] lies in staff work organized in such a way that the appropriate specialization is brought to bear upon each aspect of a single decision, the synthesis being provided by the men at the top.”).
• Further, it is standard agency practice for staff members to prepare the opinions adopted by the agency. While this practice has been the subject of criticism, it has been defended as necessitated by heavy administrative work loads. As one often cited scholar has observed,
The objection to the separation of deciding from opinion writing may be unanswerable except in terms of inevitability. No one has yet conceived a system which will dispose of the quantity of adjudication, without an undue diversity of results, and will at the same time permit the deciding officers to write their own opinions.... The best solution of the Board’s problem is probably the one the Board has worked out — the use of assistants.
K. Davis, Administrative Law 239 (1972).
Nor has Gulf States made a persuasive showing that it has been disadvantaged because the Commission’s Majority Opinion was not issued simultaneously with its Order. The purpose underlying the requirement that an agency must provide a statement of findings as to disputed issues and reasons for its determination is “to enable a reviewing court to determine with some measure of confidence whether or not the ratemaking authority, which still remains in the Commission, has been exercised in a manner which is not arbitrary, capricious or unreasonable.” Central Louisiana Electric Co. v. Louisiana Public Service Comm’n, 437 So.2d 278, 279 (La.1983).
The case cited by Gulf States to support its contention that the combination of pros-ecutorial and fact-finding functions in one person violates due process, Allen v. Louisiana State Board of Dentistry, 543 So.2d 908 (La.1989), is not comparable to a rate-making proceeding. Allen involved the adjudication provisions of the Louisiana Administrative Procedure Act, not applicable here, and concerned a quasi-criminal prosecution which resulted in the plaintiff’s suspension from the practice of dentistry. Further, the plaintiff was given no notice of the ex parte participation of the prosecutor in the drafting of the Board’s formal findings of fact and conclusions, and no opportunity to object to the findings and conclusions prior to their adoption by the Board. The Court also found that the Board adopted the prosecutor’s draft verbatim, after a minimal review. In contrast, the Commission’s Majority Opinion in the present case was not the "secret product of an advocate,” as the court found in Allen. Gulf States had full knowledge of the participation of counsel and consultants in the drafting of the Special Report of Counsel, and. was granted a full day of hearing to rebut its findings and conclusions before the Commission issued its order.
The U.S. Supreme Court set the permissible limits of judicial review of administrative decision making in the four Morgan cases. In the second of those cases, Morgan v. United States, 304 U.S. 1, 18, 58 S.Ct. 773, 776, 82 L.Ed. 1129 (1938), the Court held that it was “not the function of the court to probe the mental processes of the Secretary” of Agriculture. Id. at 18, 58 S.Ct. at 776. In the fourth case, United States v. Morgan, 313 U.S. 409, 61 S.Ct. 999, 85 L.Ed. 1429 (1941), the Court compared the administrative process to a judicial proceeding, and held that inquiry into the process by which either the judge or administrator reached his conclusions would be destructive of the decision maker’s responsibility.
The Second Circuit of Appeals has observed that
what emerges from the Morgan quartet is the principle that those legally responsible for a decision must in fact make it, but that their method of doing so—their thought processes, their reliance on their staffs—is largely beyond judicial scrutiny.
KFC National Management Corp. v. N.L.R.B., 497 F.2d 298, 304 (2d Cir.1974); see also N.L.R.B. v. Baldwin Locomotive Works, 128 F.2d 39, 47 (3d Cir.1942) (“[W]e may not tell the Board that it must ‘hear’ in some one particular manner so long as it does ‘hear,’ i.e., consider the evidence and argument.”).
We find that the Commissioners did indeed “hear” and decide this case in accordance with their constitutional and statutory duty and with the due process requirements of an administrative hearing. Judicial inquiry into the methods by which they arrived at a decision is therefore at an end.
Having concluded that Gulf States’ due process rights were not violated by the Commission’s procedures, we turn to the standard of review to be applied to the issues remaining before us. The district court, noting that this Court has described the standard in a variety of ways, relied upon the standard articulated in the recent case of CTS Enterprises v. Louisiana Public Service Comm’n, 540 So.2d 275 (La.1989): “a court will not upset the agency’s finding unless it is based on an error of law or is one which the Commission could not have found reasonably from the evidence.” Id. at 278. Although the Court in that case specified that the quoted standard applied in a common carrier setting, it is similar to our previous descriptions, cited above, of the standard to be applied in ratemaking cases. See, e.g., Louisiana Power & Light v. Louisiana Public Service Comm’n, 523 So.2d 850 (La.1988) (the inquiry is “whether the commission acted unreasonably or arbitrarily in setting rates for the utility”); Central Louisiana Electric Co. v. Louisiana Public Service Comm’n, 437 So.2d 278 (La.1983) (order will be upheld unless shown to be “arbitrary, capricious, abusive of its authority, clearly erroneous or unsupported by evidence”).
We therefore apply the standard that Commission orders are to be upheld unless they are arbitrarily or capriciously rendered, or are not reasonably supported by the evidence.
II. PRUDENCE
Article 4, § 21 of the Louisiana Constitution grants the Public Service Commission the authority to regulate “all common carriers and public utilities” in the state. In the exercise of this authority, the Commission is charged with setting reasonable and just rules, regulations and orders. LSA-R.S. 45:1167. In order to carry out its constitutional and legislative mandates, the Commission is required to determine how much of a utility company’s investment should be included in its rate base, ultimately to be borne by the ratepayers. In doing so, it must balance the interest of the ratepayers in the lowest possible rates, against that of the utility and its investors, who understandably desire the highest possible rates. Morehouse National Gas Co. v. Louisiana Public Service Comm’n, 245 La. 983, 162 So.2d 334 (1964). Although there is no single formulation sufficient to express constitutional, statutory, or judicially derived standards for determining how much of a utility’s investment in a particular plant should be included within its rate base, see Federal Power Comm’n v. Hope Natural Gas Co., 320 U.S. 591, 64 S.Ct. 281, 88 L.Ed. 333 (1944), one of the principles used by ratemaking bodies and courts to make such a determination is the prudent investment standard. That standard “essentially applies an analog of the common law negligence standard for determining whether to exclude value from rate base.” Appeal of Conservation Law Foundation, 127 N.H. 606, 507 A.2d 652, 673 (1986). That is, the utility must demonstrate that it “went through a reasonable decision making process to arrive at a course of action and, given the facts as they were or should have been known at the time, responded in a reasonable manner.” Re Cambridge Electric Light Co., 86 P.U.R.4th 574 (Mass.D.P.U.1987).
Further, under the prudent investment rule, a utility is compensated for all prudent investments at their cost when made, irrespective of whether they are deemed necessary or beneficial in hindsight. Duquesne Light Co. v. Barasch, 488 U.S. 299, 109 S.Ct. 609, 102 L.Ed.2d 646 (1989). That is, the focus in a prudence inquiry is not whether a decision produced a favorable or unfavorable result, but rather, whether the process leading to the decision was a logical one, and whether the utility company reasonably relied on information and planning techniques known or knowable at the time. Metzenbaum v. Columbia Gas Transmission Corp., Opinion No. 25, 4 FERC 161,277. Although a prudence review is necessarily retrospective in that it involves an examination of past circumstances, past information available, and past decisions, these factors may not be evaluated in light of subsequent knowledge. Finally, the inquiry encompasses a public utility’s continuation of an investment as well as its decision to enter into that investment, see Re Central Vermont Public Service Corp., 83 P.U.R.4th 532 (Vt. Pub.Serv.Bd.1987), and requires the utility to respond prudently to changing circumstances or new challenges that arise as a project progresses. In Re Long Island Lighting Co., 71 P.U.R.4th 262 (N.Y.Pub.Serv.Comm'n, 1985).
Burden of Proof
Capital and other expenditures reflected in utilities’ pro forma requests for rate increases are generally accepted by the Commission as appropriate and necessary, and therefore recoverable, expenses. In that sense, a utility’s investments are presumed to be prudent and allowable. When, however, the Commission raises serious doubt about the prudence of a particular investment, a searching inquiry becomes necessary, and at that point, the burden shifts to the utility to prove that the expenditure was in fact necessary and appropriate, or resulted in no additional costs. See Union Electric Co., 40 F.E.R.C. 61,046 (FERC 1987); Long Island Lighting Co. v. Public Serv. Comm’n of New York, 134 A.D.2d 135, 523 N.Y.S.2d 615 (3d Dept. 1987); Re Central Vermont Pub. Serv. Comm’n Corp., 83 P.U.R.4th 532 (Vt.P.S. B.1987).
A. Public Service Commission’s Position On Prudence
1. Load Forecasting and its Bearing on Prudence
In order to determine whether Gulf States’ decision to restart River Bend in 1979 was reasonable, given the analytical tools and information available at the time, Kennedy & Associates, outside consultants employed by the Commission, performed an analysis of the planning process which led to the decision. Because a major thrust of Gulf States’ argument is that at the time of the decision it was faced with an overwhelming need for new generation sources, Stephen Baron of Kennedy & Associates first examined the company’s load forecasting techniques to determine whether its forecasts, which were clearly too high in retrospect, were reasonable when made. He concluded that the techniques were inadequate, and led Gulf States to overestimate its need for generating capacity. More specifically, he found that the company’s forecasting methods, which had produced consistently inaccurate load growth estimates even in one year forecasts, failed to adequately reflect the impact of price changes on the use of electricity. At a time when most utilities were using more sophisticated econometric models to measure the impact of economic factors on demand, Gulf States continued to rely on its traditional trending analyses, which were based on prior demand, and on interviews with large industrial customers.
In the summer of 1978, the company prepared a special peak demand forecast that assumed a peak annual demand growth of approximately 5.9%. However, the forecast ran only until 1984, a year prior to the projected commercial operation of River Bend. Estimates for subsequent years were projected by calculating the growth rate for the last years of the six year period and assuming that that rate would continue. According to Baron, this forecasting technique ignored price elasticity effects and made the unreasonable assumption that growth from existing customers would continue indefinitely. The Commission notes that the significance of price elasticity effects should have been apparent to the company because a corporate model run by Gulf States in 1979 predicted that from 1978 on, electricity prices would rise 5.99% annually, an increase substantially greater than the 1.5% rate of increase historically experienced by the company. The Commission also maintains that the inadequacy of the company’s load growth forecasting techniques was acknowledged by the former president of Gulf States, Norman Lee, who testified that a consultant was brought in on an unofficial basis in 1978 “to teach us how to do it.” Further, in 1979, a specially created company task force reported that Gulf States was the only utility studied which relied on trending and judgmental techniques to forecast load, and recommended a complete reevaluation of its forecasting process.
In addition, the Commission notes that many of the events relied upon by Gulf States to explain why it was facing an overwhelming and urgent need for greatly expanded generation at the time of the restart decision had occurred prior to the decision to suspend the project in 1977. Further, it strenuously argues that the company’s contention that River Bend was critical to its ability to meet future service demand is contradicted by Gulf States’ decision in August 1978 to sell the unit. At the time of that decision, the company was aware of the provisions of the Industrial Fuel Use Act, and of the unexpected jump in its load growth in 1977 and 1978. Yet, the Commission emphasizes, Gulf States undertook an extensive national and international marketing effort to sell River Bend, an effort which indicated that the company believed that it could better meet its load growth with other alternatives.
2. Generation Alternatives: Gulf States’ Economic Studies
The consultants also reviewed Gulf States’ analysis of alternatives to River Bend at the time of the restart decision. They found that virtually no analysis was made of the economic consequences of the options available in 1979, particularly in comparison to the thorough economic studies performed or commissioned by the company prior to the original decision to build River Bend. The earlier studies had compared the costs of the various alternatives over the life of the plants, including capital, operations, and fuel costs, and had concluded that the total cost of nuclear energy would be less than either coal or oil. In contrast, the consultants found that Gulf States performed no site-specific economic studies after 1974. The Commission argues that the major studies relied upon by the company are of construction costs, rather than of the cost of producing electricity over the life of River Bend compared to other generating alternatives.
The Commission dismisses studies conducted in 1976, 1977, and 1978 alleged by Gulf States to have “reaffirmed that the nuclear option was the most economic.” It notes that the 1976 study consists of four pages, two of which contain computations, and the other two of which chart the results of those computations. The Commission argues that the study does not relate specifically to River Bend, and uses a nuclear capital cost of $858 per kilowatt, which implies that a unit the size of River Bend could be built for $806 million — more than $100 million less than the company's estimate for River Bend in September 1975, and nearly $1 billion less than its estimated cost in late 1978. The Commission describes the 1977 study as consisting of one page containing a list of numbers presumably designed to show mills per kilowatt hour for River Bend and for the Nelson coal units. It asserts that Gulf States has never provided a basis for determining the assumptions used to develop those numbers. The Commission further contends that the 1978 study, termed the “Restart Study” by Gulf States, was not an economic study, but rather an analysis of the financial impact of various planning alternatives. It argues that because the study covered only a ten year period, it obviously cannot be construed as an economic study of the life-cycle costs of River Bend, which had an estimated life of forty years, or of that of its alternatives.
Regarding the Federal Power Commission’s 1978 study entitled “Nuclear vs. Coal Cost Comparison,” the Commission argues that it is a backward-looking analysis of costs of plants already on line in 1975, and that the majority of the nuclear plants reviewed cost less than $100 million. Again, the study did not address the economics of River Bend or an alternative to that unit. The Commission further contends that Gulf States’ reliance on a Nuclear Regulatory Commission study issued in December 1978 is undermined by the testimony of Norman Lee, the president of the company at the time of the restart decision, who acknowledged that he did not show the study to the Board, and knew that the capital cost assumptions reflected in it were well below the estimated cost of River Bend in 1979. The Commission also argues that the company’s claim that this study reflected a consensus view in the industry on the economics of nuclear versus coal is contradicted by the fact that the nuclear industry cancelled more units than it started in 1977, 1978, and 1979. In 1978, there were thirteen cancellations and one start. In 1979, there were eight cancellations and one start — River Bend, the last nuclear plant to be started anywhere in the country.
Finally, the Commission addresses testimony by company representatives that numerous comparative studies were performed during the period at issue. The Commission notes that on November 15, 1978, James Derr, a Gulf States planner, filed testimony before the Commission to show that River Bend would be economical. The comparative cost calculations were shown on one page of paper, which Mr. Lee later testified was typical of the many studies allegedly performed by Derr and other executives, and which he characterized as “back-of envelope” studies. The Commission argues that the Derr analysis, although it purported to be based on the total cost of River Bend, listed a cost per kilowatt of $1,400, or about $1.3 billion for the unit. Mr. Lee testified that in November of 1978, Gulf States knew that River Bend would cost about $1,800 per kilowatt, but that it was necessary to use the “official” estimate of the project’s cost before the Commission. The Commission concludes that the company was aware that cost studies employing accurate estimates would not support the nuclear alternative.
The Commission contends that other documents reveal that the restart decision was motivated by Gulf States’ desire to avoid a large write-off rather than by concern for the economic consequences to its ratepayers. The company’s top management met on August 1, 1978 to discuss “the most serious problem facing the company — what to do about River Bend I.” The minutes of that meeting disclose that there was an extensive discussion of the effects of can-celling the unit. Following this discussion, the Chairman, W. Donham Crawford, ruled out a write-off of the investment in River Bend, and concluded that the company was left with one option, “and that option is to build it.” The Commission argues that, given the magnitude and the risk of the project that it was contemplating, Gulf States’ failure to make any attempt to ascertain the Commission’s position on a possible River Bend cancellation, and the company’s cursory assumption that it would receive no rate relief for recovery of sunk costs if the unit was cancelled, were unreasonable. It notes, for example, that in 1978 or early 1979, Gulf States was allowed recovery and a return on its amortized investment in the cancelled Blue Hill coal units, as well as a return on the unam-ortized balance on those units. The Commission further contends that the company’s decision to build the unit only if it could not be sold clearly was designed solély to preserve the value of the asset, and not to provide least cost energy. The Commission cites the company’s selection of the option to sell as its first choice as evidence that Gulf States’ management did not really believe nuclear to be the most economical alternative.
3. Generation Alternatives: Commission’s Economic Studies
The Commission’s consultants testified that although they had found the decision to restart River Bend to be imprudent, it was still necessary to determine whether there should be an imprudence disallowance, since even an imprudent planning process could lead to a beneficial economic result through fortuitous circumstances. Kennedy & Associates therefore analyzed what generation choice the company should have made, based on circumstances existing at the time, and whether that choice would have been beneficial compared to River Bend. An economic analyst employed by the firm, Randall Falkenberg, determined that one alternative had been a lignite plant, which Gulf States’ expansion plans showed could be completed within the same time frame as River Bend. He thus performed a study comparing the option of completing River Bend against cancelling the unit and replacing it with a lignite plant. Employing least cost techniques and a computer model assertedly used by utilities during the relevant period, Mr. Falkenberg compared these alternatives over a range of variables and assumptions. He concluded that lignite had an economic advantage over nuclear of approximately $60 million a year, or more than $2 billion in total.
In order to calculate the damages resulting from the company’s restart decision, Kennedy & Associates determined the cost of a lignite unit the size of Gulf States’ share of River Bend, to which they added the sunk and cancellation costs associated with River Bend, the cost of additional transmission facilities for a lignite unit, and the loss of tax benefits associated with the nuclear unit. As a result of these calculations, they recommended that $1.4 billion of Gulf States’ $3 billion investment in River Bend be disallowed from the rate base as imprudent. That figure did not include the cost of the company’s obligation to purchase electricity from Cajun’s portion of the unit for five years or certain accounting order deferrals granted to Gulf States by the Commission in December 1986. Dr. Kennedy testified that had those costs been included, the total disallowance would have been as high as $2 billion.
Another consultant hired by the Commission, Charles Komanoff, also performed an analysis of the restart decision. He determined that Gulf States’ management should have decided to build a coal-fired unit in 1979, particularly in light of the accident at the Three Mile Island Nuclear Plant in March of that year. The